FAA’s Implementation Plans for Satellite Navigation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FAA’s Implementation Plansfor Satellite Navigation Briefed By: Kanwaljit S. Sandhoo (MITRE/CAASD) 8th European CGSIC/IISC Meeting, Prague December 2-3, 1999

  2. Overview • Background • SATNAV Program Objectives • Wide Area Augmentation System (WAAS) • Local Area Augmentation System (LAAS) • Summary

  3. Available to All Nations, Free of Direct User Charges Basic GPS Civil Aviation Benefits • Improves Aviation System Safety • Available for Primary Use in the Oceanic Phase of Flight • Available for Supplemental Use for En Route, Terminal, and Non-Precision Phases of Flight • Cost Effective Resource for Nations with Limited Air Navigation Infrastructures • Primary Means Use of GPS can Reduce or Eliminate Maintenance Costs Associated with Older Expensive Ground-based Navigation Aids

  4. Current Navigation Deficiencies • Large Separation Standard Requirements • Lack of accurate Aircraft Position/Navigation Data • Inability to Provide Optimum Routings to all Users • Absence of Instrument Approaches at Qualified Runways • Restrictive Departure Procedures in Poor Visibility • Limited Automated Aircraft Surface Navigation

  5. Basic GPS System Limitations • Integrity • Notification Time: 15 Minutes or Greater • Availability • 70% for 24 satellites • 98% for 21 satellites • Accuracy • Sufficient for En Route through Non-Precision Approach • Not Sufficient for Precision Approach Does not satisfy Civil Aviation Requirements for Primary-means Navigation in all Phases of Flight

  6. Satellite Navigation Program Objective

  7. Wide Area Augmentation System (WAAS) • Safer • Increased Capacity • Cost Effective

  8. WAAS Phase I Status • Hardware Installed and Tested • 25 WAAS Reference Stations (WRS) • 2 WAAS Master Stations (WMS) • Communications Installed and Operational • 2 INMARSAT Satellites (AOR-W and POR) • Terrestrial Communications Network • Software • Software Final Qualification Test Completed • 7 of 8 Design Qualification Tests Completed • Successfully Completed 3 Signal in Space Builds • System Integration Completed

  9. WAAS Phase I Capabilities • Introduces Operational Capability • Non-Precision Approach • Precision approach: WAAS Precision Approach procedures and GPS/WAAS Certified Receivers Will Become Available to the Aviation Community • Increases Quantity of Airfields with Precision approach Capability

  10. WAAS Phase ISchedule • 60 Day Stability Test/DQT 1/30/00 • Contractor Acceptance Inspection 4/25/00 • Joint Resource Council In Service Review (ISR) Decision 6/30/00 • Instrument Approaches Published 9/07/00 • Commissioning (IOC) 9/25/00

  11. WAAS FOCInvestment Analysis • Scope: • Congress Wants SatNav Program to be “Most Cost-Beneficial” • Congress Wants FAA to Conduct Lease vs. Buy of WAAS Satellites • FAA Needs to Re-Baseline WAAS and LAAS Programs • Approach: • Involve Users, Industry, and Government Agencies • Re-Calculate Benefits/Costs Using Conservative Approach • Focus on Risk Reduction Strategies in Determining Recommendations

  12. WAAS FOCInvestment Analysis (Cont’d) • Four Alternatives Developed and Analyzed; Includes Different Levels of Investment in WAAS/LAAS/Navaids • Preferred Alternative Based on Performance, Benefit/Cost (2.4), Risks, and Strategic Considerations • Checkpoints Built to Minimize Risk and Allow Alternate Paths • Navaids Reduced 2008-2013 to Basic Backup Network • 4 GEO Satellites to be Acquired Between 2002 and 2008 • Precision Approach Throughout CONUS • Capable of Being the Only Navigation System in an Aircraft • Final Operating Capability (FOC) FY2006 • Capable of Being the Only Navigation Service Provided by the FAA

  13. Local Area Augmentation System (LAAS) L1 - 1575.42 MHz

  14. LAASAcquisition Schedule 99 01 03 05 07 09 11 Assumed by FAA for Maintenance/Liability 18 CAT I Part 171 CAT I Acquisition 20 20 20 7 7 8 8 8 8 (Total of 124 CAT I) CAT III FSD R&D CAT III Conversion from CAT I (Converts78 CAT I to CAT III) 26 26 26 CAT III New Procurement 12 12 12 (Total 0f 114 CAT III) SUMMARY: 160 Total LAAS - 46 CAT I - 114 CAT III (78 CAT I Conversion + 36 New Procurement)

  15. Summary • On September 2, 1999, the FAA JRC Reinforced the FAA’s Commitment to Satellite-Based Navigation • WAAS and LAAS Baseline Approved • Low-End Users Get Safety and Access • High-End Users Get: • Improved Safety • More Airports and Runways • More Efficiencies in Airspace and Terminal Areas • FAA Gets Modernization of NAS • Improved Safety, Improved Efficiency, and Reduced Cost

  16. FAA GPS Product TeamWebsite • For further information on the FAA’s WAAS Program, please visit our website at: http://gps.faa.gov