The BES project has successfully completed Phase 1 on schedule as of October 2004, which included the purchase of Oracle modules for customer online interactions and necessary hardware. A subset of 275 IEL customers is now utilizing the new software. For Phase 2, targeted for the first quarter of 2005, non-US IEL customers will be added, expanding existing functionalities. Phase 3, expected by Q3 2005, will see further software integration and new electronic offerings. Phase 4 aims to capture requirements for customer-facing applications by Q3 2005.
E N D
IEEE ITSC Update IEEE IT Department 08-November-2004
Business Entity System (BES) Project Status • Phase 1 • Completed On Schedule - Oct 2004 • Included purchase of Oracle modules (Customer On-line, Contracts & Data Librarian) and necessary system hardware & support software • Subset of IEL customers (275) are now being processed using new software • Phase 2 • Target 1st Quarter 2005 – Tracking On Schedule • Add Non US IEL customers • Expand the functionality to include additional electronic only package - ASPP & POP customers
Business Entity System (BES) Project Status • Phase 3 • Target 3RD Quarter 2005 • Continues software integration with purchase of additional Oracle modules (Advance Pricing, Bill of Materials & Sales Reporting) • Functional integration to be expanded to include new electronic offerings (eg. Enterprise) and print subscription ordering & fulfillment • Will provide enhanced service integration, sales reporting, service and operational efficiencies • Phase 4 • Capture requirements – 3rd Quarter 2005 • Include customer facing self-service applications and integration into content delivery platform (Xplore)
BMS Project Next Steps • Update to FinCom – Ben Johnson 25-Sep-04 • Receive Vendor response to RFP 29-Sep-04 • Receive Volunteer feedback on requirements 15-Nov-04 • Finalize requirements and Define Scope for BMS Phase I Nov 2004 • Complete Preliminary Vendor Presentations Nov 2004 • Confirm Preliminary Vendor Cost projections Nov 2004 • Obtain Preliminary Board Approval on Budget Nov 2004 • Confirm Scope and budget information based on POC Feb 2005