1 / 7

OPIM 3801: Principles of Project Management

OPIM 3801: Principles of Project Management. Review for the first midterm Problem section outline. Learning Curves. I will give you the formula: T n = T 1 n log (learning rate, 2) You should be able to:

halee-dean
Télécharger la présentation

OPIM 3801: Principles of Project Management

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. OPIM 3801:Principles of Project Management Review for the first midterm Problem section outline

  2. Learning Curves • I will give you the formula: Tn = T1nlog(learning rate, 2) • You should be able to: • Use the formula in Excel to compute the labor time for each unit if given the learning rate • Use Goal Seek (under Data -> What-If) to find the learning rate if total labor hours for a batch is given • Add up cost for labor, revenue for units, find breakeven point

  3. Critical Path and PERT • Find the critical path, ES, EF, LS, LF • Interpret an AOA or an AON network picture to get predecessors • Use the PERT template to: • Find a probability given a completion date • Find a completion date given a probability • Know Z = (X – mu) / sigma • And X = Z*sigma + mu • Or skip the Z using norm.dist& norm.inv

  4. Crashing • Starting with normal & crash, times and costs • Compute limit column • Compute Crash Cost/week (or day etc.) • Set up column for reductions and resulting times after reductions • Set up path times as totals of resulting times • Total crashing costs are the sum-product of crash/time with the reduction amounts

  5. Crashing (cont.) • With zero reductions longest path is the normal project duration. • Paste in the limit amounts (paste values) for reductions; longest path is now the shortest possible project duration • Set up solver to find cheapest way to get to a particular target. • Use binary variable when partial crashing is not allowed.

  6. Leveling • New tasks -> Auto-Scheduled • Format -> critical tasks and project summary task • List resources on resource sheet • Assign resources using checkbox, or right click the “assign resources” • Try “Level only in available slack” first for best possible solution, then without splits or changing individual assignments, then with

  7. Leveling (cont.) • Insert columns “total slack” or “free slack” to see those if needed • Insert column “leveling delay” to see delays due to leveling (in elapsed days = real days) • Use max % in the resource sheet to have generic workers (2000% = 20 workers, for example)

More Related