Placing Equipment

Placing Equipment. Chapter 5. Chapter Topics. Placing concrete directly from trick mixers Manual or motorized buggies Crane and bucket Concrete conveyors Concrete pumps. Placing Directly from Truck Mixers. Most economical placing method Minimal handling; minimizes segregation

garren
Télécharger la présentation

Placing Equipment

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Placing Equipment Chapter 5

  2. Chapter Topics • Placing concrete directly from trick mixers • Manual or motorized buggies • Crane and bucket • Concrete conveyors • Concrete pumps

  3. Placing Directly from Truck Mixers • Most economical placing method • Minimal handling; minimizes segregation • With chute extensions up to 20 ft • Deliver 8 to 10 cy and weigh up to 80,000 lbs • Avoid cracking sidewalks and driveways • Avoid open excavations or walls • If wall 6 ft deep, stay 6 feet away • Take advantage of mixer-mounted conveyors

  4. Manual or Motorized Buggies • Transport from mixer to deposit • Walk-behind or riding • Some can fit through 36 inch doorways • Placing capacity ranges from 15 to 20 cy/hr • Consider costs • Buggy may need temporary ramps • Can’t run over reinforcing

  5. Crane and Bucket • Lift concrete bucket to desired location • Typically for small placements: columns • Two buckets increase production • Buckets • Different sizes: 1/3 to 3 cy • Different attachments: rubber discharge chutes

  6. Conveyors • Mounted to ready mix truck • Separate conveyors • Can discharge concrete quickly

  7. Concrete Pumps • Trailer pumps • General purpose: 20 to 35 cy/hr • Pump up to 250 ft vertically • Pump up to 1000 ft horizontally • 4 to 5 inch diameter pipelines • Labor intensive for pipeline placing and removal

  8. Concrete Pumps • Boom-mounted pumps • Most efficient method for large placements • Consider these factors • Delivery output • Pump layout and boom length • Site conditions • Number of pumps needed