1 / 23

MeerKAT/KAT-7 Progress/Status

MeerKAT/KAT-7 Progress/Status. Francois Kapp DBE Sub-System Manager francois.kapp@ska.ac.za +27(0)21 506-7300. Outline. KAT-7 Status Early results Future Plans MeerKAT Status DBE Key Specifications Required Modes Some Early Design Aspects SKA Activities. KAT-7 Status.

erica
Télécharger la présentation

MeerKAT/KAT-7 Progress/Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MeerKAT/KAT-7 Progress/Status Francois Kapp DBE Sub-System Manager francois.kapp@ska.ac.za +27(0)21 506-7300

  2. Outline • KAT-7 • Status • Early results • Future Plans • MeerKAT • Status • DBE • Key Specifications • Required Modes • Some Early Design Aspects • SKA Activities

  3. KAT-7 Status • All cold feeds installed • Remote Operations centre in Cape Town active • Full 14 (16) antpol correlator in continuum mode in use • All single dish commissioning work completed • Interferometric commissioning work on-going • Spectral Line mode and Beam Former mode to be available by end 2011 • Processing pipeline is hand cranked

  4. KAT-7 Status

  5. KAT-7 Early Results

  6. KAT-7 Early Results

  7. KAT-7 Early Results Christiansen, W. N., et al.

  8. KAT-7 Early Results Christiansen, W. N., et al.

  9. KAT-7 Early Results

  10. KAT-7 Future Plans • New modes deployed • Spectral Line Modes • Beam Former Modes • Targeted experiments to explore aspects of MeerKAT • Transient Search • Pulsar Timing • “KAT-8” • Include first MeerKAT antenna with existing array • Verification of new design

  11. MeerKAT Status • System Engineering Process • Large Survey Projects • Concept Design Review – July 2010 • Preliminary Design Review – July 2011 • Infrastructure Critical Design Review completed in September 2011 • Antenna Tender by end 2011 • Sub-system Specifications by end 2011 • First Offset Gregorian Dish in 2013 • Ramp up to full array in 2016

  12. MeerKAT Status

  13. MeerKAT DBE • DBE group responsibility has grown • Correlator/Beamformer Sub-system • Digitiser Sub-system • Time and Frequency Reference Sub-system

  14. MeerKAT DBE

  15. MeerKAT Key Specifications Number of antennas 64 offset Gregorian Dish diameter 13.5 m Minimum baseline 29 m Maximum baseline 8 km (Phase 1) 20km (Phase 2) Frequency bands (receivers) 0.58 – 1.015 GHz 1 – 1.75 GHz 8 – 14.5 GHz Continuum imaging dynamic range at 1.4 GHz 60 dB Line-to-line dynamic range at 1.4 GHz 40 dB Mosaicing imaging dynamic range at 14 GHz 27 dB Linear polarisation cross coupling across -3 dB beam -30 dB Sensitivity (0.58 – 1.75GHz) 220 m2/K Sensitivity (8 – 14.5GHz) 200 m2/K

  16. MeerKAT Required Modes • Concurrent observation of continuum and several spectral lines • Leads to a wider instantaneous BW than the feed BW • Pulsar Timing Mode • VLBI • Sub-arrays

  17. MeerKAT Frequency Range • Debate / ECP on frequency range for Phase 1. • Options: • 1000 – 1750 MHz • 900 – 1575 MHz • 900 – 1720 MHz • 900 – 1670 MHz • Decision to be based on further assessment of the performance risk for the feed. • Further assessment implies doing the design work, but the decision is deferred.

  18. MeerKAT DBE Technology • ROACH3 will reduce correlator cost and complexity • New ADC’s • L-Band • UHF-Band • X-Band

  19. MeerKAT KAPB

  20. SKA Activities • Bid Documentation submitted on 15 September 2011 • Some activity through February 2012, mainly politics now • SSG to make recommendation • We are focused on MeerKAT

More Related