LQ session: Introduction Giorgio Ambrosio

BNL - FNAL - LBNL - SLAC. LQ session: Introduction Giorgio Ambrosio. LARP Collaboration Meeting 12 Apr. 8-10, 2009 Napa (LBNL). OUTLINE: LQ goals and WBS Overall LQ status Schedule and budget FY10 plans in last talk. Long Quadrupole. Main Features: Aperture: 90 mm

jase
Télécharger la présentation

LQ session: Introduction Giorgio Ambrosio

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BNL - FNAL - LBNL - SLAC LQ session: IntroductionGiorgio Ambrosio LARP Collaboration Meeting 12 Apr. 8-10, 2009 Napa (LBNL) • OUTLINE: • LQ goals and WBS • Overall LQ status • Schedule and budget • FY10 plans in last talk LQ session: Introduction – G. Ambrosio

  2. Long Quadrupole Main Features: • Aperture: 90 mm • magnet length: 3.6 m Goal: • Gradient: 200+ T/m Timeframe: • Original: • by the end of 2009 • Present: • 1st Long Quad test by the end of 2009 • Performance and reproducibility by the end of 2010 LQ session: Introduction – G. Ambrosio

  3. LQ WBS • Coils are being fabricated at FNAL and BNL • F. Nobrega (FNAL), and J. Schmalzle (BNL) • Quench protection and instr. design & proc. at LBNL • H. Felice • Shell structure: design, procur. & assembly at LBNL  P. Ferracin • Collar structure: procurement at FNAL  F. Nobrega • All LQ models to be tested at FNAL  G. Chlachidze LQ session: Introduction – G. Ambrosio

  4. Coil Fabrication Status • Found problem after coil #3 heat treatment • Performed analysis further analysis needed • Developed solution for LQS01 coils LQ02 coils Further analysis by core programs Coils 4 and 5 will be used for practice assembly Coils 6 to 9 will be used for LQS01 LQ session: Introduction – G. Ambrosio

  5. Status (cont.) • Coils: • found and solved issues with impregnation and instrument. • Coils #4 to #7 delivered to LBNL • Shell structure: • Assembled LQS with Al dummy coils (LQSD) • and tested it at LN • Quench protection: • Improved trace design based on coil fabr. feedback • tested protection heaters on coil 5 at LN, and firing units • Test prep: • Successful handling and test of LQSD • VMTF improvements in progress LQ session: Introduction – G. Ambrosio

  6. Start LQS01 assembly: June 9 Start LQS01 test: August 26 Note: reaction &impregnation of coils #12 and #13 not funded in FY09 LQS01 Schedule LQ session: Introduction – G. Ambrosio

  7. LQS01 Readiness Reviews • GOAL: Assess readiness for LQS01 assembly (by evaluating: choice of coils, structure, target pre-stress and assembly procedure) and test (test facility and test plan) • #1: “LQS structure and target pre-stress” • April 7, LBNL • #2: “LQ coil design and fabrication, & LQS01 assembly” • end of May/ June at FNAL • #3: “Test readiness and test plan”  PASSED Introduction – G. Ambrosio

  8. FY09 Budget Adjusted Original FY09 budget: 2,128 374 1,116 638 Why? LQ coil cost: • FY09 budget while plan was not defined • Estimates with no contingency • $5M max for magnet R&D LQ session: Introduction – G. Ambrosio

  9. “Project” monitoring • Weekly LQ Task Leaders • Status, progress, issues • Expenses monitoring • Based on LARP finance status reports (irregular this year) LQ session: Introduction – G. Ambrosio

  10. Next • More details about each task in next talks • FY10 options/plans and budget in last talk LQ session: Introduction – G. Ambrosio