New York State Department of Transportation. Region 8 Bundled Bridges (Orange County) Design-Build Project (PIN 8BOW.0E, D900029) Request for Qualifications Informational Summary. Region 8 Bundled Bridges (Orange County) Design-Build Project (PIN 8BOW.0E, D900029). Project Overview

jloraine
Télécharger la présentation

New York State Department of Transportation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. New York State Department of Transportation Region 8 Bundled Bridges (Orange County) Design-Build Project (PIN 8BOW.0E, D900029) Request for Qualifications Informational Summary

  2. Region 8 Bundled Bridges (Orange County)Design-Build Project (PIN 8BOW.0E, D900029) • Project Overview • Quality Control & Quality Assurance • Procurement

  3. Region 8 Bundled Bridges (Orange County)Design-Build Project (PIN 8BOW.0E, D900029)Procurement Contact Catherine Traina Attn: Region 8 Bundled Bridges (Orange County) Project Procurement Office of Contracts New York State Department of Transportation 50 Wolf Road, 6th Floor Albany, New York 12232 Catherine.Traina@dot.ny.gov

  4. Region 8 Bundled Bridges (Orange County)Design-Build Project (PIN 8BOW.0E, D900029) • Project Overview • General Location • Goals • General Scope of Work • Utilities • Quality Control & Quality Assurance • Procurement

  5. Region 8 Bundled Bridges – Orange CountyDesign-Build Project (PIN 8BOW.0E, D900029) General Location

  6. Region 8 Bundled Bridges – Orange County Design-Build Project (PIN 8BOW.0E, D900029) General Location

  7. Region 8 Bundled Bridges – Orange County Design-Build Project (PIN 8BOW.0E, D900029) General Location

  8. Region 8 Bundled Bridges – Orange County Design-Build Project (PIN 8BOW.0E, D900029) General Location

  9. Region 8 Bundled Bridges – Orange County Design-Build Project (PIN 8BOW.0E, D900029) General Location

  10. Region 8 Bundled Bridges – Orange County Design-Build Project (PIN 8BOW.0E, D900029) General Location

  11. Region 8 Bundled Bridges – Orange County Design-Build Project (PIN 8BOW.0E, D900029) General Location

  12. Region 8 Bundled Bridges – Orange County Design-Build Project (PIN 8BOW.0E, D900029) General Location

  13. Region 8 Bundled Bridges – Orange County Design-Build Project (PIN 8BOW.0E, D900029)Goals • Replace seven Bridges in Region 8 • Ensure coordination with all utility owners, third parties and any adjacent construction projects • Ensure a long-service life for all Project elements to satisfy long term preservation goals • Maximize the benefit of the public investment in the Project and provide the best value to the Department • Deliver the Project safely, on schedule & within budget

  14. Region 8 Bundled Bridges – Orange County Design-Build Project (PIN 8BOW.0E, D900029) General Scope of Work • Replace seven bridges in Orange County • Reconstruct Highway approaches to the new structures • Maintain traffic throughout construction • Specific traffic requirements/constraints at each bridge site to be presented in RFP • Minimize traffic impacts • Relocation and/or preservation of existing utilities

  15. Region 8 Bundled Bridges – Orange County Design-Build Project (PIN 8BOW.0E, D900029) General Scope of Work (Continued) • Remediation and disposal of any asbestos containing materials • Lead-based paint removal • Comply with existing environmental constraints • Threatened and endangered species • Wetlands • NYSDEC in-stream work date restrictions • Date restrictions for tree removal (due to Northern Long-eared and/or Indiana bats) • Invasive plant species control and emerald ash borer requirements • Erosion and Sediment Control and SPDES

  16. Region 8 Bundled Bridges (Orange County)Design-Build Project (PIN 8BOW.0E, D900029) Utility Coordination – Existing Utilities • Ensure coordination with all utility owners • Existing utilities at each site will be detailed in the Draft RFP

  17. Region 8 Bundled Bridges (Orange County)Design-Build Project (PIN 8BOW.0E, D900029) Utility Coordination - Relocation and/or Preservation of Existing Utilities • Department to provide Two-party (Department and Utility) Preliminary Utility Work Agreement(s) in RFP, including approximate timeframes • Three Way Coordination – DB, Utility, & State • DB Team responsible for holding utility coordination meetings • DB Team responsible to meet and coordinate with utility(ies) and Department, and negotiate Three-party (Department, Utility, and DB Team) Final Utility Work Agreements, including final locations and agreed upon timeframes

  18. Region 8 Bundled Bridges (Orange County)Design-Build Project (PIN 8BOW.0E, D900029) Agenda • Project Overview • Quality Control & Quality Assurance • Procurement

