An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Davis-Woodland Water Supply FY 13/14 Budget Agency Board June 20, 2013

  2. Proposed FY 13/14 Budgetat April 2013 Board Meeting

  3. FY 13/14 Budget

  4. Changes from April Board Meeting by Major Budget Category • Agency Administration: no change • Program Management: + $20,000 • Construction quality assurance contract procurement • Regional Facilities Planning & Pre-Design: + $40,000 • Elimination of chlorine/chloramine mixing study (- $50,000) • Completion of aerosol study (under contract) • Energy consultant services (under contract)

  5. Changes from April Board Meeting by Major Budget Category • Water Rights Permits: + $123,000 • SEIR preparation (under contract) • Environmental & Permitting: + $20,000 • Environmental assistance for SRF funding applications • Supplemental Water Supply: - $60,000 • Woodland-only ASR will be a separate contract directly with Woodland

  6. Changes from April Board Meeting by Major Budget Category • Land/RW Acquisition: + $3,081,645 • RWTF purchase finalized FY 13/14 • Updated easement purchases remaining based on appraised values • Design: + $254,000 • Completion of value for money (VFM) analysis (under contract) • Pre-design fee (+ $250,000) • Updated DBO procurement costs

  7. Changes from April Board Meeting by Major Budget Category • Construction: + $268,500 • PG&E design costs (+ $181,000) • Reduced permitting fees (- $43,000) • Design & construction quality assurance coordination (+ $50,000) • 10% reduction in DBO construction costs (- $1.693 million) • Geotechnical costs associated with settlement monitoring (+ $17,000)

  8. Changes from April Board Meeting by Major Budget Category • Construction (con’t): +$268,500 • Increase in Agency allocation of Joint Intake costs (+ $1.757 million)

  9. FY 13/14 Budget Quarterly Breakdown

  10. Summary of FY 13/14 Contracts

  11. Questions