An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LCLS Injector Commissioning Workshop (ICW) October 9-11, 2006 Drive-Laser Experience at FLASH Overview of the laser system Running experience Remarks

  2. The Photocathode RF Gun • L-band rf gun (1.3 GHz) • Pulsed 5 or 10 Hz • RF pulse length up to 900 µs • RF power 3.2 MW or 42 MV/m max gradient • Cs2Te cathode laser beam e- beam Cathode Siegfried Schreiber, DESY * LCLS Injector Commissioning Workshop (ICW) * 9/11-Okt-2006

  3. General Design Issues of the Laser • L-band RF gun + requirement on e- bunches determines transverse and longitudinal shape of laser, synchronization • Photocathode: work function, QE determines wavelength, energy • Superconducting accelerator long bunch trains → Laser average power in the Watt range • Suitable type of lasermode-locked solid-state system (MOPA: synchronized oscillator + amplifiers + frequency converter to UV) Siegfried Schreiber, DESY * LCLS Injector Commissioning Workshop (ICW) * 9/11-Okt-2006

  4. Laser System Overview Diode-pumped Nd:YLF Oscillator Not a commercial system, cooperation DESY/Max-Born-Institute, Berlin Conservative design: operationable in a ‘user’ environment Modulators (AOM EOM AOM) 108 MHz 1.3 GHz 13.5 MHz Piezo tuning of cavity length Faraday isolator Pulse picker Pockels cell Remote controlled mirror box fround trip= 27 MHz Epulse= 0.3 µJ Stabilized by quartz tubes Fiber-coupled pump diodes Diode pumped Nd:YLF amplifiers Epulse= 6 µJ Imaging to the cathode Fast current control Pulse picker Faraday isolator Flashlamp pumped Nd:YLF amplifiers Beam shutter LBO BBO Relay imaging telescopes Fast current control Remote controlled attenuator Epulse< 0.3 mJ IR→ UV Double pulse generator Epulse< 50 µJ Siegfried Schreiber, DESY * LCLS Injector Commissioning Workshop (ICW) * 9/11-Okt-2006

  5. Modulators (AOM EOM AOM) 108 MHz 1.3 GHz 13.5 MHz Piezo tuning of cavity length fround trip= 27 MHz Stabilized by quartz tubes Fiber-coupled pump diodes Pulse Train Oscillator (PTO) • Mode-locked pulsed oscillator • Diode pumped (32 W) • Synchronized to 1.3 GHz master oscillator • 1.3 GHz EO modulator with 2 AOMs (108 + 13.5 MHz) • Phase stability < 300 fs rms • Pulse length 12 ps (fwhh) (IR) • Stabilized with quartz rods • Thermal expansion coefficientfused quartz = 0.59 ppm/K (Al = 24 ppm/K) • 27 MHz pulse train • Train length 2.5 ms, pulsed power 7 W Siegfried Schreiber, DESY * LCLS Injector Commissioning Workshop (ICW) * 9/11-Okt-2006

  6. 5 m m Chain of Linear Amplifiers • 2 diode pumped and 2 flashlamp pumped single pass amplifiers • Fully diode pumped version is running at PITZ • Laser diodes: 32 W pulsed, 805 nm end pumped through fibers energy from 0.3 µJ to 6 µJ/pulse Xe flashlampsNd:YLF rod, Ø 5 or 7 mm • Flashlamps pumped heads: cheap, powerful (pulsed, 50 kW electrical/head)current control with high power IGPT switches allows flat pulse trains energy up to 300 µJ (1 MHz), 140 µJ (3 MHz) small-signal gain = 20 extractable peak power 1.2 kW, duty cycle 2% Siegfried Schreiber, DESY * LCLS Injector Commissioning Workshop (ICW) * 9/11-Okt-2006 Fluorescence profile

  7. 1.2 nC Electron beam pulse train (30 bunches, 1 MHz) Pulse Trains 800 µs After amplification (1 MHz) • 2 Pulse pickers, based on Pockels cell + polarizer → up to 3 MHz • Preamplification (diodes) of 1.2 ms long train • Power amplification with variable bunch pattern Amplitude Output of the laser oscillator (27 MHz) Time Siegfried Schreiber, DESY * LCLS Injector Commissioning Workshop (ICW) * 9/11-Okt-2006

  8. Bunch Pattern and MPS • Change bunch pattern on user request • Number of bunches • Different bunch frequencies: 1 MHz, 250 kHz, 100 kHz and others • Realized with an FPGA based controller producing the appropriate trigger for the Pockels cell • The controller is also the interface of the machine protection system to the laser Siegfried Schreiber, DESY * LCLS Injector Commissioning Workshop (ICW) * 9/11-Okt-2006