  19. Region 8 Bundled Bridges (Orange County)Design-Build Project (PIN 8BOW.0E, D900029) Quality Control (QC) • QC shall be the Design-Builder’s Responsibility • Design-Builder shall be required to develop a QC Plan covering both Design QC and Construction QC • Design-Builder shall appoint a QC Manager responsible for Project QC • Design QC may be by the Designer in accordance with the QC Plan • Construction Inspection shall be by an Independent Engineering Firm (Hired by the Design-Builder) • Materials Testing shall be by an Independent Testing Firm or Laboratory (Hired by the Design-Builder) • The Materials Testing Firm shall report to the Construction Inspection Firm

  20. Region 8 Bundled Bridges (Orange County)Design-Build Project (PIN 8BOW.0E, D900029) Quality Assurance (QA) • Design & Construction QA is Department’s Responsibility • The Department may perform QA on any of the Design-Builder’s Design and Construction Activities • The Department may utilize an independent Consultant to perform QA of the Design-Builder’s Designs • Department Staff will perform Construction QA • RFQ Section 1.9 covers QA/QC • RFP will describe in detail the Department’s QA Role for the Project

  21. Region 8 Bundled Bridges (Orange County)Design-Build Project (PIN 8BOW.0E, D900029) Agenda • Project Overview • Quality Control & Quality Assurance • Procurement • Schedule • Contract Information • SOQ Evaluation and Selection • Additional Information and Website

  22. Region 8 Bundled Bridges (Orange County)Design-Build Project (PIN 8BOW.0E, D900029) Procurement Schedule

  23. Region 8 Bundled Bridges (Orange County)Design-Build Project (PIN 8BOW.0E, D900029) Contract Information • Lump Sum Design-Build Contract • Two Step Design-Build Procurement Process • Opportunity for ATC (Alternative Technical Concepts) submittal and one-on-one meetings after Final RFP issuance. • Project Schedule • Total Duration 24 Months +/- • There will be a Payment Schedule provided in the RFP • Stipend Amount is provided in the RFQ • Liquidated Damages may be imposed for missed milestones and/or missed Project Completion date • All ROW Acquisition Required for this Project, except releases, will be acquired by the NYSDOT • Construction Related Permits (i.e., Staging Area) by Design-Builder

  24. Region 8 Bundled Bridges (Orange County)Design-Build Project (PIN 8BOW.0E, D900029) SOQ Evaluation and Selection • Pass/Fail Evaluation Factors • Legal; • Financial; • Backlog Capacity; • Vendor Responsibility; and • Quality Evaluation Factors • Organization and Key Personnel (25%) • Experience of the Firms (25%) • Project Understanding (20%) • Past Performance (25%) • Compliance with SOQ Format and Organization (5%)

  25. Region 8 Bundled Bridges (Orange County)Design-Build Project (PIN 8BOW.0E, D900029) Additional Information • Responses to Questions will be posted on the Project Web Site • Final date for receipt of Questions on RFQ December 22, 2014 • There will be a Buy America Clause • There will be a DBE Participation Goal defined in the RFP • RFQ Section 1.10 covers Insurance & Bonding

  26. Region 8 Bundled Bridges – Orange County Design-Build Project (PIN 8BOW.0E, D900029)Additional Information (continued) • Reference Information which will be posted on the Project Web Site when the Draft RFP is issued: • Final Design Reports • Existing Right of Way and/or Acquisition maps as necessary • As-Built Record Plans • Bridge Inspection Reports and Load Ratings • Geotechnical Data Reports (Borings) • Survey/Photogrammetric Base Mapping Plannimetrics • Survey/Photogrammetric DTM • Hydraulic Survey and Hydraulic Cross Section Report • CADD and InRoads files • Traffic Counts

  27. Region 8 Bundled Bridges (Orange County)Design-Build Project (PIN 8BOW.0E, D900029) Project Website & Questions Link to Project Website: https://www.dot.ny.gov/main/business-center/designbuildproject17 Questions: • During the RFQ stage, questions should be submitted in writing to the Department’s designated contact, who is listed in the RFQ Appendix A, on slide 3 and the following slide.

  28. Region 8 Bundled Bridges (Orange County)Design-Build Project (PIN 8BOW.0E, D900029) Procurement Contact Catherine Traina Attn: Region 8 Bundled Bridges (Orange County), Project Procurement Office of Contracts New York State Department of Transportation 50 Wolf Road, 6th Floor Albany, New York 12232 Catherine.Traina@dot.ny.gov