GLAST LAT Tracker Tower15 Pre-Ship Review

GLAST LAT Tracker Tower15 Pre-Ship Review. Luca.latronico@pi.infn.it INFN-Pisa. Tower 15 - Assembly and test highlights. tray17 replacement. September 19-21, 2005 (INFN-Pisa) : assembly of complete tray stack incomplete cable set (C5 missing, C2 non-flight) Sidewalls, alignment

gamba
Télécharger la présentation

GLAST LAT Tracker Tower15 Pre-Ship Review

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. GLAST LAT Tracker Tower15 Pre-Ship Review Luca.latronico@pi.infn.it INFN-Pisa

  2. Tower 15 - Assembly and test highlights tray17 replacement • September 19-21, 2005 (INFN-Pisa) : • assembly of complete tray stack • incomplete cable set (C5 missing, C2 non-flight) • Sidewalls, alignment • September 29 – Oct. 3, 2005 (Alenia-Roma) • TVAC (9/26-29) • VIB (9/29-10/3) • October 5-11, 2005 (INFN-Pisa) : • C5 installation • C2 replacement • Solithane, EMI taping • Alignment verification, final CPT • Full EIDP details at: • http://glast.pi.infn.it tray to be replaced

  3. Tower 15 – configuration Tower PN: LAT-DS-00722 (rev3) Tower SN: 15 Environmental test performed with following configuration variations: • C5 missing • C2-008 non-flight installed in place of C2-020 Delivery configuration notes: • Kapton and poron foam as per LAT-DS-00722 • 4 layers of Poron foam 0.037 THK used on Bottom and Top Tray (–X) side (in place of 5 layers) Alignment well within stay-clear Measured mass 32.920 Kg

  4. Tower 15 – Open NCRs • INFN/PI-589: environmental test in non-flight configuration • the environmental tests were performed with a missing cable (C5) and 1 non-flight cables (C2), as agreed by an MRB • Full flight set provided after environmental test and installed before delivery • the NCR can be closed • INFN/PI-590: cold/hot power off/on not performed • The problem is due to a known and documented issue with resetting MCM (NCR 417) with missing cables • To avoid the many and unknown number of power cycle needed to re-establish a good configuration with as many readable layers as possible, hot/cold switch on and off were not performed • Update SLAC waiver LAT-XR-07340 to include tower 15? • the NCR can be closed • INFN/PI-586: Vacuum level out of specification • The situation is similar to earlier TVAC tests and the proposal is to accept the test as for previous MRBs • Tower 8 performed TVAC test together with tower 15 and its relative NCR was closed during tower 8 preship review on 10/5 • the NCR can be closed

  5. Tower 15 - Efficiency run 306001376 before env-test taken in Alenia after TVAC All layers well within spec (eff > 98%) no changes in bad channels during env test pre-ship data analysis underway – results will be included in EIDP

  6. Tower 15 - Bad channels behaviour X0 and Y17 slightly exceed 16 during hot soaks

  7. Tower 15 - noisy channels behaviour Fluctuation are due to noisy channels