The kick-off meeting held in June 2004 focused on establishing the project's structure and the FPP changes. Key highlights included updates from WP5 leader TID and A1 leader, along with discussions on delays, budget changes, and new requests regarding the Celtic work plan. The meeting emphasized standardization and set up an online collaboration environment. Preparations for upcoming workshops and periodic meetings were outlined, alongside defining home networks and collaboration among partners. This document captures crucial inputs and action items for future progress.
E N D
Kick-off Conclusions Kick-off meeting June 2004
Project structure and FPP (changes) • WP5 leader TID, Elisa A1 leader • Delay M and D • Budget changes • New changes requests to the Celtic.
Work plan (first months) WP0 • Set up of framework • Relationship with other projects • Standardization • Set on-line colab environment. • Take in mind: Encompas standardization v 0.1
Work plan (first months) WP1 • Provide BB and aplic catalogue • Workshop Sep.
Work plan (first months) WP2 • Meet in WP2. Agree of architecture. • Involvement of Wp1 and Wp3 • Same place to workshop Wp1 (Sep)
Work plan (first months) WP3 • Periodic meeting every months • 22 June 1 meeting • Sync Wp1 and Wp3.
Work plan (first months) WP4 • Meeting defining the in home networks • Partners + services invloved: FT • October
Work plan (first months) WP5 • Planning • Indication (BB) about infrastructures (before Wp1 meeting). • Meeting just after Wp1 meeting.
Meetings calendar • Next Plenary meeting • Hosted by France Telecom • 01/2005
Web repository / online collaboration environment. • Invitation during June • First version available in July • Feedback needed for improvements