1 / 34

Tom Overbye Dept. of Electrical and Computer Engineering

EVALUATING THE POTENTIAL IMPACT OF TRANSMISSION CONSTRAINTS ON THE OPERATION OF A COMPETITIVE ELECTRICITY MARKET IN ILLINOIS. Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois at Urbana-Champaign Champaign, IL overbye@ece.uiuc.edu May 13, 2005. Overview.

ivor-davis
Télécharger la présentation

Tom Overbye Dept. of Electrical and Computer Engineering

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EVALUATING THE POTENTIAL IMPACT OF TRANSMISSION CONSTRAINTS ON THE OPERATION OF A COMPETITIVE ELECTRICITY MARKET IN ILLINOIS Tom Overbye Dept. of Electrical and Computer Engineering University of Illinois at Urbana-Champaign Champaign, IL overbye@ece.uiuc.edu May 13, 2005

  2. Overview • Presentation summarizes results of UIUC portion of the project, which was done in close collaboration with ANL. • Goal was to do detailed security constrained optimal power flow (SCOPF) studies to assess the impact of transmission system constraints in the Illinois transmission grid • Studies were done using PowerWorld Simulator with SCOPF add-on

  3. Security Constrained OPF • The SCOPF provides an “optimal” system dispatch that satisfies the base case and contingency constraints; can uses either the “ac” or “dc” power flow approach • used dc approach in this study • The bus locational marginal prices (LMPs) can then be directly determined from the SCOPF solution • the LMPs tell the incremental cost of supplying one more MWh to a bus

  4. Three Bus OPF/LMP Example

  5. Unenforceable Constraints Must Be Considered in Solution

  6. LP-based SCOPF • LP-based SCOPF used full contingency processing to determine the contingent violations, and then iterated between the power flow to take into account system non-linearities (phase shifter limits) and LP with linearized model to redispatch controls • an “outer loop” was used with SCOPF to resolve the contingencies with the optimized system

  7. Constraints were Enforced in LP using Slack Variables

  8. System Model • Model was constructed from 2003 summer peak power flow case, with utility modifications • original case contained about 42,700 buses • To reduce computation, a 12,925 bus, 1790 generator “equivalent” was created • equivalent covered region roughly bounded by Minnesota, Missouri, Tennessee, Ohio and Michigan • full Illinois system was included in the model

  9. Illinois System Diagram

  10. System Model, continued • In-state generator cost information was provided by ANL • Out-of-state generator cost information was determined by UIUC using a variety of sources • Fuel-costs were as provided by ANL • Hourly system load variation was as provided by ANL to be equal to assumed 2007 conditions • Phase shifters were allowed to vary in the SCOPF solution

  11. Contingencies • Each solution enforced 1360 contingencies provided by the Illinois Utilities

  12. Solution Overview • Initial SCOPFs were solved for each hour for the assumed 2007 conditions with the assumption that all generators submitted bids equal to marginal costs • data was calculated and stored for each bus for each hour  hundreds of millions of numbers

  13. Solution Problem • Results showed Illinois to be a net importer of power, which did not match historical data for recent • Potential reasons for this discrepancy • potentially inaccurate out-of-state cost estimates • potentially inaccurate fuel costs • insufficient model size (e.g., east coast markets were not included in the study)

  14. Summary of Statewide Results:Solution One

  15. Hourly Interchange for 1st Quarter

  16. Modified Solution • To access impact of interchange skew on results a second 2007 case was run with the out-of-state generator cost data increased slightly • this changed Illinois to being a net importer • While these changes did modify the results, they had little impact on the congestion regions

  17. Summary of Statewide Results:Solution Two

  18. Hourly Interchange for 1st Quarter of Modified Solution

  19. Interpretation of Results • A point to stress in understanding the results is the details matter. For example, whether a particular line was binding, and hence the cause of high LMPs in a region, was dependent upon many factors, including the line’s limit, the contingency set, and availability of post-contingent operating procedures

  20. Interpretation of Results, cont. • It should also be stressed that there were LOTS of results. Hence trying to summarize the results was a major challenge!

  21. Interpretation of Results, cont. • Key results were a listing of the binding constraints, and the resultant LMPs

  22. Illinois Transmission System Congestion Regions: First Case

  23. Illinois Transmission System Congestion Regions: Second Case

  24. Congestion Region Details • Details about each congestion region are included in the report • Example: Kankakee congestion region Due to congestion on blue Davis Creek 345/138 kV transformer for 345-L17704_R-S contingency (loss of red transformer and several other devices)

  25. Profit Maximization • Profit maximization was studied at the 90% of peak load level, a level that would be reached about 80 hours per year • Profit maximization was tested by increasing generation bids at one or more generators, and then calculating the company’s revenue from its generators

  26. Profit Maximization Results • The only companies found to have the ability to increase their revenue were Midwest Generation, Ameren CILCO and CWLP

  27. Midwest Generation • One scenario is for the generators at Collins, Powerton and Waukegan to submit bids equal to marginal cost, and all others to submit bids equal to a multiplier times their marginal cost • Table on next page shows results

  28. Variation in Midwest Generation Relative Profit

  29. 90% Load LMPs with All Marginal Cost Bids

  30. 90% Load LMPs with Some Midwest Gen Bids 10 times Marginal Cost

  31. Ameren CILCO • Scenario considered was Edwards generators submit bids equal to a multiplier times their marginal cost; all others submit marginal cost • This causes a binding constraint on the Tazwell-East Peoria 138 kV line (contingencies are loss of Duck Creek-Tazewell 345 kV or loss of Tazewell-Powerton 345 kV) • Results assume the upgrade of the Tazewll-E.Springfield 138 kV line

  32. Ameren CILCO Results

  33. CWLP • If CWLP increased bids on all their plants eventually they would increase their revenue

  34. Conclusion • For many loading conditions the Illinois transmission grid will have congestion, resulting in LMP variation • For certain loading conditions some companies could increase their revenue by submitting bids substantially above their marginal cost

More Related