380 likes | 390 Vues
Learn how the City of Manistee implemented an asset management process to improve their streets and infrastructure. Find out about their proactive approach, challenges faced, and the positive outcomes achieved.
E N D
City of Manistee An Asset Management Journey
Manistee Factoids • Incorporated in 1869 • Population 6,586 • $5,000,000 General Fund Budget • 4.3 Sq. Miles – 3.2 land, 1.1 water • Located at mouth of Manistee River on Lake MI • Victorian Port City
Manistee Streets Overview • 18.2 miles of Major Streets • 29.4 miles Local Streets • 2.2 miles State Trunkline • 1 Bascule bridge over Manistee River • $358,000 Act 51 - Major • $129,000 Act 51 – Local
The Manistee Story • Poster child for worst first program • Pave it and forget it • Crack seal: what’s that? • Maintenance: Plow, sweep, and………..fill potholes • How come our roads are so bad? There has to be a better way
Drivers for Asset Management • City Strategic Plan • Destination of choice • Infrastructure a priority • Maintain what we have • Impacts budget
Drivers for Asset Management • Sewer Separation Projects • State (MDEQ) mandated 1997-1999 • $14 M in work – many streets rebuilt • Led to false sense of security • Streets starting to age & deteriorate
Drivers for Asset Management • Insufficient financial resources • Stretch the $$$ • More flexibility needed
What did Manistee Do to Implement the Asset Management Process? • Raise Awareness • Provide Education • Acquire Tools & Training • Incorporate & Communicate • Create Plan • Implement Plan • Report Results
Raise Awareness • Introductory meeting • MDOT & NWMCOG • Internet research • Summer 2007 • Asset Mgt Conference • Introduction to Asset Mangement • Finance Director & DPW Director
Provide Education • Fall 2007 • Introduction To Asset Management • City Manager & Engineer • Sent Staff to PASER Training Sessions • January 2008 Kickoff • Hosted Introduction to Asset Mgt seminar at City Hall • 2008 Asset Mgt. Conference • 2008 Asphalt Maint. Seminar • Presented at May Regional MML Meeting
Acquire Tools & Training • Acquired Roadsoft GIS • Attended Beginning & Advanced Roadsoft • Available from Michigan Tech Local Technical Assistance Program (LTAP) • www.roadsoft.org • www.michiganltap.org • Critical to success
Incorporate & Communicate • Weave asset management into the City’s “Culture of Doing Business” • Front & Center during decision making • Discussed at Staff meetings • Keep Council informed & connected • Updates on process • Budgetary impacts & limitations
Create Plan • Establish Project Team • Cross-Functional Finance Engineering DPW
Create Plan • Assess Current Condition (PASER) • Select Appropriate Treatments • Estimate Costs & Budget Constraints • Predict Future Condition of Network & Develop Network Goals • Evaluate Treatments (Optimize Strategy) • Identify Candidate Projects • Report Results
Assess Street Conditions (Data) • Acquire Street PASER Data • Received data from NWMCOG • Rated all streets in April 2008 • Professionally by City Engineer • City Staff assisted • Annually rate streets in fall • Roadsoft laptop data collector and GPS
Select Appropriate Treatments • The mix of treatments appropriate to your community • Capitalizes on “windows of opportunity” • The right fix at the right time in the right place • Many new techniques • Hot-In-Place
……..and Budget Constraints Asset Management Plan Implementation $150,000 $150,000 $150,000
Predict Future Condition of Roads • Work with LTAP to analyze PASER data • Tim Colling Create scenarios: • Different fixes • Budget constraints • Optimize deterioration curves • Review for reasonableness • Understand software & limitations
Develop Network Goals • Keep it simple • Maximize Remaining Service Life (RSL) • For Manistee, this doesn’t mean things are getting better, simply not declining as fast • Refine goals as we gain experience
Identify Candidate Projects • Cross-Departmental Staff Team • Factors: • Cost & budget • Future sewer work • Traffic Flow • Need • Grants (Leverage) • Condition of Base (Core) • Strategic Plan
2009 Projects • Approximately 3.25 miles of work • Hot-In Place • Ultra Thin Overlay 3/4” • $475,000
Report Results • Keep Council fully informed: • Progress • Successes • Failures • Evaluate plan, techniques and outcomes • Adjust if necessary • Not static • Continue annual PASER rating
Doing Business Smarter…….. Asset Management has irreversibly changed the way the City looks at street projects • Energized the project team • Unleashed creativity • HIP, Fiber Mesh • More thorough evaluation of potential projects • Objective, best practice decision-making • Measurable objectives and outcomes
……..and More Economically • Major & Local Street Budgets – constrained • Stretch Available Dollars • 3x as much with recent project • Stop wasting money on ineffective or inappropriate treatments • Leverage money thru grants
Lessons Learned • Effort Needs a Champion • Education, Education, Education • Communication with Staff & Council • Stakeholder Buy In • Don’t re-create the wheel - many resources • Technology tools critical • New maintenance techniques available