The MICE beamline and hall are nearing completion, with the shielded area virtually done. Concrete for the replacement west wall has been ordered, and corner pieces are on the verge of ordering. Expected delivery and installation timelines are around 6 weeks, subject to surveys for extra wall and roof shielding. High-density blocks are available soon, and additional materials ordered by Oxford will contribute to ongoing installations. Final details are being confirmed, with a review planned for the end of September, setting the stage for future projects.

haruki
Télécharger la présentation

MICE Beamline and Hall Progress Update: Shielding and Installation Plans

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MICE MICO September ‘07 Chris Nelson

  2. Beamline and Hall • Shielded area virtually complete • SW corner • Replacement West wall concrete ordered, corner pieces about to be ordered • Delivery both ~6 weeks, installation next opportunity • Extra wall near Door and roof subject to survey • Extra shielding in plinth doorway • Plan using high density blocks, availability ~1 week • Agreement with Paul Wright RPA • Check numbers needed and Order today • Plinth rails installed & surveyed • Double check needed on alignment measurements • CKOV stand • Materials and parts ordered by Oxford • Discussion, & Extra small detail drgs lifting, dowel pins etc (being finished?) • CJN will organise PRR (Peter back next week)

  3. Triplet baseplates at RAL • Installation details being finalised, hope to install 1-2 weeks time • But Need blockhouse access • Rolling platform • Review end September • Ordered air skates • First platform required March 08 • Future plans • False floor • Concrete plinth

  4. MICE – platforms and baseplates CONCEPT – PLATFORM WITH AIR SKATES CLAMPED TO BASEPLATE IN INSTALLED LOCATION. WHEN ACCESS IS REQ’D THE CLAMPS ARE RELEASED AND THE TRACKER IS FLOATED TO A PARKED POSITION.

  5. Mechanical Services • Water- order being written out • Other services/gases • Need for detector groups to request any required services • Compressed air line for when Linde equipment in use • Nitrogen for CKOV (bottle/gas line)?