SlideServe
Menu
Préférences
© SlideServe · v2026

Optimizing Outage Scheduling Protocols for Enhanced Grid Reliability

herbst avatar
5 diapositives · 143 Views · Sep 12, 2014

Explore the evolution of outage scheduling before and after key events, such as severe weather or ERCOT directives, with a focus on enhancing grid reliability and safety. Learn about challenges faced during outage cancellations and the importance of efficient restoration procedures. Discover valuable lessons learned and suggestions for improved outage management processes.

Optimizing Outage Scheduling Protocols for Enhanced Grid Reliability - slide 1
01 / 5Optimizing Outage Scheduling Protocols for Enhanced Grid Reliability
1 / 17

Télécharger la présentation

Optimizing Outage Scheduling Protocols for Enhanced Grid Reliability
Une image / un lien ci-dessous est fourni (tel quel) pour télécharger la présentation

Politique de téléchargement : le contenu du site vous est fourni TEL QUEL pour votre information et votre usage personnel ; il ne peut être vendu, concédé sous licence ni partagé sur d’autres sites sans l’accord de son auteur.Le contenu vous est fourni TEL QUEL, pour votre information et votre usage personnel uniquement. Téléchargez la présentation en cliquant sur ce lien. Lors du téléchargement, si vous ne parvenez pas à télécharger une présentation, l’éditeur a peut-être supprimé le fichier de son serveur.Pendant le téléchargement, si vous ne parvenez pas à obtenir une présentation, le fichier a peut-être été supprimé par l’éditeur.

F I N

Plus de contenu associé

Transcription de la présentation
  1. Outage Scheduling Before and After Events Ebby John CenterPoint Energy

  2. Cancelling Outages During Events • Requested by ERCOT or Initiated by Transmission Owner • Due to Short Supply, Storms, Other • Reliability of ERCOT Grid • Reliability of Local Network • Safety

  3. Cancelling Outages During 02-02-2011 Event • Due to forecasted extreme cold weather, CNP began cancelling next day planned outages on 01-31-2011. • Evaluated conditions each day and cancelled outages for next day • Canceled outages for week 02-07-2011 due to second wave of extreme cold.

  4. Concerns with Outage Restoration • Once an outage is cancelled, Protocols require resubmitting with at least 3 days notice. • Delays with Equipment and Personnel mobilized in the Field • Maintaining an outage in the OS that has been canceled in the field would produce inaccurate EMS and Market results.

  5. Lessons Learned • ERCOT has been working with Equipment Owners To manage Outage Coordination during Emergency Events. • ERCOT needs to have a clearly defined process to make restoration easier and more predictable. • Suggestions • Shorter Approval turnaround • Make use of Forced Outage process • Super User capability in OS for ERCOT Operator • New Outage Scheduler state for temporary hold.