G4V- Grid for vehicles

Frankfurt (Germany), 6-9 June 2011. G4V- Grid for vehicles. Round Table RT5c/4a Integration of plug-in-vehicles in distribution networks. Contribution from 2 major EU FP7 projects: MERGE and G4V.

halil
Télécharger la présentation

G4V- Grid for vehicles

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Frankfurt (Germany), 6-9 June 2011 G4V- Grid for vehicles Round Table RT5c/4a Integration of plug-in-vehicles in distribution networks. Contribution from 2 major EU FP7 projects: MERGE and G4V Analysis of the impact and possibilities of a mass introduction of electric and plug-in hybrid vehicles on the electricity networks in Europe Thomas Theisen RWE Paolo Scuro Enel

  2. Agenda • Overview: the G4V project • EVs: Background • Business/Economic, Environmental and Societal Implications for Electro-Mobility • Customer perspective: Results of the European G4V survey • Economic and Environmental impacts of Electro-Mobility • Implications for business models of the key stakeholders • Impact of electromobility on electricity networks THEISEN – DE – RT 5c/4a – G4V

  3. Overview: the G4V project Project duration: Jan 2010 – June 2011 time-horizon: 2030 Key – Question: What needs to be started now in order to enable a mass market of EV? ScenariosWP1 • technical issues • legal framework • business model • customer convenience • environmental aspects RoadmapWP7 WP3 Regulatory framework Business modelsWP 2 Socio-economics ICTWP4 Grid Infra-structureWP5 PowersystemoperationWP6 Recommendations THEISEN – DE – RT 5c/4a – G4V

  4. Agenda • Overview: the G4V project • EVs: Value for the entire system • Business/Economic, Environmental and Societal Implications for Electro-Mobility • Customer perspective: Results of the European G4V survey • Economic and Environmental impacts of Electro-Mobility • Implications for business models of the key stakeholders • Impact of electromobility on electricity networks THEISEN – DE – RT 5c/4a – G4V

  5. The alterable characteristics of the EVs makes them good candidates to impact the system… …technically and economically: • Provide flexibility to the system: • Buffer the variability of intermittent generation coming from renewable energy sources • Tool for managing congestion in the power networks • Demand response services • Load-shaping services • Trading flexibility: • Due to their small scale, the EVs need to be operated as an ensemble • Niche for a new function: Aggregation (that can be taken by an existing or a new actor) • Trade the services that they can provide in the most appropriate markets • … and also ecologically .... THEISEN – DE – RT 5c/4a – G4V

  6. Agenda • Overview: the G4V project • EVs: Value for the entire system • Business/Economic, Environmental and Societal Implications for Electro-Mobility • Customer perspective: Results of the European G4V survey • Economic and Environmental impacts of Electro-Mobility • Implications for business models of the key stakeholders • Impact of electromobility on electricity networks THEISEN – DE – RT 5c/4a – G4V

  7. Preferences of potential users of EVs related to charging – A survey in 8 countries Survey results(1,900 responses were received from 8 countries) : • Preference of home recharging (70 % ) • Interest in delayed charging (with price incentives) • average of 5,8 on a scale from 1-7 • Most interested UK: 6,1 • Less enthusiastic Spain: 5,6 • Main reason not to be interested: being afraid not having the possibility to use their car • V2G: Less interest compared to delayed charging • average of 4,4 on a scale from 1-7 • Most interested UK and Portugal • Main reason not to be interested : • benefit too low (50%) THEISEN – DE – RT 5c/4a – G4V

  8. Agenda • Overview: the G4V project • EVs: Value for the entire system • Business/Economic, Environmental and Societal Implications for Electro-Mobility • Customer perspective: Results of the European G4V survey • Economic and Environmental impacts of Electro-Mobility • Implications for business models of the key stakeholders • Impact of electromobility on electricity networks THEISEN – DE – RT 5c/4a – G4V

