SlideServe
Menu
Préférences
© SlideServe · v2026

Overview of Co-located Soil Chemical Sampling Approach

jcora avatar
5 diapositives · 72 Views · Jan 05, 2020

This overview focuses on the co-located soil sampling approach in Area IV & NBZ to enhance knowledge of chemical contamination, co-location with radionuclides, and streamline analysis processes. EPA and DOE collaboration expedites sampling efforts.

Overview of Co-located  Soil Chemical Sampling Approach - slide 1
01 / 5Overview of Co-located Soil Chemical Sampling Approach
1 / 17

Télécharger la présentation

Overview of Co-located Soil Chemical Sampling Approach
Une image / un lien ci-dessous est fourni (tel quel) pour télécharger la présentation

Politique de téléchargement : le contenu du site vous est fourni TEL QUEL pour votre information et votre usage personnel ; il ne peut être vendu, concédé sous licence ni partagé sur d’autres sites sans l’accord de son auteur.Le contenu vous est fourni TEL QUEL, pour votre information et votre usage personnel uniquement. Téléchargez la présentation en cliquant sur ce lien. Lors du téléchargement, si vous ne parvenez pas à télécharger une présentation, l’éditeur a peut-être supprimé le fichier de son serveur.Pendant le téléchargement, si vous ne parvenez pas à obtenir une présentation, le fichier a peut-être été supprimé par l’éditeur.

F I N

Plus de contenu associé

Transcription de la présentation
  1. Overview of Co-located Soil Chemical Sampling Approach Stephie Jennings, DOE October 12, 2010

  2. Agreement in Principle • Agreement in Principle states: • “Where EPA is already taking samples for radiologic contaminants as part of its Area IV and Northern Buffer Zone survey work, DTSC will arrange for analysis of split samples (paid for by DOE)”

  3. Objectives of Chemical Co-located Sampling • To provide an even greater level of knowledge about chemical contamination in Area IV and the NBZ • To take advantage of EPA’s efforts for soil collection in terms of timing • To begin to determine if chemical and radionuclide soilcontamination are co-located or are they separate problems?

  4. Why? • Due to volume needed for sampling the decision was made to co-locate samples instead of splits • Entire effort is prescriptive • EPA makes location decisions • DTSC approves sampling plan and approach • Answers questions about co-location of radionuclide and chemical contamination • Uses DOE’s existing contract with CDM to quickly be in the field with EPA

  5. Proposed Process • DTSC • Approves Sampling and Analysis Plan • Provides approval to proceed • EPA • Identifies soilsample locations with public • Collects soilsample for chemical analysis • Gives sample to CDM • DOE/CDM • Accepts soilsample from EPA • Procures laboratories for soil samplechemical analysis in collaboration with DTSC and with input from key stakeholders