VRD vs QHr Scheduling. J E Scheiderich 5-24-04. VRD vs. QHr Scheduling. Purpose: Present a means to give participant transactions equal footing with VRD Especially relevant to time related issues Utilize VRD constructs – e.g. supply curves as part of the process

hailey
Télécharger la présentation

VRD vs QHr Scheduling

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. VRD vs QHr Scheduling J E Scheiderich 5-24-04

  2. VRD vs. QHr Scheduling • Purpose: • Present a means to give participant transactions equal footing with VRD • Especially relevant to time related issues • Utilize VRD constructs – e.g. supply curves as part of the process • Allows a time period to see if participant actions sufficiently arbitrage the price spreads between NY and NE • If it does not produce desired results then implement VRD… jes/Select Energy

  3. VRD vs. QHr Scheduling • Important note… • We have not yet discussed VRD in the context of NY’s RTS/SMD2. So far a separate in-hour process was considered since BME ran once per hour and well ahead of time as well. • As this is written it presumes RTC (the commit component of RTS) schedules the transactions subject to the limitations of the supply curves (and security). • It presumably would be possible to shorten the timeframe, ignoring RTC. This would require a separate process of some sort and all the impact would fall onto RTD – the real time dispatch component jes/Select Energy

  4. VRD vs. QHr Scheduling • Proposal: • Participants would submit transactions to one ISO 30+ minutes in advance of one ¼ hour interval for which they would flow if chosen • Checkout is proposed to be automatic between the ISOs – if ramp is available and RTC accepts your bid, you get in the queue • We might consider using NY as the required bid would eliminate the need for possible transmission allocation scheme • Supply curves as already proposed by the ISOs would be used to avoid price “flipping” jes/Select Energy

  5. VRD vs. QHr Scheduling • Proposal (cont): • While transactions could be offered in either direction, only those that would aid the arbitrage would be scheduled to flow • Note that any transaction entered will be considered and if scheduled and priced at RT proxy bus prices • There will be no opportunity for transaction “failures” • Propose a “no-Tag” approach for these transactions • Participant transactions will be subject to the ahead of vs. RT price risk but for a shorter period jes/Select Energy

  6. VRD vs. QHr Scheduling:Benefits • Provides opportunity for participants to address the problem by reducing, not eliminating, transaction risk • Shorter lead & flow times – 30+ & 15 minutes, respectively • Single point of transaction entry • Utilizes capabilities that the ISOs would need for VRD including supply curves & security checks • Reduces potential for “throw-away” development • Eliminates transaction risk to the ISOs • No opportunity for transaction “failures” by MPs due to missing tags, mismatched schedules etc. jes/Select Energy

  7. VRD vs. QHr Scheduling: Benefits (cont) • Avoids any gain/loss allocation issues the ISOs would have with VRD • See A2_VRD Straw Proposal_7-25-03.pdf for the 7-31-03 MSWG/MC meeting; page 11 • Failure of MPs to arbitrage price spreads in a significant manner would ultimately lead to a full VRD implementation jes/Select Energy