330 likes | 543 Vues
Allocating Transmission Line Costs. Case Study of: ICC v . FERC 576 F.3d 470. Presented 11/29/09 by: Daniel Hergott email: drhergott@gmail.com. ICC v. FERC Presentation Overview. The Problem FERC Ruling 7 th Circuit Majority Holding 7 th Circuit Dissent
E N D
Allocating Transmission Line Costs Case Study of: ICC v. FERC 576 F.3d 470 Presented 11/29/09 by: Daniel Hergott email: drhergott@gmail.com
ICC v. FERC Presentation Overview • The Problem • FERC Ruling • 7th Circuit Majority Holding • 7th Circuit Dissent • Consequence and Remaining Questions Relief on Chicago sub station across from the Daley Center built in the1930’s during WPA
1. The General Problem: We Need More Transmission Lines • U.S. electric grid is old and needs to be updated • But to what end? DOE Map showing Mid-Atlantic Area Congestion Corridor
Transmission Line Challenges • Mitigating Environmental Impact • Wide right of ways • Aesthetics • Siting • Physical Geography • Easements • Local opposition • Coordinating • State & Local Agencies • RTO Members • And . . .
Expensive to Build – Who Pays? • How should the pay structure be designed? • What role do regulators play in rate design? • How do we regulate the regulators?
“Project Mountaineer” • 550 to 900 miles of 500 kV and 765 kV transmission lines (all in the East) • Cost: $3.3 to $3.9 billion • Who should pay?
License Plate Rate Design Transmission lines are paid by: • Utilities in the sub-regional zone • Utilities that benefit from the new transmission
According to PJM: “Although a large number ($3.3 to $3.9 billion), if such costs are spread to all customers within the PJM footprint, the cost to a typical retail customer would amount to only one mill/kwh.” -- Karl V. Pfirrmann, president of the PJM Western Region*
Postage Stamp Rate • Costs are rolled-in and allocated to all customers according to each customer's share of the region's load
“Project Mountaineer” “Super-highway” to Bring Low Cost Coal Resources to Market • “PJM[‘s] new initiative [utilizes the] regional transmission planning process to . . . develop an efficient transmission “super-highway” to bring low cost coal resources to market.” -- Karl V. Pfirrmann, president of the PJM Western Region*
How Much Does Chicago Benefit From “Project Mountaineer”? • New Market For Energy Sales • Increased Reliability in the PJM Network • Cost Sharing for All Lines Above 500 kV
2. FERC’s Ruling:PJM Interconnection, L.L.C., 119 F.E.R.C. ¶ 61,063 (2007) • Cost allocation is not an exact science • It involves judgment of a myriad of facts • We all benefit from a more reliable grid • 500 kV and above transmission creates sufficiently broad benefits J. Wellinghoff, FERC Chairman
FERC’s Rate Plan: New facilities at or above 500kV: • Region-wide Postage Stamp Rate • New facilities below 500 kV: • License Plate Rate Design
FERC’s Policy Goals: • Encourage the development of “backbone” infrastructure • Provide cost certainty to support new investment • Eliminate recurring litigation over cost allocation • Provide incentives to construct new transmission
3. ICC Takes its Complaint to the 7th Circuit “Not so fast Wellinghoff!” J. Posner of the 7th Cir.
Federal Power Act 16 USCS § 824e(a): Whenever the Commission . . . shall find that any rate . . . is unjust, unreasonable, unduly discriminatory or preferential . . . the Commission shall determine the just and reasonable rate. Power of Commission to fix rates and charges:
7th Circuit Holding:Remanded • “[Under the APA] our review is deferential, we require only that the agency have made a reasoned decision based upon substantial evidence in the record.” • “Not even the roughest estimate of likely benefits to the objecting utilities is presented.” • “FERC is not authorized to approve a pricing scheme that requires a group of utilities to pay for facilities from which its members derive no benefits.”
Calculating Benefit • The Commission has a duty to: • Compare the costs assessed against a party to the burdens imposed or benefits drawn by that party • If it cannot quantify the benefits: • But has articulable and plausible reasons to believe that the benefits are at least roughly commensurate with those utilities’ share of total electricity sales, then fine; • But FERC cannot avoid comparing the costs and benefits
4. Dissent: J. Cudahy • FERC did not explain how PJM’s members benefit from a reliable network because no court has ever required it to do so. • Upgrades to the grids reliability were presumed to benefit all of the network’s members.
Big Picture • U.S. grid is inadequate and urgently needs to be upgraded • Grid was not built for long-distance transmission • Demand for renewable energy poses additional transmission challenges • Long-distance transmission is accomplished most efficiently by the highest levels of voltage—500 kV and above
Electricity Grid Needs a “Backbone” R. Nader, Presidential Candidate
Dissent’s Final 2 Points • FERC isin a better position to improve a deficient transmission grid than this court • “Explanations come to an end somewhere” – L. Wittgenstein L. Wittgenstein
5. Consequence and Remaining Questions • How would the Supreme Court rule? • Who is in the best position to improve the electric grid? • How should it be improved? • Renewable Energy • Smart Grid (efficiency and conservation) • Cost/Benefit Analysis
C.J. Roberts May Know • Grant Cert? • Circuit Split? • How do we regulate the regulators (Chevron Analysis)? • “There is no neutral or inherently fair allocation of fixed costs, as the history of rate design amply demonstrates.” J. Roberts D.C. Circuit* C.J. Roberts
Chevron 2-Step Ambiguity: Has Congress directly addressed the question at issue? Reasonable: Is the agency's action based on a permissible construction of the statute?
I DON’T MAKE PREDICTIONS! Administrative Law is not for SISSIES! Nino is WRONG.
Who Is In the Best Position to Improve the Electric Grid? • FERC: • Expertise • Promote Renewable Energy • Develop Smart Grid • Courts: • Incremental Change • Protect Regional Concerns • Congress: • Address National Issues • Set Clear Policy Goals • Democratic Accountability
How Should the Grid Be Improved? • Bigger is Not Necessarily Smarter • Distribution Improvements • Decentralize • Environmental Impact • Renewable Energy • State Renewable Portfolio Standards • Long-Distance Transmission • Cost/Benefit Analysis • Carbon Tax • Economic Benefits • Follow the Money
Goals for a BRIGHT FUTURE • Reduce GHG’s • Reduce Reliance on Fossil Fuels • Improve Grid Reliability, Energy Efficiency, and the Economy