The Kentucky Transportation Cabinet (KYTC) and the Department of Corrections (DOC) initiated a cooperative Inmate Work Crew Program in 2006, benefiting the Commonwealth by utilizing inmate labor for various public projects. Crews consisting of 5-10 inmates, supervised by correctional officers, engage in activities such as trash pickup, landscaping, and maintenance. The program not only provides work experience for inmates but also results in significant cost savings for the state, generating over $17 million annually compared to contractor crews while ensuring the safety and care of crew members.
E N D
KYTC/DOC Inmate Work Crew Program Darrell L. Burks Roadside Environment State Administrator June 8, 2011
Cooperative Effort To Benefit The Commonwealth • KYTC needed work crews • DOC needed work for inmates • Program initiated spring 2006 • MOA between KYTC and DOC • Win-Win Situation
DOC Provisions • Inmate work crews (5 -10 inmates/crew) • Correctional Officer to supervise work crew • Lunch and drinks for crew members • Means of communication • Medical care for crew members
KYTC Provisions • Work experience program • Per diem reimbursement for inmate meals • Reimbursement of Correctional Officer’s salary and benefits • Transportation • All tools, equipment, and supplies • Safety equipment and PPE • Safety training for inmates and Officer • Training for KYTC staff
Current Inmate Work Crews • State Prisons • 10 of 13 institutions • 17 inmate work crews • Private Prisons (CCA) • 1 of 3 institutions • 2 inmate work crews • Local County Jails • 21 of 75 county/regional jails • 22 crews
Work Activities • Trash pickup along roadways • Tree trimming and brush removal • Weed-eating and grass trimming • Guardrail repair • Building maintenance repair • KYTC landscape and grounds maintenance • Equipment maintenance • Sight distance clearing • Maintenance of roadway drainage systems
Crew Rate/Day = $184.87 260 work days/year Annual crew cost = $48, 066.20 Crew Rate/Day = $1800.00 260 work days/year Annual crew cost = $468,000.00 DOC Crew vs. Contractor Crew
Annual Labor Savings • $ savings /work crew = $419,933.80 • Grand Total Annual $ Labor Savings (41 DOC crews vs. 41 contractor crews) $17,217,286
Darrell L. BurksRoadside Environment State AdministratorKentucky Transportation Cabinet200 Mero Street, Third Floor EastFrankfort, KY 40622502-564-4556Darrell.Burks@ky.gov