1 / 103

Engineering Project Management

Engineering Project Management. Engineering Project Management. Define the terms project and project management , and differentiate between project and process management. Describe the causes of failed engineering / technology projects.

jhuggins
Télécharger la présentation

Engineering Project Management

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Engineering Project Management

  2. Engineering Project Management • Define the terms project and project management,and differentiate between project and process management. • Describe the causes of failed engineering / technology projects. • Describe the basic competencies required of project managers. • Describe the basic functions of project management. • Differentiate between PERT and Gantt chartsas project management tools.

  3. Overview • Describe eight activities in project management. • Define scope and write a statement of work,to document scope. • Use a work breakdown structure,to decompose a project into tasks. • Estimate tasks’ durations, and specify intertask dependencies on a PERT chart. • Assign resources to a project and produce a project schedule with a Gantt chart. • Assign people to tasks and direct the team effort • Use critical path analysis to adjust schedule and resource allocations in response to schedule and budget deviations. • Manage user expectations of a project and adjust project scope.

  4. What is your project management practice? • Burn the mid night oil ????? • 24-7 in order to meet the deadline!

  5. Your own experiences • From your past experiences, such as • Your C++ programming project • Subject based mini-project • Did you apply any project management skills? • Do you think a proper project management practice is necessary? • What is/are the most important factor(s) affecting the progress, or success of your project?

  6. Theory of project management

  7. Project, Project Management, and Process Management Project– a sequence of unique, complex, and connected activities having one goal or purpose and that must be completed by specific time, within budget (and other resources), and according to specifications/requirements.

  8. Project management • Project management– the process of scoping, planning, staffing, organizing, directing, and controlling the development of an acceptable system at a minimum cost within a specified time frame. The project management is a subset of management. • There are four (4) management functions: planning, organizing, directing, and controlling.

  9. Measures of Project Success SIX (6) criteria for project success: • The resulting system is acceptable to the customer • The system was delivered “on time.” • The system was delivered “within budget and allocated resources.” • The process and the final system is up to required standard. • All the documentation (i.e. reports) are well written and complied. • The system development process had a minimal impact on ongoing business operations. (in FYP cases, i.e. not have adverse effect on study of your other subjects)

  10. Some Common Causes of Project Failure • Complete failure in time management / project scheduling • Lack of commitment to the project • Depends on your expectation • Taking shortcuts through or around the system development methodology

  11. Some Common Causes of Project Failure • Poor expectations management (unlikely in a final year project) • Scope creep (範疇蔓延)–the unexpected and gradual growth of requirements during the project. • Feature creep(功能蔓延)–the uncontrolled addition of technical features to a system. • Premature commitment to a fixed budget and schedule • Are you willing to spend more than $1200?

  12. Causes of Project Failure • Poor estimating techniques • Overoptimism • Or over confident • The mythical man-month (name of a book written by Brooks, 1975) • Adding manpower to a late project makes it later! • Inadequate people management skills (for team projects) – only 1 student doing all the works • Insufficient resources • Supervisor to blame? • Failure to “manage to the plan” • Do you have a plan?

  13. Business awareness Business partner orientation Commitment to quality Initiative Information gathering Analytical thinking Conceptual thinking Interpersonal awareness Organizational awareness Anticipation of impact Resourceful use of influence Motivating others Communication skills - written, oral & graphical Developing others Monitoring and controlling Self-confidence Stress management Concern for credibility Flexibility Project Manager Competencies (Adapted from Wysocki, Beck, and Crane, Effective Project Management: How to Plan, Manage, and Deliver Projects on Time and within Budget.)

  14. Project manager Who is the project manager? Your supervisor? Your group mate? Nobody?

  15. Project Management Functions Eight (8) functions performed by every project manager: • Scoping – setting the boundaries of the project • Planning– identifying the tasks required to complete the project • Estimating– identifying the resources required to complete the project • Scheduling– developing the plan to complete the project • Organizing– making sure members understand their roles and responsibilities • Directing– coordinating the project • Controlling– monitoring progress • Closing– assessing success and failure

  16. Project Management Tools & Techniques PERT chart (Programme Evaluation & Review Techniques)– a graphical network model used to depict the interdependencies between a project’s tasks. Gantt chart– a bar chart used to depict project tasks against a calendar.

  17. PERT Chart

  18. Gantt Chart

  19. Microsoft Project Gantt Chart

  20. Microsoft Project PERT Chart

  21. Activity 1 – Negotiate Scope Scope– the boundaries of a project – the areas of a business that a project may (or may not) address. Includes answers to five (5) basic questions: • Product • Quality • Time • Cost • *Resources - Manpower, Money, Material, Equipment, Facility, Information/Technology Statement of work– a narrative description of the work to be performed as part of a project. Include scope statement, project definition, project overview, and document of understanding.

  22. Scope of project • Are you dare to tell your supervisor that the scope is too large? • Are you dare to tell your supervisor that the project is too difficult to handle? • Did you talk to your supervisor related to the scope?

