The San Marcos Unified School District's Board Meeting on February 10, 2014, covered crucial updates regarding various facilities projects. Key projects include the Woodland Park Middle School modernization, with two classrooms modernized and Administration Building remodel, and completion of Twin Oaks High School's Administration Building remodel. Additional technology infrastructure projects were discussed, focusing on improvement at multiple schools. Updates also included the development of the NCREC-South project and enhancements at Carrillo Elementary School, ensuring better educational environments for students.
E N D
Facilities Updategoverning Board meeting San marcos unified school district February 10, 2014
Facilities Update: In Construction • Woodland Park MS Modernization Project: Mar 2014* • Modernize two (2) classrooms • Remodel Administration Building • Twin Oaks HS Modernization Project: Completed • Remodel Administration Building • Prop K: Technology Infrastructure Projects: • Mission Hills HS, La Costa Meadows ES, Paloma ES – Feb 2014* • Knob Hill ES, Richland ES, Twin Oaks ES, San Elijo MS – July 2014* • NCREC – South: August 2014* • Professional Development and Centralized Kitchen • Carrillo ES: Modernization Project: Apr 2014* • Modernize two (2) classrooms to add restrooms *Note: Scheduled Completion Dates
Facilities Update: Woodland Park MS Classroom Modernization and Expansion
Facilities Update: Woodland Park MS New Restrooms
Facilities Update: Woodland Park MS Student Support Services
Facilities Update: Woodland Park MS Conference Room and Student Support Services
Facilities Update: Woodland Park MS Student Support Services
Facilities Update: Twin Oaks HS Before AFTER Administrative and Student Support Services
Facilities Update: Twin Oaks HS Administrative and Student Support Services
Facilities Update: Twin Oaks HS Administrative and Student Support Services
Facilities Update: District-wide I.T. Infrastructure Project • Phase 1: 4 campuses • MHHS, DO, LCM, PAL • Feb. 2014 completion • Phase 2: 4 campuses • Design complete • Bid February 2014 • Complete July 2014 • KH, RL, SEMS, TOES • Working on E-rate projects (additional Federal funding)
Facilities Update: NCREC - South Professional Development and Centralized Kitchen Project • 3 Classrooms for Professional Development • 1 Portable Kitchen (from San Marcos High School Temporary Campus)
Facilities Update: Carrillo ES Mod. Existing Remodel
Facilities Update:thank you! Governing Board Meeting February 10, 2014