1 / 8

TE-EPC Budget Code Status 08-06-2009

TE-EPC Budget Code Status 08-06-2009. VALERIE MONTABONNET CERN. 68215 – Consolidation POPS Infrastructure [Jean-Paul] Planned: 2MCHF Committed: 1.9MCHF (2009-05) New needs 2009: 350kCHF 2010: 100kCHF 2011: 200kCHF Action: mail to Simon Baird [Jean-Paul].

Télécharger la présentation

TE-EPC Budget Code Status 08-06-2009

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TE-EPC Budget Code Status 08-06-2009 VALERIE MONTABONNET CERN V. Montabonnet

  2. 68215 – Consolidation POPS Infrastructure [Jean-Paul] • Planned: 2MCHF • Committed: 1.9MCHF (2009-05) • New needs • 2009: 350kCHF • 2010: 100kCHF • 2011: 200kCHF • Action: mail to Simon Baird [Jean-Paul]

  3. 68251: Consolidation – PSB Multipole Power Converters [Serge] • Committed: 750kCHF • 200kCHF already paid • 550kCHF will be paid when the ACAPULCO converters will be delivered at CERN (end 2009 – 2010) • Balance: 250kCHF for the FGC3, DIM cards procurement and installation works • Allocated budget: 860kCHF • Action: No

  4. 68550: Operation - LEIR power converters [Carlos] • Allocated budget: 45kCHF • Engaged: 57kCHF • Balance: -13kCHF • Orders in 2008 but payment in 2009 [SMILE, DANFYSIK, 250kVA spare transformer for the RF converter] • No more needs • Action: No more engagement to be done, mail to Lise Salvi, Dorothée [Valérie, Gilles] • 68712: Consolidation - LINAC3 Brukker power converters [Carlos] • Planned: 220kCHF, 250kCHF[2008] • Engaged: 272kCHF (2008 and 2009) • Budget overrun: 23% [due to EN-EL electrical distribution board renovation, ….] • No more needs • Action: No more engagement to be done, mail to Lise Salvi, Dorothée [Valérie, Gilles]

  5. 68725: CTF3 power converters (with laser phot. Diode) [Gilles] • Requested budget: 285kCHF • Operation: 56kCHF [Error] shall be 83kCHF • Consolidation – new converter request: 202kCHF • Allocated budget: 117kCHF • Action: Code to be managed only by TE-EPC [Christophe Mugnier / Lise Salvi]

  6. 68731: Linac4 klystron modulators [Carlos] • WP estimation: 250kCHF for 2009 • Requested: 340kCHF (included 2008 “avoir”) • Allocated budget: 150kCHF • Action: Allocated budget to be updated [Carlos, Lisa Salvi] • Code 68732: Linac4 quadrupole and steering power converters[Carlos] • WP estimation: 120kCHF for 2009 • Requested: 40kCHF • Allocated budget: 300kCHF • Comments: “L'estimation initiale des dépenses pour cette année était de 120 kCHF car on pensait placer un contrat de production pour ces alims à la fin de cette année et donc payer les 10% de sa valeur. Compte tenu des retards sur ce projet, suite au changements de responsabilités et indéfinition sur l'électronique, le groupe EPC a demandé 40 kCHF. »[Carlos] • Action: Allocated budget to be updated [Carlos, Lisa Salvi]

  7. 68733: Linac4 bending power converters [Carlos] • WP estimation: 10kCHF for 2009 • Requested: 35kCHF (10kCHF + “avoir 2008”) • Allocated budget: 90kCHF • Action: Allocated budget to be updated [Carlos, Lise Salvi] • Code 68734: Linac4 Septa high current pulsed converters [Carlos] • WP estimation: 50kCHF for 2009 • Requested: 80kCHF • Allocated budget: 100kCHF • Action: Allocated budget to be updated [Carlos, Lisa Salvi] • Code 68735: Linac4 3MeV test stand converters refurbishment [Carlos] • Requested: 30kCHF • Allocated budget: 50kCHF • Comments: “C. Rossi avec l'accord de Maurizio, a décidé d'utiliser ce code pour payer les dépenses associées avec l'installation de 5 convertisseurs additionnels au Stand Test 3 MeV) » • Action: Allocated budget to be updated [Carlos, Lise Salvi]

  8. 68736: Linac4 HV precision measurement facilities [Miguel] • Requested budget: 80kCHF • Allocated budget: 40kCHF • Action: Allocated budget to be updated [Carlos, Lise Salvi] • Code 68737: Linac4 Control electronics for power converters [Carlos] • WP estimation: 20kCHF for 2009 • Requested: 20kCHF • Allocated budget: 50kCHF • Action: Allocated budget to be updated [Carlos, Lise Salvi]

More Related