1 / 25

201-MHz NCRF Cavity Program Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory MUTAC Review at Fermi

201-MHz NCRF Cavity Program Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory MUTAC Review at Fermilab March 16, 2006. Collaborators. M. Dickson, R. MacGill, J. Staples, S. Virostek, M. Zisman Lawrence Berkeley National Laboratory

eyad
Télécharger la présentation

201-MHz NCRF Cavity Program Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory MUTAC Review at Fermi

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 201-MHz NCRF Cavity Program Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory MUTAC Review at Fermilab March 16, 2006

  2. Collaborators M. Dickson, R. MacGill, J. Staples, S. Virostek, M. Zisman Lawrence Berkeley National Laboratory A. Bross, A. Moretti, B. Norris, Z. Qian Fermi National Accelerator Laboratory J. Norem Argonne National Laboratory R. Rimmer, L. Phillips, G. Wu Jefferson National Laboratory Y. Torun Illinois Institute of Technology D. Summers University of Mississippi W. Lau, S. Yang Oxford University, UK

  3. Outline • Introduction • 201 MHz Cavity Progress • Cavity design and fabrication • Cleaning, vacuum and assembly • Shipping • Installation at MTA, FNAL • Installation: vacuum, RF couplers and probes, power transmission lines, baking system, … • Low power microwave measurements • Progress on curved Be windows • 21-cm (radius) curved Be windows for 201 MHz cavity • Asymmetric heating of the curved windows • Transient studies: pulse heating and to steady state • Preliminary tests of the cavity • Summary

  4. Ionization Cooling LH Absorbers RF Cavities Introduction • High gradient RF cavities to compensate for lost longitudinal energy • Strong magnetic field to confine muon beams • Lose energy in LH absorbers Goal: • Development of NC 201-MHz cavity that can operate at ~ 16 MV/m under a few Tesla solenoidal B fields Designing, engineering, fabricating, conditioning and operating a cavity at 16 MV/m with B is a challenging

  5. Introduction (Cont’d) NCRF R&D Programs Develop highest possible NCRF accelerating structure to meet the requirements for NF or MC • Prototype of 201 MHz cavity • Completed cavity design and fabrication • Cavity installation at MTA in Sept. 2005 • Assembly and vacuum • RF power plumbing • RF conditioning started in late Feb. 2006 • Experimental studies at 805 MHz with and without external magnetic fields up to 5-Tesla (2.5 Tesla for MICE) • Completed 5-cell cavity with open iris test at Lab G • Designed, fabricated and tested pillbox-like cavity with demountable windows at Lab G and moved and resumed recently at MTA, FNAL • Tests with two curved Be windows • Reached 32 MV/m easily without external magnetic field • More tests are in progress with magnetic fields versus achievable gradient • Button test

  6. Cavity Status at Last MUTAC Where we were at last MUTAC in Berkeley (Apr-2005) • Welding of cooling tube to cavity • Extruding of four ports and vacuum leak tight • Placed purchase order of curved Be windows Work needs to be done at the time: • Cavity interior buffing • Chemical cleaning and high pressure water rinse of the cavity interior • Surface cleaning + electro-polishing (EP) • High power RF conditioning of RF couplers with windows • Low power microwave measurements of the cavity with windows: • Frequency • Quality factor Q • Couplings • RF coupler measurement and tuning • Packing and shipping to MTA, FNAL

  7. The Cavity at J-Lab in Apr-2005 Outside • cavity body • cooling tube • ports and flanges • leak tight Extruded ports outer and inner surface finish Inside

  8. Cavity Progress: Final Interior Buffing • Best possible surface treatment: like SCRF cavities • Final interior buffing of cavity is performed to ensure the surfaces are ready for electropolishing • Less buffing needed near equator where fields are lower • An automated process of buffing was developed using a rotary buffing wheel and a cavity rotation fixture • Some local hand work required to clean up some areas • A series of pads with graduated coarseness was used • Goal was scratch depth shallow enough for EP removal

  9. Cavity Progress: EP Setup EP setup and the U-shape electrode for EP at J-Lab

  10. Interior Surface Electropolish • After buffing, cavity underwent a chemical cleaning process • Test bars with various degrees of buffing were run through an electropolish process • Cavity was rotated with a U-shaped electrode fixed in place • Initial polish failed due to depletion of the solution, and rebuffing was required • 2nd EP successfully removed scratches in high field regions • Final process is a high pressure water rinse of cavity surface

  11. Cavity RF Couplers and Assembly • Coupling loops were fabricated using standard copper co-ax • Most coupler parts were joined by torch brazing – vacuum leaks were found in two of the outer conductor joints • Coupling loop contains an integrated cooling tube • The coupler was designed to mate with an SNS style RF window manufactured by Toshiba • High power conditioning performed at SNS (ORNL)

  12. Coupler Conditioning Two loop couplers • Conditioning started during PAC-05 week at SNS, ORNL • Good vacuum ~ low 10-8 Torr • Achieved 600 kW in TW mode (matched load) • Achieved 10 kW average power (~ 9 kW for nominal NF parameters) • Achieved 2.4 MW peak power in SW mode (at variable short positions) • Two ceramic windows work flawlessly within two weeks of RF conditioning RF Load 805 MHz RF Power Two couplers

