Leak detection for Liquid Pipelines - Lots of talk – How well can it really work?

Leak detection for Liquid Pipelines - Lots of talk – How well can it really work?. Pipeline Safety Trust Conference November 2011 New Orleans, LA. Harold Winnie, CATS Manager (Central Region). Agenda. Protecting People and Environment Federal Code 49 CFR part 195

Télécharger la présentation

Leak detection for Liquid Pipelines - Lots of talk – How well can it really work?

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Leak detection for Liquid Pipelines - Lots of talk – How well can it really work? Pipeline Safety Trust Conference November 2011 New Orleans, LA Harold Winnie, CATS Manager (Central Region)

  2. Agenda • Protecting People and Environment • Federal Code 49 CFR part 195 • §195.444 CPM leak detection • Advisory Bulletin 10-01 • §195.446 Control room management • API 1130 • Resources

  3. PHMSA's approach to protecting people and the environment. • Pipeline leak detection is one of the many layers of protection • Operators required to deploy a comprehensive set of safety measures to protect the public and the environment • effective means of identifying and responding to hazardous liquid pipeline leaks at the earliest possible time. • Pipeline operators are continuously improving the cumulative performance of these interconnected layers of protections • including advances in leak detection systems.

  4. Protections Include • Customized leak detection technology deployment; • Periodic risk-based assessment and defect repair prioritized by environmental and safety consequences; • Corrosion management; • Pipeline right-of-way surveillance; • Public awareness activities resulting in enhanced citizen leak condition recognition and response; • Emergency preparedness and coordinated response, including ongoing liaison efforts with emergency responders; • A review and incorporation of lessons learned from accident analyses and investigations.

  5. Direct Regulatory References CPM • 195.2 Definitions, Computation Pipeline Monitoring • 195.134 Design Requirements, CPM Leak Detection • 195.444 Operation and Maintenance, CPM Leak Detection • 195.452(i)(1) Integrity Management, General Requirements • 195.452(i)(3) Integrity Management, Leak Detection • 195.452(i)(4) Emergency Flow Restricting Devices

  6. Federal Code 49 CFR Part 195 §195.444 CPM leak detection. • Each computational pipeline monitoring (CPM) leak detection system installed on a hazardous liquid pipeline transporting liquid in single phase (without gas in the liquid) must comply with API 1130 in operating, maintaining, testing, record keeping, and dispatcher training of the system.

  7. Advisory Bulletin ADB-10-01 • Advising and reminding hazardous liquid pipeline operators • importance of prompt and effective leak detection capability • in protecting public safety and the environment. • Operating plans and procedures should include the performance of an engineering analysis • determine if a computer-based leak detection system is necessary to improve leak detection performance and line balance processes. • Engineering analysis determines a system would not improve leak detection performance and line balance processes • the operator should perform the periodic line balance calculation process outlined herein and take any other necessary actions required to ensure public safety and protect the environment.

  8. §195.446 Control Room Management. (a) Each operator must have and follow written control room management procedures that implement the requirements of this section. • Operator must develop the procedures no later than August 1, 2011, and must implement according to the following schedule. • The procedures required by paragraphs (b), (c)(5), (d)(2) and (d)(3), (f) and (g) implemented no later than October 1, 2011. • The procedures required by paragraphs (c)(1) through (4), (d)(1), (d)(4), and (e) implemented no later than August 1, 2012. • The training procedures required by paragraph (h) must be implemented no later than August 1, 2012, except that any training required by another paragraph of this section must be implemented no later than the deadline for that paragraph.

  9. §195.446 • (a) General • (b) Roles and responsibilities. • (c) Provide adequate information • (d) Fatigue mitigation • (e) Alarm management • (f) Change management • (g) Operating experience • (h) Training • (i) Compliance validation • (j) Compliance and deviations.

  10. API 1130 4.2.1 Performance Metrics • Selection of a CPM system for a given pipeline involves evaluation of the required and expected (or estimated) performance of the system.  • The following categorizes and describes performance metrics for selection consideration. • Reliability. • Sensitivity. • Accuracy. • Robustness.

  11. Other Documents • API 1149 Pipeline Variable Uncertainties' and Their Effect on Leak Detectability • CSA Z662 Oil and Gas Pipeline Systems

  12. Available Resources • PHMSA Website: • http://www.phmsa.dot.gov • National Pipeline Mapping System: • http://www.npms.phmsa.dot.gov/ • Stakeholder Communications: • http://primis.phmsa.dot.gov/comm/ • Federal Regulations: • http://www.gpoaccess.gov/cfr