Shielding of Route Goward Status – 25 June 2013

Shielding of Route Goward Status – 25 June 2013. Main works of Route Goward will be completed end of June 2013 (1st layer blacktop on june 28th) Finishing works : Metalworks – in july 2013 2 nd layer of blacktop and parking – after Septum 16 works.

elia
Télécharger la présentation

Shielding of Route Goward Status – 25 June 2013

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Shielding of Route Goward Status – 25 June 2013 • Main works of Route Gowardwillbecompleted end of June 2013 (1st layer blacktop on june 28th) • Finishingworks: • Metalworks – in july 2013 • 2nd layer of blacktop and parking – after Septum 16 works

  2. Somepictures of the works: Temporary road Pilingworks Retainingwall

  3. Formwork for the slab Biocofra Slabreinforcement

  4. Backfilling Concreting Road works

  5. Shielding of Septum 16 Status – 25 June 2013 • Adjudication of the works on 19 June 2013 • June-July 2013 - Preparatoryworks • « Sondages » • Felling of trees • Removal of the barrierclosingaccess to the PS • Removal of the streetlighting • Setting out of the works • Worksite installation • Information campaign for users and TSO • July 2013 – Earthworks • September 2013 - Pilingworks

  6. «Sondages»

  7. Worksite installations: Parking route Goward sharedwith CV Concretebatching plant (to beconfirmed) Temporaryspoil dump «Passage pieton» closed Access to building 561 (RP)

  8. Expected in July 2013! Provisional Schedule

  9. Thankyou for your attention Any questions?