HIFI from now through launch
HIFI from now through launch. Peter Roelfsema. HIFI project status. Main success HIFI delivered and integrated (except LO) various troubles, but it’s working Pieter New calibration manager; Michael Olberg HCSS remerge, pipeline progress Russ’ team
HIFI from now through launch
E N D
Presentation Transcript
HIFI from now through launch Peter Roelfsema
HIFI project status • Main success • HIFI delivered and integrated (except LO) various troubles, but it’s working Pieter • New calibration manager; Michael Olberg • HCSS remerge, pipeline progress Russ’ team • AOT/sequencer improvements Kevin, Volker • Main issues H/W • ILT conclusions, outlook for ground and in-flight tests; Wednesday meeting • LO integration with satellite • Baffle/attenuators • LCU ripple • Lots of back-and-forth to Friedrichshafen • Documentation IUM, procedures • Main issues operations • Ops plans – C/O, PV, routine • Data distribution • Set up ICC@MOC and operational ICC (SRON, subnodes) • GS testing HIFI from now through launch - page 2
HIFI organization HIFI reorganization • HIFI manager Peter Roelfsema • AIV manager Pieter Dieleman • Operations David Teyssier • Uplink Kevin Edwards/Pat Morris • Calibration manager Michael Olberg • GS test manager Albrecht de Jonge HIFI from now through launch - page 3
Groups and meetings • Management group – bi-weekly meetings • Peter, Nick, Pieter, Michael, Russ • System group – bi-weekly meetings • Nick, Pieter, Michael, Pat/Kevin, David, Russ, Albrecht, Thijs, Peter minutes to be published on WWW • Subgroups per area set up by leaders • Likely e.g. Downlink will have multiple (e.g. pipeline, infrastructure, IA etc.) minutes to be published on WWW • PA/QA • Herman for H/W and Do for GS issues • Need to go to stricter configuration control regular CCBs HIFI from now through launch - page 4
Upcoming activities • Activities • Finalise hardware integration • Satellite moves; January to ESTEC, late May to Kourou • Testing: • Satellite Integrated Satellite Test (includes Reference Mission Scenario) • System: System Validation Test, System Operations Validation Test • Ground segment: DP End-to-End tests, PV verification, simulations • Launch campaign • Operations phases • Check Out • Performance Verification • Reviews • Instrument User Manual – late October • PV review – November • ICC readiness review – early 2008, GSRR -2 months 1st March • Ground Segment Readiness review – L-3 months 1st May • Flight acceptance review HIFI from now through launch - page 5
Herschel schedule Update of 15 September • Launch 31 July • 1 month recovery need • …(very) success oriented HIFI from now through launch - page 6
Next consortium meeting • Tuesday/Wednesday 8/9 April - Groningen HIFI from now through launch - page 7