STORM RESTORATION REPORTING TO FEMA

STORM RESTORATION REPORTING TO FEMA. Gary Hurst Manager, Corporate Accounting hurstgr@epb.net. APRIL 27 STORM FACTS. 129,515 HOMES/BUSINESSES LOST POWER 8,966 ELECTRIC LOCATIONS DAMAGED 1,130 BROKEN POLES REPLACED 415 TRANSFORMERS REPLACED 193 OIL SPILLS CLEANED UP

hila
Télécharger la présentation

STORM RESTORATION REPORTING TO FEMA

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. STORM RESTORATIONREPORTINGTOFEMA Gary Hurst Manager, Corporate Accounting hurstgr@epb.net

  2. APRIL 27 STORM FACTS • 129,515 HOMES/BUSINESSES LOST POWER • 8,966 ELECTRIC LOCATIONS DAMAGED • 1,130 BROKEN POLES REPLACED • 415 TRANSFORMERS REPLACED • 193 OIL SPILLS CLEANED UP • 58 MILES OF ELECTRIC LINE REPLACED • $25,000,000 STORM RESTORATION COSTS

  3. PRE-STORM CONSIDERATIONS • UNIQUE FERC ACCOUNTS • 5616 – TRANSMISSION DISPATCHING (STORM) • 5816 – DISTRIBUTION DISPATCHING (STORM) • 5937 – OH LINE MAINTENANCE (STORM) • 5997 – FIBER/SMART GRID (STORM) • 9308 – SUPPORT (STORM) • SINGLE WORK ORDER FOR CONSTRUCTION REQUESTS (CRs) • MUTUAL AID TEMPLATE (APPA) • BOILER PLATE CONTRACT FOR CONTRACTORS

  4. STORM RESTORATION COSTS UTILITYFEMA ADMINISTRATIVE COSTS CATEGORY A CONTRACTOR COSTS CATEGORY B CREDIT CARDS/PETTY CASH/CHECKS CATEGORY F EQUIPMENT COSTS BY COUNTY LABOR COSTS CRs MATERIAL COSTS PREMISE OUTAGE TRANSFORMERS/SPILLS/SALVAGE

  5. ADMINISTRATIVE COSTS • WAS 3% OF OTHER COSTS, NOW ACTUAL COSTS • COSTS TO PREPARE SUPPORTING DOCUMENTATION • OPERATING COSTS TO VERIFY RESTORATION EFFORT • COSTS TO ANSWER NUMEROUS QUESTIONS • COSTS TO MODIFY DOCUMENTATION • ALLOCATE TO CATEGORIES A, B, AND F • EPB ADMIN COSTS: TN - $28K, GA - $15K

  6. CONTRACTOR COSTS • CATEGORY A - TREE TRIMMING • CATEGORY B - MUTUAL AID FROM OTHER UTILITIES • CATEGORY F – ALL OTHER CONTRACTORS • REQUIRED DOCUMENTATION • CONTRACTS • MUTUAL AID AGREEMENTS • INVOICES • SEPARATE STORM INVOICE • INVOICE WITH STORM COSTS IDENTIFIED BY STORM CR/FERC • LABOR, EQUIPMENT, MATERIALS, TRAVEL, FUEL, LODGING, MEALS • TIMELY • PAYMENT VERIFICATION – COPIES OF ALL CHECKS/WIRE TRANSFERS: TN - $15.1 MILLION, GA - $1.3 MILLION

  7. CREDIT CARDS/PETTY CASH/CHECKS • CATEGORY B • FUEL - $4k (CAN INCLUDE IF NOT IN VEHICLE HOURLY RATE) • MEALS - $280k • LODGING - $362k • MISCELLANEOUS - $0k • MATERIAL - $40k • MOVED TO EPB MATERIAL COSTS

  8. EQUIPMENT COSTS • CATEGORY F • LOWER OF FEMA OR UTILITY EQUIPMENT RATES – HOURLY RATES BY CLASS • EQUIPMENT USAGE MUST BE DETAILED BY HOURS PER DAY • EACH PIECE OF EQUIPMENT MUST HAVE A DRIVER IDENTIFIED FOR EACH DAY OF USE • DETAILED EQUIPMENT RECORDS MUST TIE TO DETAILED LABOR RECORDS

  9. LABOR • CATEGORY B • PERSONNEL SUPPORTING STORM RESTORATION EFFORT • OVERTIME ONLY UNLESS WORKING UNSCHEDULED TIME • CATEGORY F • PERSONNEL IN THE FIELD WORKING TO RESTORE SERVICES • REGULAR AND OVERTIME BOTH ELIGIBLE • INCLUDE NAME, JOB DESCRIPTION, RATE OF PAY, HOURS OF REG-1.5-2.0 BY DAY, TOTAL DOLLARS PER EMPLOYEE PER DAY, SORT ALPHABETICAL • MUST PROVIDE TIME SHEETS AS REQUESTED • SALARIED PERSONNEL NOT ELIGIBLE

  10. CATEGORY B LABOR • TEMPORARY EMPLOYEES/RETIREES • FOOD SERVICE • MATERIAL MANAGEMENT • OTHER • NON-UNION PERSONNEL • CALL CENTER PERSONNEL • IT SUPPORT PERSONNEL • OTHER • UNION PERSONNEL • MATERIAL HANDLERS • DISPATCHERS • OTHER

  11. CATEGORY F LABOR • TEMPORARY EMPLOYEES/RETIREES • BIRD DOGS/SCOUTS • LINEMAN • OTHER • NON-UNION PERSONNEL • BIRD DOGS/SCOUTS • LINEMAN • OTHER • UNION PERSONNEL • LINEMAN • SUBSTATION TECHNICIAN • OTHER

  12. OTHER LABOR CONSIDERATIONS • COPY OF UNION CONTRACT • OVERTIME POLICY FOR EXEMPT EMPLOYEES DURING “STORM RESTORATION” EFFORT • FRINGE BENEFIT ANALYSIS • MUST EXCLUDE EQUIPMENT MAINTENANCE PERSONNEL IF INCLUDED IN EQUIPMENT RATES • MUST PROVIDE INVOICES FROM TEMP AGENCIES FOR ALL TEMPORARY STORM WORKERS

  13. MATERIAL COSTS • CATEGORY F • NO OVERHEADS ALLOWED • PROVIDED • BY DAY • QUANTITY • DESCRIPTION • DOLLAR AMOUNT • MUST PROVIDE PICK TICKETS AS REQUESTED

  14. TRANSFORMERS/SPILLS/SALVAGE • LIST EACH TRANSFORMER REPLACED • POLE NUMBER • STOREROOM ITEM # • TRANSFORMER SIZE • STATUS – REPAIRED/DAMAGED BEYOND REPAIR • REPAIR/REPLACEMENT COST • PCB OIL TEST (PPM) • SALVAGE VALUE/DISPOSAL COST • HOW YOU DISPOSED OF OIL AND DIRT • INVOICE FROM DISPOSAL COMPANY • INVOICE FOR SALE OF SALVAGE -WIRE, ETC

  15. THE END