  13. Shipment to the MTA at FNAL • System assembly included: tuner plates, port blank-offs, diagnostic spool, window cover plates, gate valve and window pump-out tubes • Final leak check conducted prior to shipping • Cavity was back-filled with nitrogen in its assembled state and packaged in a custom made crate for shipping to the MTA Coupler shipment

  14. Final Assembly & Measurement at MTA • Cavity assembly was mounted on the support and couplers were installed in a portable clean room • Dummy copper windows (flat) are used initially • Couplers were set and frequency was measured • Bakeout system hardware was installed • System is leak tight View port with RF probes End plate with diagnostic ports RF loop couplers

  15. Low Power Measurements at MTA • f = 199.578 MHz • Q0 = 49,000 ~ 51,000 (better • than 90% of the design value) • Two couplers • balanced • coupling adjustments S11 Measurement

  16. Tuner Measurements • Mechanical tuning plates at four locations • Dial indicators to measure displacement between Al plates • Tuning measurement in air • Equivalent to MICE cavity under vacuum • Adjusted up to 2-mm with 8 steps of 0.25-mm each • Measured tuner sensitivity • ~ 78 kHz/mm • Calculated tuner sensitivity • 115 kHz/mm • Disagreements are due to deflection of the Al plates Dial indicators

  17. 42-cm Curved Be Windows • Two windows available now (LBNL) • 42-cm in diameter and 0.38-mm in thickness • Good braze (between the two annular copper frames and the thin beryllium foil) • Achieved the designed window profile • Thin Ti-N coatings on both sides • Ready for HP tests

  18. Asymmetric RF Heating • ANSYS simulations • A 15o slice cavity model • Solve for RF fields • 8.4 kW average heating power • 20 Co water cooling • Heat flux and temperature distribution • Stress and displacement • Frequency shifts Heat flux (w/m2) T ~ 130 Co • Frequency shift of 94 kHz from room • temperature to full RF power due to • Cavity body expansion (small) • Window displacement (major) • Tuner • Tuning sensitivity 115 kHz/mm •  500 kHz range T ~ 70 Co Temperature (Co)

  19. Asymmetric RF Heating (cont’d) High! Thermal stress Elastic stress limit of beryllium is 310 MPa

  20. RF Pulse Heating on the Windows ANSYS Transient simulations: • Solve for RF fields • Scaled (normalized) the fields to 4.5 MW peak power • Apply the power distribution within 124.4 us pulse and 15 Hz repetition rate • Temperature rise • Window and cavity deformation using the temperature distribution • Cavity frequency shift Temperature rise by a single pulse ~ 1 Co at r = R = 21-cm Cavity frequency change: ~ 80 Hz center middle edge

  21. RF Heat Transient to Steady State 8.4 kW average heating power: same pulse and rep. rate Monitor temperature at three locations on the windows at r = 0; r = R/2; r = R = 21-cm From 20 Co to steady state, it takes ~ 13 mins with frequency shift of 94 kHz. This frequency shift is well within the cavity bandwidth and can be tuned easily by mechanical tuners Cavity frequency stability with the Be windows under RF heating (from transient to steady state) is not a problem

  22. Preliminary Test: Setup at MTA RF probes 201 MHz coaxial RF power line The cavity Loop power coupler Loop power coupler Vacuum pump Radiation monitor Portable clean room Movable cavity support

  23. Cavity Design Parameters • The cavity design parameters • Frequency: 201.25 MHz • β = 0.87 • Shunt impedance (VT2/P): ~ 22 MΩ/m • Quality factor (Q0): ~ 53,500 • Be window radius and thickness: 21-cm and 0.38-mm • Nominal parameters for cooling channels in a muon collider or a neutrino factory • ~ 16 MV/m peak accelerating field • Peak input RF power ~ 4.6 MW per cavity (85% of Q0, 3 filling time) • Average power dissipation per cavity ~ 8.4 kW • Average power dissipation per Be window ~ 100 watts

  24. Preliminary Test Conditioning started in late Feb. 2006 with • Flat copper windows (plates) with Ti-N coatings • RF diagnostics: field, power & radiation measurements • Good vacuum ~ high 10-9 Torr Without external magnetic field, the cavity was conditioned very quietly and quickly to reach ~ 16 MV/m successfully Gradient is limited by RF power of 4.2 MW due to the modulator. 2 [MV/m]/division 0.1 ms/division

  25. Summary • The cavity reached design gradient of 16 MV/m successfully with almost no hard MPs: • Careful handling of the cavity • Good and clean surface finish • EP and high pressure water rinsing • Ti-N coatings of the windows • Test plan being actively developed to include test studies with • Thin and curved Be windows • RF heating on the windows: transient and steady state • External magnetic fields and achievable gradients versus the magnetic fields • Numericaland experimental studies of MP for the 201 MHz cavity

More Related