1 / 26

The Theory of Constraints Critical Chain Management using MS Project 2010 and ProChain

The Theory of Constraints Critical Chain Management using MS Project 2010 and ProChain. Variability Is A Fact Of Life. Objective. Define “Theory of Constraints Critical Chain Management?” What are the core issues TOC CCPM must resolve?

hateya
Télécharger la présentation

The Theory of Constraints Critical Chain Management using MS Project 2010 and ProChain

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The Theory of Constraints Critical Chain Management using MS Project 2010 and ProChain Variability Is A Fact Of Life

  2. Objective • Define “Theory of Constraints Critical Chain Management?” • What are the core issues TOC CCPM must resolve? • The Difference between the WBS and Project Network and why we need both. • Difference between Critical Path and Critical Chain Project Management • Project Synchronization and Staggering • Understanding tasks variability and buffer management • Aligning Behavior to increase our execution velocity • Demo of MS Project 2010 and ProChain

  3. What is the Theory of Constraints? Bottlenecks

  4. Organizational Core Issues • Too much concurrent demand in the same window of time. • Bad Multi-tasking • Safety time in current tasks is wasted • Conflicting Priorities – Resource contention • Behavior misalignment • Student Syndrome • Parkinson’s Law • CYA (Assets) • 3 minute egg

  5. What is Critical Chain Portfolio Management? The TOC solution for planning, scheduling and managing performance in a project environment. It is applied in both single project and multi project environments where resources are shared across several different projects concurrently. (TOCICO Dictionary, 1st edition, 2007) The longest string of work in a schedule, taking into account all tasks and resources dependencies.

  6. Theory of Constraint: Critical Chain Process

  7. The Difference between the WBS and Project Network

  8. Work Breakdown Structure

  9. Project Network

  10. Critical Path vs. Critical Chain Project Management Hybrid Gas only The algorithms used to determine the critical path vs. the critical chain are radically different.

  11. What are some of the differences?

  12. TOC requires Project Synchronization and Staggering Reducing the number projects in the system and focusing on the critical few will deliver more projects faster creating velocity WilmerHale

  13. Task variability is a fact of life. • Putting on a pair of Levis • Putting on a pair of Levis you owned in High School • Putting on Sweats

  14. Buffer Management – Leading Indicator Task variability is protected by aggregated buffers

  15. Aggregated Buffers Saves Time and Money WilmerHale

  16. Task Estimating

  17. Resource Histogram – Understanding Capacity

  18. Critical Chain Planning & Execution Process

  19. Aligning Behavior to increase our execution velocity

  20. In Summary • What did we learn? • Critical Path Management was developed by the DOD using unlimited resources, Critical Chain accounts for the reality that all task have variability and that resources are limited • Buffer Management provides a calculated leading indicator that provides an early warning if projects are trending to slip their dates. • CCPM accounts for the reality in variability.

  21. How can you implement this process in your environment? • Recognize the need for a new way to management projects in a resource constrained environment. • Obtain agreement on the core problem resulting from managing projects using CPM with constrained resources. • Gain buy in and acceptance on Critical Chain Project Management • Treat the implementation of CCPM as a project. • Provide training and education for Project Manager, Resource Managers, Senior Management and other IS Staff on the benefits of CCPM • Develop the internal technical capability to manage CCPM projects within our environment • Develop phased rollout approach for other projects to adopt CCPM • Evaluate results after each phased rollout and establish new policies, procedures and best practices.

  22. Presentation Delivered by:Gerald Leonard, PMP, MCTS, CQIA, ITILEmail:gerald.leonard@verizon.netLinkedIn: http://www.linkedin.com/in/geraldjleonardBlog: http://principlesofexecution.typepad.com/principles-of-execution/Twitter: http://twitter.com/#!/geraldjleonard

More Related