An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 9th JVOC MeetingThursday 24th of January 2002at 14 :30, Bldg 36-1-003 Cooling system for Tracker (TK) and Preshower (SE) -General description- M. Jeske (ST/CV)

  2. Chilled water production CMS-Point 5 UXC 55 CMS detector USC 55 (CV Zone)

  3. Cooling of TK and SE detectors:fluids and interfaces to/from overground chilled water production chilled water C6F14 brine COOLING RACKS R 404A COLD PRODUCTION

  4. Demands on cooling system • cold energy supply of 4 subsystems with different cooling requirements • 1. TK pixel: 7 kW @ -10 °C (- 20 /-17 °C)*) • 2. TK strip: 80 kW @ -10 °C (- 20 /-17 °C) *) • 3. TK screen: 10 kW @ -10 °C (- 11.5 /-8.5 °C) *) • 4. SE shower: 20 kW @ -6 °C (- 14 /-11 °C) *) • cold energy transport over a distance of up to 200 m • 150 m brine, 50 m C6F14 • maximum of reliability and availability •  redundant cooling system • *)…C6F14 supply/return temperature

  5. Concept of cooling system for TK and SE subdetectors

  6. Main components of Plant A (74 kW)location USC

  7. Main components of Plant A (74 kW) location UXC - 17 °C - 20 °C

  8. C6F14 Pumping Station • Leak detection: • liquid level surveillance in tank • advantages: • technically easiest possibility • cheap (level switch< 500 CHF) • disadvantages • inertia/precision of leak detection • switch differential 1...5 mm (hysteresis) • Tracker (Vtank = 1 m3, d = 0,8 m, H =2 m) • loss of 0,5…2,5 l necessary • before realization of leak • Purge: • suction of C6F14 into the tank • by means of vacuum pump Reference: Uniphase Cooling Unit (5 kW/-25 °C) building 186, M. Bosteels