  9. Significant avoidance of wind energy curtailment by optimized EV charging ... even at low levels of EV penetration Example: UK, 30% wind penetration in the system THEISEN – DE – RT 5c/4a – G4V

  10. Impact on production costs: Optimized charging leads to reduced overall operational costs Key reasons for cost savings in Optimized EV charging: • Avoidance of wind energy curtailed • Reduced usage of expensive generators • Reduced provision of response by conventional generators • Reduced emission costs THEISEN – DE – RT 5c/4a – G4V

  11. Agenda • Overview: the G4V project • EVs: Value for the entire system • Business/Economic, Environmental and Societal Implications for Electro-Mobility • Customer perspective: Results of the European G4V survey • Economic and Environmental impacts of Electro-Mobility • Implications for business models of the key stakeholders • Impact of electromobility on electricity networks THEISEN – DE – RT 5c/4a – G4V

  12. Market/ system conditions THEISEN – DE – RT 5c/4a – G4V

  13. System operation • Generation scheduling • Minimise total operating costs • Power balance constraint (including EVs’ charge and discharge) • Security: system reserve requirements • Units technical operating constraints: - Minimum up- and down-times - Up and down ramp rate limits • EVs scheduling • “Maximise revenues” • EVs’ energy requirements • EVs operating constraints: - State of charge - Charging and discharging rates - EV’s status THEISEN – DE – RT 5c/4a – G4V

  14. Conclusions of the aggregator model • The coordination of the aggregator and markets is a large and complex optimisation problem • Aggregators will sell their services only if their price is competitive (the total system welfare increases) • The V2G services are acquired for: • Energy arbitrage • Generation schedule changes • Systems with “flat” supply curves would hardly acquire V2G services for energy arbitrage • When the EVs penetration is large enough to flatten the total system demand, there are no opportunities to provide V2G services THEISEN – DE – RT 5c/4a – G4V

  15. Agenda • Overview: the G4V project • EVs: Value for the entire system • Business/Economic, Environmental and Societal Implications for Electro-Mobility • Customer perspective: Results of the European G4V survey • Economic and Environmental impacts of Electro-Mobility • Implications for business models of the key stakeholders • Impact of electromobility on electricity networks SCURO – IT – RT 5c/4a – G4V

  16. Tool to evaluate EV impact on Distribution Grids • Stochastic approach • Inputs: • Collection of almost 200 real grid data (MV & LV) • Driving patterns from mobility study • 8 different EVs control strategies • Outputs: • Overloads in lines and sub-stations • Required reinforcement investment • Technical parameters (security margins, energy and power in violation) SCURO – IT – RT 5c/4a – G4V

  17. Control strategies: Conservative Scenario Uncontrolled Tariff Control Examples SCURO – IT – RT 5c/4a – G4V

  18. Control strategies: Pragmatic Scenario • Pragmatic solutions envisage an active role of the DSO • Charging process integrate into smart grid solutions. • Those solutions are achievable within today technology and regulatory conditions • Possible to host higher percentage of EVs Load by EVs is reduced, if secondary substation is at capacity SCURO – IT – RT 5c/4a – G4V

  19. Control strategies: Advanced Scenario • More advanced solutions, for example using the Aggregator or multiple agents, can provide additional benefits for the electrical system such as higher integration of renewables • To introduce them additional researches are needed; for example to integrate them in grid congestion management Aggregator Model Multiple Agents (Powermatcher ) SCURO – IT – RT 5c/4a – G4V

  20. Simulation results • Using control strategies is possible to reduce and postpone grid reinforcement • To apply some of the control strategies it is required to implement smart grid functionalities • Moreover, there is the opportunity to use EVs to offer services to the electric system (e.g. integration of renewable sources) SCURO – IT – RT 5c/4a – G4V

  21. Presentation of the Final Results of the G4VProject 30 June 2011 BRUSSELS Further information & registration: www.g4v.eu