1 / 11

Audit Preparation

Audit Preparation. September 8 – 11, 2008 ERCOT will be audited as the.  Reliability Coordinator (RC)  Transmission Operator ( TOP)  Balancing Authority (BA) and  Transmission Service Provider (TSP). Logistics. ● 13 auditors (4 NERC, 5 TRE) 4 FERC observers

Télécharger la présentation

Audit Preparation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Audit Preparation

  2. September 8 – 11, 2008 ERCOT will be audited as the  Reliability Coordinator (RC)  Transmission Operator ( TOP)  Balancing Authority (BA) and  Transmission Service Provider (TSP)

  3. Logistics ● 13 auditors (4 NERC, 5 TRE) 4 FERC observers ● Two interviewing groups running concurrently: Mon – Wed noon. ● Operations floor interviews scheduled for Wed afternoon ● Additional SME’s onsite from ONCOR and TMPA (at the request of NERC)

  4. Definitions and Acronyms • CMEP – Compliance Monitoring and Enforcement Program • RSAW – Reliability Standard Audit Worksheet • OSD – Operating Standards Department • SME – Subject Matter Expert

  5. OVERVIEW OF PREPARATIONS Developed the matrix Answer RSAWs and Questionnaires

  6. Developing the matrix • Map ERCOT to NERC • First meeting – June 30th of 2007 • Last meeting – April 11th of 2008 • ~30 meetings with market participants • 6 ROS presentations and • 1 presentation to TAC by ROS Chair

  7. RSAW Action Plan ● 94 FERC approved NERC Reliability Standards ● 57 standards in 2008 CMEP with RSAWs ● Divided by Operations, Planning, and Security ● Broken into 9 weekly packages began on May 15, 2008 final sent out July 15, 2008.

  8. RSAW Action Plan(cont) ● Assigned to SME Utilized the matrix with references 2007 Audit Responses were reviewed ● OSD reviewed evidence and resolved with SMEs ● Management review

  9. Current Status 7/31/08  92% (34 out of 37) RSAW’s have been completed by SME’s  60%(about 22 out of 37)RSAW’s have been resolved with SME’s  67%(90 out of 135)action items have been completed.  100% response on 4 questionnaires received

  10. Remaining Schedule ● Work with Market Participants scheduled to provide support ● Review FERC approved NERC Reliability Standards not on CMEP ● Review Board approved NERC Standards ● Two training sessions will be provided to SME’s

  11. Questions ? ?

More Related