PENJADWALAN PROYEK SISTEM LANJUTAN

PENJADWALAN PROYEK SISTEM LANJUTAN. SESI : 7 BY ARISM,SKOM,MMSI. Gambar Event Node. ES. NO : no. identifikasi node ES : earliest start time LF : latest finish time A, B, C : activity. NO. LF. Algoritma Jalur Kritis :

erik
Télécharger la présentation

PENJADWALAN PROYEK SISTEM LANJUTAN

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PENJADWALAN PROYEK SISTEM LANJUTAN SESI : 7 BY ARISM,SKOM,MMSI. MANPRO-M7 : PENJADWALAN PROYEK LANJUT

  2. Gambar Event Node ES NO : no. identifikasi node ES : earliest start time LF : latest finish time A, B, C : activity NO LF Algoritma Jalur Kritis : Suatu algoritma untuk menghitung waktu mulai tercepat (earliest start time/ES) dan waktu selesai terlama (latest finish time/LF) setiap kegiatan. B A C MANPRO-M7 : PENJADWALAN PROYEK LANJUT

  3. Perhitungan ES dan LF : • Forward pass : • Menghitung waktu mulai tercepat / ES dimulai dari node awal hingga node akhir. • (2) Backward pass : • Menghitung waktu selesai terlama / LF dimulai dari node akhir hingga node awal. MANPRO-M7 : PENJADWALAN PROYEK LANJUT

  4. D 22 H A 8 E 10 D2 27 I B 20 F 7 6 4 5 1 2 8 3 15 0 12 10 8 50 35 35 8 7 J 15 C D1 12 G 15 Gambar Forward Pass MANPRO-M7 : PENJADWALAN PROYEK LANJUT

  5. D 5 35 22 H 35 A 8 E 10 8 50 D2 27 I 50 B 20 3 F 8 1 2 4 6 7 0 12 15 10 35 8 7 8 0 J 15 C D1 12 G 15 Gambar Backward Pass MANPRO-M7 : PENJADWALAN PROYEK LANJUT

  6. SLACK : Waktu suatu kegiatan yang dapat ditunda tanpa mempengaruhi total waktu penyelesaian seluruh proyek. JALUR KRITIS : Jalur kegiatan dimana setiap kegiatan nilai slack = 0. ES—Earliest Start Time : Waktu mulai tercepat. LF—Latest Finish Time : Waktu selesai terlama. LS—Latest Start Time--Waktu mulai terlama yaitu : LF – Waktu estimasi EF—Ealiest Finish Time--Waktu selesai tercepat yaitu : ES + Waktu estimasi Slack : LS - ES MANPRO-M7 : PENJADWALAN PROYEK LANJUT

  7. WAKTU KEGIATAN TIDAK PASTI ai + 4 mi + bi Expected Time : ti = ------------------- 6 dimana : a = waktu optimis; b = waktu pesisimis; m = waktu paruh / tengah-tengah. Standar Deviasi / SD : Penyimpangan standar terhadap kedua waktu estimasi. ai - bi SD = --------- 6 MANPRO-M7 : PENJADWALAN PROYEK LANJUT

  8. DAFTAR WAKTU KEGIATAN TIDAK PASTI MANPRO-M7 : PENJADWALAN PROYEK LANJUT

  9. EXPECTED TIME SETIAP KEGIATAN 3+12+3 tD=--------------= 3 6 12+60+18 tA=--------------= 15 6 5+24+13 tB=--------------= 7 6 2+12+10 tE=--------------= 3 6 1+12+11 tF=--------------= 3 6 8+36+16 tC=--------------= 10 6 MANPRO-M7 : PENJADWALAN PROYEK LANJUT

  10. STANDAR DEVIASI SETIAP KEGIATAN 3 - 3 sdD=-------= 0 6 18 - 12 sdA=---------= 1 6 13 - 5 sdB=--------= 1,333 6 10 - 2 sdE=--------= 1,333 6 11 - 1 sdF=--------= 1,667 6 16 - 3 sdC=--------= 1,333 6 MANPRO-M7 : PENJADWALAN PROYEK LANJUT

  11. C 5 25 15 10 25 A D 15 F 3 3 3 E B 7 1 0 2 4 15 15 7 3 17 21 0 DIAGRAM JARINGAN PROYEK SISTEM MANPRO-M7 : PENJADWALAN PROYEK LANJUT

  12. SELAMAT MENEMPUH UJIAN TENGAH SEMESTER SEMOGA SUKSES SELALU MANPRO-M7 : PENJADWALAN PROYEK LANJUT