Simulation Based Production Planning, Scheduling, and Control. Johannes Krauth Sim-Serv. Overview. Planning Steps Methods Applied The Contribution of Simulation Examples The Future. Planning Steps. Production Programme Planning / Plant or Process Design (time horizon: years)

Simulation Based Production Planning, Scheduling, and Control - slide 1
01 / 37Simulation Based Production Planning, Scheduling, and Control
1 / 17

Télécharger la présentation

Simulation Based Production Planning, Scheduling, and Control
Une image / un lien ci-dessous est fourni (tel quel) pour télécharger la présentation

Politique de téléchargement : le contenu du site vous est fourni TEL QUEL pour votre information et votre usage personnel ; il ne peut être vendu, concédé sous licence ni partagé sur d’autres sites sans l’accord de son auteur.Le contenu vous est fourni TEL QUEL, pour votre information et votre usage personnel uniquement. Téléchargez la présentation en cliquant sur ce lien. Lors du téléchargement, si vous ne parvenez pas à télécharger une présentation, l’éditeur a peut-être supprimé le fichier de son serveur.Pendant le téléchargement, si vous ne parvenez pas à obtenir une présentation, le fichier a peut-être été supprimé par l’éditeur.

F I N

Plus de contenu associé

Transcription de la présentation
  1. Simulation Based Production Planning, Scheduling, and Control Johannes Krauth Sim-Serv

  2. Overview • Planning Steps • Methods Applied • The Contribution of Simulation • Examples • The Future

  3. Planning Steps • Production Programme Planning / Plant or Process Design (time horizon: years) • Production Planning (months / weeks) • Detailed Scheduling (days / hours) • Control

  4. Overall Planning Objectives • Maximise Capacity Utilisation • Minimise Delays • Minimise Throughput Times • Minimise Work in Progress Note: Conflicting Objectives!!

  5. Facility Planning • Based on assumed demand • Searches “optimal” match of needed and available capacity • Planning horizon: years • Not an ongoing activity

  6. Optimal Match Needed per year: 10,400 h milling ______________ 8,500 h welding … Available per year: 4 machines = 5376 h (1 shift, 80% utilis.); = 10752 h (2 shifts) __________________ 4 workers = 8400 h 5 workers = 10080 h … ?

  7. Limitations • no interdependencies taken into account • based on estimated / experienced degrees of capacity utilisation • adequate for strategic, long-term planning, when little information is available

  8. Production Planning • Based on (expected) customer orders • Using fixed throughput times per step (based on experience or assumptions) • Accepts / rejects orders and fixes start and end dates

  9. Example: Assumed and Real Durations

  10. Limitations • Capacity assumed available • Actual shop floor status not taken into account • Waiting times included and therefore fixed • Applicable only when long delivery times are acceptable

  11. Production Scheduling • Planning Horizon: 1 week – 1 day • Based on confirmed orders and actually available resources • Must take into account technical restrictions • Finds exact sequence of operations per work station

  12. Production Scheduling • Must be “fit for reality”!

  13. Contribution of Simulation • Detailed models • Exact representation of all processes, all needed resources • Realistic transition times, based on current shop floor status • All kinds of rules and constraints can be taken into account

  14. Ways to Use Simulation: 1. Offline, from outside Simulation Model controls MRP /ERP System feeds back

  15. Ways to Use Simulation 2. Online, as part of planning toolbox MRP / ERP System: Long Term Planning Module_____________________ Medium Term Planning Module___________________ Scheduling Module: Simulation Model Shop Floor

  16. Typical “Leitstand” / APS tool

  17. Contribution of Optimisation • Can use a large variety of criteria for “optimal” solutions • Finds very good schedules quickly • Takes away hours of routine work from the planners • Allows them to focus on the essentials

  18. Examples • 2 Examples: Simulation helps optimise planning tool and process • 4 Examples: Simulation and Optimisation modules as part of planning toolbox

  19. Conclusion from Examples: • Broad range of industry sectors • Leitstand / APS tools can complement existing MRP / ERP tools or run stand-alone • Typical benefits include • Higher capacity utilisation • Less WiP • Less delays, shorter throughput times • Payback often within a few months!!

  20. Summary • Simulation Based Scheduling and Control offers substantial advantages • Many approaches available for different special requirements • Also useful for SMEs • Sim-Serv assists with selection of best suited approach