An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Facilities Updategoverning Board meeting San marcos unified school district August 19, 2014

  2. Facilities Update: In Planning/Design • Proposition 39: Energy Jobs Act • “Kick-off” meeting • Conduct campus analyses • Create proposed project list • Submit proposals to CEC for approval • Construct projects • Proposition K: Campus Modernization Projects • Preliminary master plans • Preliminary site surveys • Special Board Meeting “Workshop”

  3. Facilities Update: In Construction • Woodland Park MS Modernization Project • Professional Learning Center (PLC) – NCREC – S • Shade Shelters – MHHS, SEMS, DSC, SME • Facilities Needs for 2014-2015 – AD, DSC, SEMS • New Classroom Buildings – CAR, DSC, SME • Technology Infrastructure Projects • San Marcos K-8 School

  4. Facilities Update: In Construction • Woodland Park MS Modernization Project: Aug. 2014 • Completed final accessible ramp, casework (cabinets), and A/V equipment New Front Entry

  5. Facilities Update: In Construction • Professional Learning Center (PLC) at NCREC – S • Professional Development

  6. Facilities Update: In Construction • Professional Learning Center (PLC) at NCREC – S • Professional Development - TOSAs

  7. Facilities Update: In Construction • Professional Learning Center (PLC) at NCREC – S • Centralized Kitchen

  8. Facilities Update: In Construction • Facilities Needs for 2014-2015 • Discovery ES • New Shade Shelter and reconstruct Walkway Cover

  9. Facilities Update: In Construction • Facilities Needs for 2014-2015 • Discovery ES • New Shade Shelter and reconstruct Walkway Cover

  10. Facilities Update: In Construction • Discovery ES • 1 temporary Portable Building • Until SMK8 opens

  11. Facilities Update: In Construction • San Elijo MS: Support for temporary enrollment growth for 2014-15 school year School • 3 lunches • Large P.E. classes Facilities • Shade Shelter for PE/Lunch • Additional Basketball Courts • Upper Field Power/Communications

  12. Facilities Update: In Construction • Facilities Needs for 2014-2015 • San Elijo MS • New shade shelter, new basketball courts, new track perimeter

  13. Facilities Update: In Construction • Facilities Needs for 2014-2015 • San Elijo MS • New shade shelter, new basketball courts, new track perimeter

  14. Facilities Update: In Construction • Facilities Needs for 2014-2015 • Mission Hills HS • New shade shelter for art and outdoor classroom

  15. Facilities Update: In Construction • Facilities Needs for 2014-2015 • San Marcos ES • New shade shelter for Kindergarten area

  16. Facilities Update: In Construction • Facilities Needs for 2014-2015 • Alvin Dunn ES • New perimeter fence

  17. Facilities Update: In Construction • New Classroom Buildings • Anticipated enrollment growth at CAR and SME

  18. Facilities Update: In Construction • Carrillo ES: 5-Classroom Permanent Building

  19. Facilities Update: In Construction • Carrillo ES: 5-Classroom Permanent Building

  20. Facilities Update: In Construction • San Marcos ES: 4-Classroom Permanent Building

  21. Facilities Update: In Construction • San Marcos ES: 4-Classroom Permanent Building

  22. Facilities Update: In Construction • San Marcos ES: 4-Classroom Permanent Building

  23. Facilities Update: In Construction • Prop K: Technology Infrastructure Projects: • Mission Hills HS, La Costa Meadows ES, Paloma ES – Completed • Knob Hill ES, Richland ES, Twin Oaks ES, San Elijo MS – Jul. – Oct. 2014 • Remaining campuses – Oct. 2014 – Spring 2015

  24. Facilities Update: In Construction • Prop K: Technology Infrastructure Projects

  25. Facilities Update: In Construction • Prop K: Technology Infrastructure Projects

  26. Facilities In Construction: SMK-8

  27. Facilities In Construction: SMK-8 Parking Parking Buildings Central Courtyard Buildings Fields

  28. Facilities Update:thank you! Governing Board Meeting August 19, 2014