Download
woodbridge school district schematic design for woodbridge high school n.
Skip this Video
Loading SlideShow in 5 Seconds..
Woodbridge School District Schematic Design for Woodbridge High School PowerPoint Presentation
Download Presentation
Woodbridge School District Schematic Design for Woodbridge High School

Woodbridge School District Schematic Design for Woodbridge High School

195 Vues Download Presentation
Télécharger la présentation

Woodbridge School District Schematic Design for Woodbridge High School

- - - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript

  1. Woodbridge SchoolDistrictSchematic Design forWoodbridge High School 17 January 2012

  2. Schematic Design Building

  3. Building Plans • First Floor Plan

  4. Building Plans • Second Floor Plan

  5. Perspectives • Rear • Front

  6. Woodbridge School DistrictTotal Project Cost Summary Building Construction Costs $ 46,470,770 Design & Consulting Fees $ 2,498,500 State, County, Local & Agency Fees $ 1,365,641 FF&E & Technology Equipment $ 1,970,000 Subtotal $ 52,304,911 Total Project Costs $ 52,304,911 Woodbridge School District Budget $ 52,539,700 Total Amount Under / (Over) Budget $ 234,789 Proposed Add Alternates $ 2,850,000 January 17, 2012

  7. Woodbridge School DistrictProject Schedule Space programming 09/22/11 – 11/16/11 Schematic Designs (30%) 11/11/11 – 01/17/12 Design Development (60%) 12/19/11 – 04/23/12 Construction Documents 03/22/12 – 08/23/12 Bid Pack A (Site Concrete & Steel) 8/20/12 Bid Pack B (building & Systems) 10/02/12 Funding available $10.5 m 10/2011 (FY-12) Funding available $21.0 m 10/2012 (FY-13) Funding available $21.0 m 10/2012 (FY-13)

  8. Questions and Answers Woodbridge SD AdministrationFearn - Clendaniel ArchitectsEDiS Company Thank you!