This presentation outlines the development and testing processes for an optical transceiver project across 12 weeks. Key activities include budget analysis, schematic design, PCB layout, and extensive testing phases focusing on alignment tolerance and shielding efficiency. The project involves a collaborative effort among team members, with tasks divided into management, design, assembly, and testing phases, addressing both conservative and aggressive design approaches. Results from the various testing stages provide insight into the product's performance and adherence to specifications.

Télécharger la présentation

GROUP 1 FINAL PRESENTATION

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. GROUP 1 FINAL PRESENTATION Ragad Al-Huq Michael Fabery Mustansir Pratapgarhwala Yeonshin Won Dae-Geun Yoon

  2. Week 1 Task Management • Webmaster - Michael, Mustansir • Budget Analysis and Ordering - Yeonshin • Testing - Michael, Mustansir, Yoon • Design – Michael, Mustansir, Ragad • Building/Soldering – Yoon • Alignment Tolerance & Analyisis – Mustansir, Yoon

  3. Week 2 Test Receiver Board Results D 21.5 K 28.5 PRBS7 K 28.7

  4. Week 3 – Optical Link Budget

  5. Week 4 – Transceiver Schematic

  6. Week 5 – Parts Ordered

  7. Week 6 – Power Supply Filter

  8. Week 7 – Final PCB Layout

  9. Transceiver Boards Standard Design Aggressive Design

  10. Week 8 – Receiver Testing Receiver Conservative PRBS7 Receiver Aggressive PRBS7 Conservative/Aggressive Receiver 5 dB

  11. Week 9 – Tx Testing Conservative TX 0 dB Conservative Tx 5 dB Aggressive Tx 0 dB Aggressive Tx 5 dB PRBS7

  12. Week 10 Loopback Testing Aggressive Design Conservative PRBS7 0 dB Aggressive PRBS7 0 dB Aggressive D21.5 5 dB

  13. Week 10 – Alignment Tolerance Bad Results D21.5 0 dB PRBS7 0 dB K28.5 0 dB

  14. Week 11 – Alignment Tolerance Good Results Rx 0 dB D21.5 Rx 0 dB K28.5 Rx 0 dB PRBS7

  15. Week 12 – Shielding 1 of 3 K28.5 Before Shielding 5 dB PRBS7 Before Shielding 5 dB K28.5 After Shielding 5 dB PRBS7 After Shielding 5 dB

  16. Week 12 – Shielding 2 of 3 K28.5 Before Shielding 10 dB PRBS7 Before Shielding 10 dB K28.5 After Shielding 10 dB PRBS7 After Shielding 10 dB

  17. Week 12 – Shielding 3 of 3 K28.5 Before Shielding 15 dB PRBS7 Before Shielding 15 dB K28.5 After Shielding 15 dB PRBS7 After Shielding 15 dB

  18. Alignment Tolerance

  19. Final Gantt Chart

  20. How Much? Quantities of 1000