Water Quality Improvements Riverglen Subdivision Valve Replacements

Water Quality Improvements Riverglen Subdivision Valve Replacements. April 4, 2013. The Infrastructure Response. Master Project. Hillsborough County Public Utilities Department Countywide Potable Water Lines Renewal and Replacement Program

emilie
Télécharger la présentation

Water Quality Improvements Riverglen Subdivision Valve Replacements

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Water Quality ImprovementsRiverglen Subdivision Valve Replacements April 4, 2013

  2. The Infrastructure Response

  3. Master Project • Hillsborough County Public Utilities Department • Countywide Potable Water Lines Renewal and Replacement Program • This program is to improve water quality and service by replacing valves and undersized lines, and connecting water lines to remove “dead ends”. Infrastructure and Development Services Public Utilities Department

  4. Project Benefits • Reduction of number of locations taken out of service during line repairs. • Maintaining fire protection. Infrastructure and Development Services Public Utilities Department

  5. Construction Work Summary • Replace: • Fifteen (15) 12-inch valves on Donneymoor Drive • One (1) 4-inch valve and one (1) 6-inch valve on Sunnyoak Drive • Seven (7) 6-inch valves on Shady Forest Drive • One (1) 4-inch Valve and Six (6) 6-inch valves on Glenpointe Drive Infrastructure and Development Services Public Utilities Department

  6. Construction Work Summary (continued) • One (1) 4-inch valve and two (2) 6-inch valves on Glenox Lane • Two (2) 6-inch valves on Kelp Lane • One (1) 6-inch valve on Racine Place • Two (2) 6-inch valves on Clover Glen Drive Infrastructure and Development Services Public Utilities Department

  7. Construction Schedule

  8. Impacts to Residents • Construction work will be done between 8 a.m. and 4 p.m. weekdays. • Occasional closures of sections of Donneymorr Drive, Sunnyoak Drive, Shady Forest Drive, Glenpointe Drive, Glenox Lane, Kelp Lane, Racine Place, and Clover Glen Drive. • Areas impacted will be fully restored. Infrastructure and Development Services Public Utilities Department

  9. Contact Information During regular business hours: Cindy Hutchens, Project Manager 813-209-3095 After Hours Emergency Line: 813-744-5600 Infrastructure and Development Services Public Utilities Department