  9. 50 kHz 1 MHz 599 bunches 100 kHz 500 kHz Lasing with long bunch trains • This year: up to 600 bunches to beam dump • 1 MHz, 500 kHz, 100 kHz, and 50 kHz • Lasing with at least 450 bunches • Problems: • Toroid protection system not yet in operation, emulated by software • Improvements required for photon diagnostics • Beam loading compensation was at limit for ACC2/3 and ACC1 for 800 µs flat top • Activation of beam line components due to darkcurrent, mostly from rf gun Siegfried Schreiber, DESY * LCLS Injector Commissioning Workshop (ICW) * 9/11-Okt-2006

  10. Laser beamline • Relay imaging with spatial filtering • Hard edge aperture after diode pumped amplifiers • Aperture imaged to → amplifier heads → doubling crystals → cathode Transverse profile not really flat hat Still noticeable pointing jitter (~10 % of spot size) Achieved good pointing stability with an additional iris in front of vacuum window (70 cm from cathode) Paid with interference fringes (20 % modulation) For the present FLASH running scheme: stability is more important than perfect beam shape Compensation of path length addition in double pulse generator by telescope Siegfried Schreiber, DESY * LCLS Injector Commissioning Workshop (ICW) * 9/11-Okt-2006

  11. UV diagnostics/doubler variable attenuator telescope x2 Movable mirrors/ splitters λ/2 wave plate polarizing splitter to rf gun prism UV Photo-diode Double Pulse Generator Streak Camera joulemeter Siegfried Schreiber, DESY * LCLS Injector Commissioning Workshop (ICW) * 9/11-Okt-2006

  12. Virtual cathode and iris aperture RF gun Iris Mirror Box Virtual cathode (Ce:YAG crystal, CCD camera Siegfried Schreiber, DESY * LCLS Injector Commissioning Workshop (ICW) * 9/11-Okt-2006

  13. 4.4 mm 1.3 mm 4.0 mm Transverse Laser Pulse Shape • Transverse shape of the UV laser pulses is not TEMoo • Intentionally closer to flat hat to avoid spatial hole burning along the pulse train 1.6 mm Exit amplifers (IR) exit BGO on cathode (no iris) magnification ~ 5 PITZ shaping (on cathode) Siegfried Schreiber, DESY * LCLS Injector Commissioning Workshop (ICW) * 9/11-Okt-2006

  14. On cathode • With additional magnification by 2 (total ~10) and remote controlled iris aperture Large iris (~open) Nominal iris 3.0 mm diameter Siegfried Schreiber, DESY * LCLS Injector Commissioning Workshop (ICW) * 9/11-Okt-2006

  15. Measured (UV, 262 nm) 120 Flat Top Fit FWHM = 19-24 ps rise/fall = 7-9 ps 100 80 60 amplitude 40 20 0 -20 0 10 20 30 40 50 60 Time (ps) Photon density (a.u.) 0 10 20 30 40 50 Time (ps) Laser Pulse Length and Shape • R&D laser at PITZ:Longitudinal flat-hat shape • Works fine in ‘lab environment’, not mature for a user facility • Present laser technology does not allow shorter rise/fall times • New development at MBI ongoing Longitudinal shape is Gaussian • Measurement with a streak camera (FESCA 200) sL= 4.4 ± 0.1 ps (at 262 nm) Siegfried Schreiber, DESY * LCLS Injector Commissioning Workshop (ICW) * 9/11-Okt-2006

  16. Vacuum mirror • Best would be to have high quality dielectric mirror • However, darkcurrent may charge it up • Charging and discharging effects beam orbit and destroys the mirror → after some tries with Al shielding we have now a good quality solid aluminum mirror (R=90%) → no long time experience with long pulse trains yet (heating due to absorption, ablation) TTF1 dielectric mirror with discharge traces Siegfried Schreiber, DESY * LCLS Injector Commissioning Workshop (ICW) * 9/11-Okt-2006

  17. Controls • Laser is fully integrated into the control system – say almost, still pieces missing (rf phases, BBO, diodes) • Controlled by a Sparc cpu running Solaris in a VME crate, mixed standard (timing, ADCs) and special equipment (ns delays, …) • Server running real time operations and controls • Server handing over parameters to controls • Some other servers for specific tasks • Interlocks controlled by an SPS system with an interface to controls (cpu, cooling water flow, temperatures, door contacts etc) • SPS controlled special mode to allow laser in tunnel while having access • Operators have easy control of the laser with options of detailed access to parameters • Easy: number of laser pulses, bunch frequency, attenuator • Expert: timing, pump parameters, feedback parameters etc Siegfried Schreiber, DESY * LCLS Injector Commissioning Workshop (ICW) * 9/11-Okt-2006

  18. Temperature Laser Room Temperature stability < 0.02 dgC- if people do not access laser room 0.05 dgC 3.5 days 6 months Siegfried Schreiber, DESY * LCLS Injector Commissioning Workshop (ICW) * 9/11-Okt-2006

