1 / 7

FINANCIAL FORECASTS July 2013 Jerome Simpson, VANGUARD Project Coordinator REC

FINANCIAL FORECASTS July 2013 Jerome Simpson, VANGUARD Project Coordinator REC. Slide 2/7. A +4m extension will absorb only ‘so much’ of this. Spending – As of mid-March 2013. A/C/D: Green percentages: Underspending * incl. Sub-contracts. 80 percent spent/Eur 752,772 unspent. Slide 3/7.

ena
Télécharger la présentation

FINANCIAL FORECASTS July 2013 Jerome Simpson, VANGUARD Project Coordinator REC

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FINANCIAL FORECASTSJuly 2013 Jerome Simpson, VANGUARD Project Coordinator REC

  2. Slide 2/7 • A +4m extension will absorb only ‘so much’ of this.. Spending – As of mid-March 2013 • A/C/D:Green percentages: Underspending • * incl. Sub-contracts 80 percent spent/Eur 752,772 unspent

  3. Slide 3/7 Move 26131 to staffing = 7 PMs for WIKI, pubs, rpting Labour rate change: REC for WIKI help, results pubs, extension, DoW u/d Proposed own Partner Shifts to mid-July 2014 • * incl. Sub-contracts | Red = changes Labour rate change: 4016: 1 PM Task 1.3; 2.5 PM: Task 4.7; 2 PM: Task 3.4 Labour rate change: 5000 (1PM Task1.3; 3.7PM Task 3.4); retains 11k for 2 extra study tours & 5k for Oct. tour

  4. Slide 4/7 Proposed Budget Decreases to mid-July 2014 • * incl. Sub-contracts | Red = changes - 16092 (WP1.1/3.4/4.5/4.6/5.3) PMs: -1.4 (WP2); -4.4 (WP4); -3 (WP5); +11,263 for Legacy Cities Eur 250,962 unspent

  5. Slide 5/7 1 PM each for T4.7, 3.4 &1.3; 2.5k Travel: T1.3&T3.4 Proposed Budget Increasesto mid-July 2014 • * incl. Sub-contracts | Red = changes Travel to Brest/CM (T1.3) + 0.5PM for Task 4.2 (website handover) & 0.5PM Task 1.3 Eur 40,694 shifted

  6. Slide 6/7 • Task 5.1: Mailing materials to WIKI, Evaluation Handbook ► Eur 5,000 (postage) • Task 5.1: Occasional CIVITAS PR work through to assignment end ► Eur 5,000 (travel) • Task 5.1: CIVITAS Stand Hardware ► Eur 25,000 (mountable flatscreens w built-in DVD or digital mirror) • Task 5.1: CIVITAS Stand audio-visual software development (interactive digital game or quiz feature, video compilation) ► Eur 36,200 (4 subcontracts@5000 for software dev., transport content, DVD ‘play all’ video compilation; design + 6PMs) • Task 5.3: Forum ‘13 Travel (Journalists, Media, Moderators, Speakers) incl. discretionary fund for non-demo cities offered on a first-come first served basis (up to 20 cities) ► Eur 36,000 + EUR 5,400 (2PMs to administer) • Task 5.3: Forum ’14 ► Up to51,142+ EUR 5,400 (2PMs to administer) • Task 5.4:Ten years of CIVITAS Awards Compendium charting the growth in prestige of the awards over 10 yrs and putting the winner cities in the spotlight, great for highlighting outstanding achievements ► Eur 28,700(6PM+12500 Printing and mailing) SUM: (177842 + 7% overhead + 20,000 s/c =)210,291 Unspent Fund Allocation (Eur 210,291) REC ‘Extra’ Summary: Eur 83,500 direct costs +14 PMs (Eur 37,800) + Eur 8491 overhead + Eur 20,000 (sub-contracts) + Optional (Forum 14)Eur 51,142 direct costs +2 PMs (Eur 5,400) +Eur 3958 overhead

  7. Thank You Jerome Simpson Tel: +36 26 504 039 E-mail: JSimpson@rec.org

More Related