1 / 10

FourStar Status

FourStar Status. Presented By. Eric Persson (OCIW). Instrument Overview. Electronics Rack. Focal Plane Mechanisms. 200K Radiation Shield. Dewars. Camera Module. Vacuum Vessel. Window. 77K Radiation Shield. Conical Adapter. CDR & Post CDR Response.

erica-nolan
Télécharger la présentation

FourStar Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FourStar Status Presented By Eric Persson (OCIW)

  2. Instrument Overview Electronics Rack Focal Plane Mechanisms 200K Radiation Shield Dewars Camera Module Vacuum Vessel Window 77K Radiation Shield Conical Adapter FourStar Status

  3. CDR & Post CDR Response • Many useful recommendations from the CDR panel. • Load ring modifications • Camera module support • Gear materials and coatings • Heaters for warmup • Cold clamps • All CDR action items have been addressed at this time. • CDR recommendations have resulted in a multitude of design simplifications and modifications. FourStar Status

  4. Recent Milestones • Contract signed for construction of vacuum vessel • Detectors finished and ready for delivery FourStar Status

  5. Detectors • Had the choice of the best 4 out of 5. Done. • The 4 Science-grade detectors are now in hand. • Best specs: • QE: J 0.79 H 0.90 Ks 0.97 • stddev(QE): J 0.014 H 0.014 Ks 0.01 • readnoise: 18 e- rms (CDS) • dark: 0.0005 e-/sec • full “well”: 150,000 e- • crosstalk: 6.1% (total) in 8 surrounding pixels • bad & hot pixel count: 0.01% (mostly dead) • Testing caveats: • QE at K cannot be real • readnoise of other devices not as low FourStar Status

  6. Ongoing Work at Carnegie • Lifetime testing of mechanisms at 77K, • Developing array test dewar for testing ASICs and engineering grade array when electronics arrive, and • Building focal plane mechanisms. FourStar Status

  7. Ongoing Work at IDG/JHU • Orders are being released for cart hardware. • Parts are being fabricated for the electronics racks and the various chassis. • Drawings sets for remaining thermal and opto-mechanical hardware being prepared for release. FourStar Status

  8. Schedule FourStar Status

  9. Narrow Band Filters They will work in the fast beam at the price of a 25% reduction in flux for a clean profile. There are 7 free positions. • We ask the SAC members to poll their institutions in order to propose filters and to find funding for them soon. They should be ordered by September 1, 2007. The relevant parameters are (only) central operating wavelength and bandwidth. 2. The team will work with the SAC to choose the set of <= 7 filters that can be accommodated in the 2 filter wheels. FourStar will not be paying for the filters. FourStar Status

  10. Narrow Band Filters (concl’d) • The team will design and specify the filters. There are several additional parameters that must be designed in, viz., substrate thickness for parfocality, blocking, and extra wavelength shift in the fast beam. 4. Carnegie will then order the filters and invoice the proposers’ institutions with an extra charge for design. Typical costs are likely to be ~ $10K per filter. 5. Once the instrument has been closed up in preparation for its commissioning run, it will not be reopened solely for the purpose of inserting a new or replacement filter (because of risk). FourStar Status

More Related