Superintendent’s Proposed Capital Improvement Plan 2009-2019

Superintendent’s Proposed Capital Improvement Plan 2009-2019. November 6, 2008. Does the school division have any capital needs for the 2009-2019 planning period?. YES!. How Are the School Division’s Capital Needs Outlined in the CIP?. Projects listed by middle school planning area

ismail
Télécharger la présentation

Superintendent’s Proposed Capital Improvement Plan 2009-2019

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Superintendent’s Proposed Capital Improvement Plan 2009-2019 November 6, 2008

  2. Does the school division have any capital needs for the 2009-2019 planning period? YES!

  3. How Are the School Division’s Capital Needs Outlined in the CIP? • Projects listed by middle school planning area • Project Summary Tables • Table 39 in current year dollars • Table 39A in inflation dollars (5.6%) • Major maintenance projects listed by priority based on need (by project and by year)

  4. Major Maintenance Modernizations New Schools CIP Priority ProjectsYears 1-5 (2009-14)

  5. Why Are Major Mechanical/Maintenance Repairs Needed? • Systems and parts have a finite life • Scarcity or unavailability of older parts • Increased operational costs • Increased operational failures (example: no heat more frequently and for longer periods) • No temporary fix for failed roofs or HVAC systems

  6. Why Are Modernization Projects Needed? • Aging facilities that require updating • Replacement of interior finishes (flooring, lighting, doors & hardware, lockers, paint, etc.) • Installation of new technology • Replacement of exterior finishes (parking lot surfaces, exterior lighting, canopies, etc.) • Improve safety

  7. Why are New School Projects Needed? • Reduce reliance on portable classrooms • Provide additional permanent • classroom space • Ease overcrowding of core • facilities at existing schools It is important to note staff reviews enrollment/housing/population trends annually to determine new school needs and proposed timelines

  8. Year 1: CIP Projects (2009-10)$19,102,300 Major Maintenance $18,180,400 *Mixing boxes only

  9. Year 1: CIP Projects (2009-10)$19,102,300

  10. Year 1: CIP Projects (2009-10)Highlights • 95% of costs are for major maintenance (HVAC & roof replacements) • 5% of costs are for CAS repairs and repaving at 3 schools • No modernization, addition and/or renovation projects • No new school projects $19,102,300

  11. Year 2: CIP Projects (2010-11)$27,862,500 Major Maintenance $14,313,400

  12. Year 2: CIP Projects (2010-11)$27,862,500

  13. Year 2: CIP Projects (2010-11)Highlights • 51% of costs are for major maintenance (HVAC & roof replacements) • No construction costs for facilities but does include A/E costs for: • modernization at 2 schools • the 8th high school (Elbow Rd./Centerville Trpke.) $27,862,500

  14. Year 3: CIP Projects (2011-12)$53,439,400 Major Maintenance $9,291,100

  15. Year 3: CIP Projects (2011-12)$53,439,400

  16. Year 4: CIP Projects (2012-13)$230,627,900 Major Maintenance $6,243,100

  17. Year 4: CIP Projects (2012-13)$230,627,900

  18. Year 5: CIP Projects (2013-14)$48,396,400 Major Maintenance $17,233,800

  19. Year 5: CIP Projects (2013-14)$48,396,400

  20. 2009-2014 CIP Summary • Most pressing funding needs are: • Major maintenance projects • If not funded in a timely manner, this portion of the CIP will increases as more needs arise • Modernization of aging facilities • 8th high school (Elbow Rd./ Centerville Trpke.) to provide relief to IRHS, OSHS, HHS & GBHS

  21. 2009-2014 Five-Year Grand Total(Inflated Dollars) $466,751,400

  22. Extended Public Hearing & Work Session Coverage7:00PM at SAB Monday, Nov. 24, 2008 & Final Action Monday, Nov. 10, 2008

  23. Additional copies of the CIP are available: • Planning & Development Dept. • www.cpschools.com • All branches of the public library CIP 2009-19

  24. What Sources are Used to Assist with Student Enrollment Projections? • Review enrollment/housing/population trends on a local, regional and national scale including: • CPS historical data • City Planning Dept. data (comprehensive plan) • Hampton Roads Planning District Commission • UVA’s Weldon Cooper Center • VA Dept. of Ed. • ODU State of Hampton Roads Annual Report • US Census • Surrounding school divisions

  25. Factors Affecting Enrollment • Basics: economy, growth rate, birth rate, migration • US Dept. of Ed.: VA school enrollment expected increase 13% (2005-17) • UVA Weldon Cooper Center: VA enrollment will increase thru 2012 • Grades K-7 increase • Grades 8-9 small increase • Grades 10-12 decline