  23. Sample statement of work • http://contracts.onecle.com/navisite/clearblue.sow.2003.01.01.shtml

  24. Statement of Work I. Purpose II. Background A. Problem, opportunity, or directive statement B. History leading to project request C. Project goal and objectives D. Product description III. Scope A. Stakeholders B. Data C. Processes D. Locations IV. Project Approach A. Route B. Deliverables V. Managerial / Technical Approach A. Team building considerations B. Manager and experience C. Training requirements (continued)

  25. Statement of Work (concluded) V. Managerial / Technical Approach (continued) D. Meeting schedules E. Reporting methods and frequency F. Conflict management G. Scope management H. Techniques/algorithm/methods to be used VI. Constraints A. Start date B. Deadlines C. Budget D. Technology VII. Ballpark Estimates (ballpark – approximately) A. Schedule B. Budget

  26. Statement of Work • Conditions of Satisfaction (what need to be done to get the grade that you want) A. Success criteria B. Assumptions C. Risks IX. Appendices

  27. Activity 2 – Identify Tasks Work breakdown structure – a graphical tool used to depict the hierarchical decomposition of the project into phases, activities, and tasks. For example to build an aircraft structure – wings, tail, crew compartment , fuselage Fuselage – primary structure, secondary structure

  28. WBS Milestone– an event signifying the completion of a major project deliverable. How to get a Grade C – completing phase A How to get a Grade B – completing phase B How to get a Grade A – completing all phases

  29. A Graphical Work Breakdown Structure

  30. Work breakdown • Some widely used reasons for creating a WBS include: • Assists with accurate project organization • Helps with assigning responsibilities • Shows the control points and project milestones • Allows for more accurate estimation of cost, risk and time • Helps explain the project scope to stakeholders

  31. Work breakdown • The project manager and subject matter experts determine the main deliverables for the project. • Once this is completed, they start decomposing the deliverables they have identified, breaking them down to successively smaller chunks of work. • How small? • Two weeks rule (able to complete in two weeks) • 8/80 rule (no less than 8 hours or longer than 80 hours) • 100% rule (the sub-tasks must to equal to the task in the upper level)

  32. Work Breakdown Structure Template – partially completed using an example of some of the work involved in an office move

  33. 1.  Estimate the minimum amount of time it would take to perform the task – the optimistic duration (OD). 2.  Estimate the maximum amount of time it would take to perform the task – the pessimistic duration (PD). 3.  Estimate the expected duration (ED) that will be needed to perform the task. 4.  Calculate a weighted average of the most likely duration (D) as follows: Activity 3 – Estimate Task Durations D = (1 x OD) + (4 x ED) + (1 x PD) 6 OD ED PD 3.33 days = (1 x 2 days) + (4 x 3 days) + (1 x 6 days) 6

  34. Exercise • Based on your own project • Derive a work breakdown structure • Estimate task durations • Identify three milestones (based on expected grade)

  35. Scheduling Strategies Forward scheduling– a project scheduling approach that establishes a project start date and then schedules forward from that date. Reverse scheduling– a project scheduling strategy that establishes a project deadline and then schedules backward from that date.

  36. Activity 5 – Assign Resources • People – includes all the system owners, users, analysts, designers, builders, external agents, and clerical help that will be involved in the project in any way. • Services – includes services such as a quality review that may be charged on a per use basis. • Facilities and equipment – includes all rooms and technology that will be needed to complete the project.

  37. Assign Resources • Supplies and materials – includes everything from pencils, paper, notebooks to toner cartridges, and so on. • Money – includes a translation of all of the above into budgeted dollars!

  38. Resource Leveling Resource leveling– a strategy for correcting resource overall allocations or unbalanced use of resources There are two techniques for resource leveling: task delaying – when more resources are needed than are available. Delaying task until resources are available task splitting – divided into sub-tasks utilize the available resources

  39. Resources Six (6) Resources- • Manpower, • Money, • Material, • Equipment, • Facility, • Information/Technology

  40. Activity 6 – Direct the Team Effort • Supervision resources • The Deadline: A Novel about Project Management • The People Side of Systems • Stages of Team Maturity (see figure to the right)

  41. 10 Hints for Project Leadership • Be Consistent. • Provide Support. • Don’t Make Promises You Can’t Keep. • Praise in Public; Criticize in Private. • Be Aware of Morale Danger Points. • Set Realistic Deadlines. • Set Perceivable Targets. • Explain and Show, Rather Than Do. • Don’t Rely Just on [Status Reports]. • Encourage a Good Team Spirit.

  42. Activity 7 – Monitor and Control Progress • Progress reporting • Change management • Expectations management • Schedule adjustments—critical path analysis (CPA)

  43. Sample Outline for a Progress Report I. Cover Page A. Project name or identification B. Project manager C. Date or report II. Summary of progress A. Schedule analysis B. Budget analysis C. Scope analysis(describe any changes that may have an impact on future progress) D. Process analysis(describe any problems encountered with strategy or methodology) E. Gantt progress chart(s) III. Activity analysis A. Tasks completed since last report B. Current tasks and deliverables C. Short term future tasks and deliverables (continued)

  44. Sample Outline for a Progress Report (concluded) IV. Previous problems and issues A. Action item and status B. New or revised action items 1. Recommendation 2. Assignment of responsibility 3. Deadline V. New problems and issues A. Problems (actual or anticipated) B. Issues (actual or anticipated) C. Possible solutions 1. Recommendation 2. Assignment of responsibility 3. Deadline VI. Attachments (include relevant printouts from project management software)

  45. Change Management Change management– a formal strategy in which a process is established to facilitate changes that occur during a project.

  46. Change management Changes can be the result of various events and factors including: • An omission in defining initial scope • A misunderstanding of the initial scope • An external event such as government regulations that create new requirements

  47. Change management • Organizational changes • Availability of better technology • Shifts in planned technology that force unexpected and significant changes to the business organization, culture, and/or processes • Management’s desire to have the system do more than was originally requested or agreed to • Reduced funding for the project or imposition of an earlier deadline.

  48. Examples • As the project progresses, the customer discovers additional scope that they would like added to the project. The project manager accepts the new scope with the intention of “fitting it in” somewhere. Even if a log is kept that records this additional scope, the customer expectation for delivery date has not changed. They expected the product to be delivered on October 15th. Now when the due date starts getting near, the project is falling behind and either 1) misses the delivery date or 2) cuts corners in testing or other areas to make it on time.

More Related