  19. Charge Stability Stability = 1.4% rms Problem:to maintain a stability < 2 % rms fine tuning of phase matching angle of the frequency conversion crystal green to UV (BBO) often required If not tuned frequently, stability drops to 5 % rms Siegfried Schreiber, DESY * LCLS Injector Commissioning Workshop (ICW) * 9/11-Okt-2006

  20. RF Gun llrf with SIMCON • Amplitude and phase regulation by calculating the vector sum of forward and reflected power • FPGA based controller in operation since Dec 2005 • Phase stability of 0.14 dg of 1.3 GHz or 300 fs achieved 1 dg of 1.3 GHz = 2.1 ps Siegfried Schreiber, DESY * LCLS Injector Commissioning Workshop (ICW) * 9/11-Okt-2006

  21. Cathode • Cathode: Cs2Te film on a molybdenum plug • RF contact with silver coated Cu-Be spring Siegfried Schreiber, DESY * LCLS Injector Commissioning Workshop (ICW) * 9/11-Okt-2006

  22. QE maps • QE map: scan with small laser spot (200 µm) over the cathode (step size 300 µm) • useful to diagnose status of cathode uniformity • Example of a non-uniform cathode → We need to consider the uniformity of both, the laser beam profile and the cathode QE • May need a feedback based on beam profiles… 78.1 73.1 78.1 Siegfried Schreiber, DESY * LCLS Injector Commissioning Workshop (ICW) * 9/11-Okt-2006

  23. Alignment of Laser • Initial alignment of laser beam onto the cathode using a scintillator mounted into the plug • Fine adjustment with • Beam based alignment (electron beam position as a function of rf phase for low charge, solenoids off)→ time consuming (2 shifts) and difficult, but yields center in respect to rf, precise • Scan laser over cathode→ scan is fast, but assumes that cathode film is centered in respect to the rf, correction less accurate • Virtual cathode helps to recover alignment and to monitor movements and pointing • However, for high QE cathodes we need an intensified and gated camera to have a permanent monitoring darkcurrent ring may also be used for rough alignment Siegfried Schreiber, DESY * LCLS Injector Commissioning Workshop (ICW) * 9/11-Okt-2006

  24. Quantum Efficiency • Example of a QE measurement:charge at rf gun exit as a function of laser pulse energy • QE = 4.8 % in this case Siegfried Schreiber, DESY * LCLS Injector Commissioning Workshop (ICW) * 9/11-Okt-2006

  25. End of lifetime QE < 0.5% Cathode lifetime • Lifetime 6 months, early 2006 we observed shorter lifetimes of 2 months • Problem for the laser: large change in output required End of lifetime QE < 0.5% • Variable attenuator useful in order not to change laser operational parameters of the laser too much Siegfried Schreiber, DESY * LCLS Injector Commissioning Workshop (ICW) * 9/11-Okt-2006

  26. Long Term Running • TTF phase 1: 12/1998 to 12/2002→ 4 years of running (36,000 h or 13•107 s) • oscillator 25,000 h or 9.2•107 shots, amplifiers 16,000 h or 6.4•107 trains @ 1 Hz • Total on-time oscillator 70%, amplifiers 50% • TTF phase 2: upgrade end of 2003: diode pumped oscillator and preamplifiers • FLASH: Running since 3/2004 with 2 and now 5 Hz • about 3•108 shots/trains with 20 pulses av. delivered for beam • Total on-time == always, even mostly during the maintenance days (4 %), off during maintenance weeks (~6 per year) • Backup system, fully diode pumped soon Siegfried Schreiber, DESY * LCLS Injector Commissioning Workshop (ICW) * 9/11-Okt-2006

  27. Maintenance • All components need maintenance and have to be replaced from time to time • Flashlamps: life time 1 to 5 107 shots (1 month = 1.3 107) • Pockels cell drivers: roughly once per year • Flashlamp power supplies: once per 3 years • Laser crystals: once per 5 years • LBO/BBO: once per 5 years • Mirrors: no change required yet • Control hardware: frequent changes, cpu, ADCs, other boards • Diode lasers: no exchange yet (20,000 h now) • Cooling water/equipment: often • Component checks once per week, occasional adjustments of timing and other parameters Siegfried Schreiber, DESY * LCLS Injector Commissioning Workshop (ICW) * 9/11-Okt-2006

  28. Conclusive remarks • Good experience with the present laser system • Advantage of collaboration with one laser institute: permanent support and ongoing development to your needs, no overhead • Risk: no quick alternative if cooperation ceases • However, similar argument holds for companies in case of complex laser systems • Design philosophy • As simple as possible (avoid components which require frequent adjustments) • ‘Ready-to-sell’ finish and robust • Use well-known technology (laser material, pump sources) • Fully integration into the control system as a must • Capability of long running in accelerator environment is proven • Laser room and laser development are separated: laser is part of the machine (access only for maintenance/repair) • Diagnostics as complete as possible to assist operators Siegfried Schreiber, DESY * LCLS Injector Commissioning Workshop (ICW) * 9/11-Okt-2006