An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Update on the Davis-Woodland Water Supply Project Agency Board June 20, 2013

  2. Discussion Topics • Recent Activities/Accomplishments • Upcoming Activities/Milestones • DBO Procurement • Project Costs • Project Schedule

  3. Recent Activities/Accomplishments April - June 2013 PROGRAM MANAGEMENT • Prepared FY 2013-14 Agency Budget • Prepared Amendment to UC Davis Agreement consistent with Amended JPA • Continued pursuit of SRF Loans: • Safe Drinking Water SRF criteria: • Lost well capacity due to exceeding MCL’s (nitrate) -Woodland • Consolidation of North Davis Meadows -Davis • Submitted initial application for Clean Water SRF • $10m in State grant funding for Joint Intake included in legislature-approved State Budget

  4. Recent Activities/Accomplishments April - June 2013 (cont’) ENVIRONMENTAL AND PERMITTING • Continued Section 404 Permit efforts - awaiting Biological Opinions from NMFS and USFWS • Commenced Aerosol Study: • Four 24-hour sampling events completed • CDPH staff site visit on 6/3/13 • Received bids for mitigation banking • Continued work on SEIR for amendment to Water Right Permit for ASR

  5. Recent Activities/Accomplishments April - June 2013 (cont’) ENVIRONMENTAL AND PERMITTING • Working with RD 2035 re: WAPA power resource base sharing at Joint Intake • Working with PG&E to define system improvements/costs to serve RWTF and Joint Intake

  6. Recent Activities/Accomplishments April - June 2013 (cont’) LAND AND ROW ACQUISITIONS • Continued work on remaining easements: • Heidrick/McGinnis and Lillard for easements along Davis Finished Water Transmission Main • Sierra Northern Railroad • Oates for 3 parcels near Joint Intake site and along Raw Water Pipeline alignment • Closing on Intake site & CPG easements • Meeting with Yolo County regarding Encroachment Permit: • Road reconstruction/repair following pipeline construction

  7. Upcoming Activities/MilestonesJune - July 2013 PROGRAM MANAGEMENT • Continue to pursue SRF low interest loan and grant funding opportunities • Continue development of ASR Program • Preparation for injection testing, modeling, SEIR, water rights amendments • Continue efforts to obtain WAPA power at Joint Intake • Complete Value for Money analysis

  8. Upcoming Activities/MilestonesJune – July 2013 (cont’) ENVIRONMENTAL AND PERMITTING • Outstanding permits/actions: • Biological Opinions from USFWS and NMFS • Section 404 Permit (US Army Corps of Engineers) • Obtain Finding Of No Significant Impact (FONSI) from Bureau of Reclamation • Obtain State 401 Water Quality Certification • Continue Aerosol Study at RWTF Site • Begin negotiations for purchase of environmental mitigation credits

  9. Upcoming Activities/MilestonesJune – July 2013 (cont’) LAND AND ROW ACQUISITIONS • Continue work with Yolo County regarding encroachment permits/road construction • Complete acquisition of Heidrick/McGinnis, Lillard, Turner, and Oates easements • Complete easement agreement with City of Davis • Continue eminent domain actions on 3 parcels PLANNING, DESIGN, AND CONSTRUCTION • Receive priced DBO proposals July 30th

  10. DBO Contract Procurement • Received Initial Concept Submittals (ICS) • Reviewed ICS and Proposal Phase Procurement Plans from both DBO teams • DBO teams presented ICS proposals to FPC and in separate meetings to CDPH • Prepared Addendum 2 to DBO RFP • Clarified questions from individual meetings • Modified RFP to respond to common issues raised by both DBO teams

  11. Follow Up to ICS Proposals • CH2M Hill • Questions/clarifications noted in ICS letter to team • Satisfactory feedback received • Proposal Phase Procurement Plan approved • CDM Smith • Noted deficiencies in ICS in letter to team • Deficiencies not corrected in team response or through contacts with references • Letter to team noted ICS not in compliance • Team withdrew from competition

  12. DBO Procurement Process • 2.5 year, competitive process • 5 initial submittals, 3 shortlisted teams • Process worked as designed • Field narrowed to 1 team from original shortlist • 2 bidders removed themselves from consideration • Impacts of delays in procurement schedule • Inability to correct deficiencies in compliance with RFP provisions • Difficulty meeting Price Ceiling requirements • Allows negotiations to begin ahead of schedule • Savings to Agency of approximately $500,000

  13. Competitive Provisions of Procurement Process • Maximum cost ceiling to ensure competitive price – both capital and operation • Maximum capital cost ceiling is 20% less than Engineer’s Estimate • Open book competitive pricing for approximately 70% of work to be completed by subcontract • Open book review of all remaining self-performed work

  14. June 15, 2013 Open House Ad

  15. Draft DBO Procurement Schedule Updated: 06/20/13

  16. 30 mgd Project Costs Presented at April Board Meeting(Apr 2013 million dollars) Construction Costs(a) Capital Costs, 2009-2016 • Includes DBO contract design and construction costs, design-bid-build Joint Intake construction costs, and Agency design review, construction quality assurance and contract compliance, engineering services during construction, environmental construction monitoring, environmental mitigation, permitting, and incidental costs. • Costs currently under discussions with RD 2035.

  17. Updated 30 mgd Project Costs(April 2013 million dollars) Construction Costs(a) Capital Costs, 2009-2016 (a) Includes DBO contract design and construction costs, design-bid-build construction costs, and Agency design review, construction management, engineering services during construction, environmental construction monitoring, and environmental mitigation, permitting and incidental costs.

  18. Significant Project Cost Changes • Increase in Agency allocation for Joint Intake ($2.3 million) • Allocation to Agency for 20% of “soft costs” (i.e. engineering services during construction, CM, etc.) ($0.9 million) • Increased estimate for pipeline trenchless crossing ($1.4 million) • Pre-design fee for DBO Procurement ($250,000) • Technical Services to Davis and Woodland ($100,000) • Raw Water Intake Agency Facilities Design ($395,000)

  19. Intake Bidding Schedule Updated: 06/19/13

  20. Project Schedule Milestones Updated: 06/20/13

  21. Questions

  22. Financing Milestone Schedule Updated: 04/17/13