1 / 10

Reliability Assessment of Wallingford Units 2-5

Reliability Assessment of Wallingford Units 2-5. Presentation to NEPOOL Reliability Committee May 6, 2003. Wallingford Units 2-5. Simple cycle combustion turbines (LM 6000) installed end of 2001, beginning of 2002 Located in Wallingford, CT; eastern edge of Greater SWCT

inez
Télécharger la présentation

Reliability Assessment of Wallingford Units 2-5

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Reliability Assessment of Wallingford Units 2-5 Presentation to NEPOOL Reliability Committee May 6, 2003

  2. Wallingford Units 2-5 • Simple cycle combustion turbines (LM 6000) installed end of 2001, beginning of 2002 • Located in Wallingford, CT; eastern edge of Greater SWCT • Total Capacity:165.5 MW (S), 198 MW (W) • Fuel: natural gas

  3. Background for Assessment • Owner: PPL Wallingford Energy LLC • On January 16 owner applied to FERC for Reliability Must Run Cost of Service (RMRCOS) contract to be effective February 1 • Owner submitted 18.4 Application April 1 to ISO for deactivation of Units 2, 3, 4 and 5 effective July 1 • 18.4 Application caused by uncertainties of RMRCOS approval and its effective date

  4. Wallingford Assessment • ISO examined the need for the 4 units using 3 methods for assessing reliability: • Generation Resource Adequacy: LOLE • Transmission/Operating Reserve Adequacy: Day Ahead Unit Commitment (DAUC) • Security Constrained Economic Dispatch (SCED)

  5. Assumptions • 2003 CELT Reference Peak Loads (50/50 Probability) • 2003: 25,120 MW • 2006: 26,290 MW • Import Limits • CT: 2200 MW • SWCT: 2000 MW (2003); 2600 MW (2006) • Milford Power operation uncertain: 490 MW • Long Island 1385 cable in service

  6. LOLE Results

  7. DAUC Results for Connecticut *Millstone 2 & 3

  8. DAUC Results for Greater SWCT * Norwalk Harbor + BEC ** SWCT Phase I 345 kV Line

  9. SCED Results: Greater SWCT *Nor Har 2 + BEC **BPH 3 + BEC

  10. Conclusions • Method showing greatest need for Wallingford units establishes the system need. • 2003 • DAUC and SCED Results: Existing system deficient with Wallingford Units 2-5 • SCED Results: Existing system with Milford Power operating is deficient with Wallingford units • 2006 • DAUC CT Results: Existing system is deficient with Milford

More Related