Benjamin Stillwell Mechanical Engineering Specialist

SPX Mechanical Systems – Infrastructure, Integration, Installation WBS U1.2.1.3.6, U1.2.1.3.11, U.1.3.3.10. Benjamin Stillwell Mechanical Engineering Specialist APS Engineering Support/Mechanical Engineering and Design DOE Lehman CD-2 Review of APS-Upgrade 4-6 Decem ber 2012. Outline.

jud
Télécharger la présentation

Benjamin Stillwell Mechanical Engineering Specialist

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SPX Mechanical Systems – Infrastructure, Integration, InstallationWBS U1.2.1.3.6, U1.2.1.3.11, U.1.3.3.10 Benjamin Stillwell Mechanical Engineering Specialist APS Engineering Support/Mechanical Engineering and Design DOE Lehman CD-2 Review of APS-Upgrade4-6 December 2012

  2. Outline • Importance • Scope • Organization • Technical Requirements • Design • Interfaces • Risks • ES&H • Cost • Schedule DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  3. Importance of Infrastructure, Installation, and Integration • SPX cryomodules require significant new hardware and infrastructure accommodations at the APS to function. • Design effort project-wide requires information and problem-resolution for mechanical interfacing. • Integration of superconducting RF cryomodules into the existing storage ring vacuum system must be carefully planned to ensure that cavities and/or storage ring operations are not compromised. DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  4. Scope - Hardware Deliverables • Cryogenic supply and distribution systems • Deionized water delivery and distribution systems • Infrastructure in building 400A for cryomodule and vacuum component preparation and testing • Mechanical components to perform cavity testing and accommodate storage ring installations DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  5. Scope - Hardware DeliverablesR&D Mechanical Components SHORTENED 7.5MM ID VACUUM CHAMBER DOWNSTREAM END-BOX WITH TAPER UPSTREAM END-BOX WITH TAPER ALUMINUM VACUUM SPOOLS RF-LOCKING GATE VALVE TEST BELLOWS TAPER SPX0 Straight Section Vacuum System (Bellows Test Configuration) DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  6. Scope - Hardware DeliverablesR&D Cryogenics Input coupler, top plate, support frame, and cryogenic plumbing for horizontal test Feedbox, neck insert, and top plate for vertical test cryostat Kinney-Tuthill vacuum pump DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  7. Scope - Hardware DeliverablesCryoplant Turn-key system includes: • 320W at 2K (100% margin) and 500W at 5K • Compressors • “Cold Box” • Gaseous and liquid helium storage • Installation supervision and commissioning Similar-scale system used at ELBE DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  8. Scope - Hardware DeliverablesCryogenic Distribution System Includes: • Approx. 70m of 4-circuit transfer line • Main distribution box (valves) • Two localend boxes (valves) • U-tubes and assorted supplies • Mechanical supports DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  9. Scope – Hardware DeliverablesDeionized Water Systems 600 gpm of additional capacity provided for a total of >900 gpm serving: HLRF amplifiers – 440 gpm HLRF test stands – 125 gpm Cryoplant-related – 150 gpm Conventional facilities – 50 gpm Total projected DI water need: 765 gpm DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  10. Scope - Integration and Installation Deliverables • Cryomodule mechanical installation support and planning. • Top-level mechanical assembly model. • Mechanical interface drawings and 400A space use plan. DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  11. Organization • Ben Stillwell – Section lead/mechanical engineer • Joel Fuerst – Lead cryogenics engineer • John Noonan – Mechanical engineer (vacuum design and storage ring integration) • Bran Brajuskovic – Mechanical engineer (dampers) • Jie Liu – Mechanical engineer (analysis) • Stan Reeves (Espo) – Mechanical engineer (ANL cryomodule hardware) • Rich Hrebic (Espo) – Mechanical engineer (cryogenics systems) • Bill Soldwisch (Espo) – Mechanical engineer (integration) • Dave Fallin – Mechanical designer/drafter • Neil Bartkowiak – Mechanical designer/drafter • Jason Lerch - Mechanical designer/drafter DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  12. Technical Requirements • Physics Requirement Documents (PRDs) – SPX0, SPX • Engineering Specification Documents (ESDs): SPX Cryomodule SPX HLRF SPX Dampers SPX Windows DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  13. Design Status Summary DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  14. Interfaces • Top-level mechanical models and drawings. • System-specific mechanical interface drawings: • Cryomodule – Storage Ring (Long Straight Section) • HLRF – Storage Ring • Cryogenic Distribution System – Storage Ring • 400A Space Use • Cryomodule installation plan • ICDs: • Cryoplant • Cryogenic Distribution System • Cryomodule Mechanical Systems– Long Straight Section DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  15. Risks • Cryoplant cooling capacity Mitigation: • Cryoplant procured with 100% additional performance margin • Experience with SPX0 cryomodule will give confidence to estimates and help to optimize thermal design • Mechanical interference discovered during installation Mitigation: • Maps of existing storage ring configuration have been generated by APS survey and alignment team. • Mock-up of cryomodule has been transported through storage ring tunnel. DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  16. ES&H • Integrated Safety Management System (ISMS) • APS-U Project following Argonne’s ISMS program requirements • Argonne Integrated Safety Management System (ISMS) Description recently revised and submitted to DOE ASO • Describes framework for integrating ESH requirements with mission objectives • References Argonne LMS procedures which implement specific portions of the ISMS • General Requirements • ANL Pressure Systems Safety Manual • ESH-13.1 Pressure Safety – Systems • ESH-4.10 Hazardous Materials - Cryogenic Liquid Safety • System-Specific Requirements • Designs subject to formal, documented design review – APS Design Review Procedure • Work control determined from hazard analysis (ANL WPC system) • Approvals by division management DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  17. SPX Mechanical Systems and IntegrationScope and WBS - U1.02.01.03 & U1.03.03 • Mechanical systems costs are roughly 25% of total SPX project cost • 22% of direct cost is labor DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  18. SPX Mechanical Systems and IntegrationScope and WBS - U1.02.01.03 & U1.03.03 • Most-costly deliverable remaining for R&D phase is SPX0 in-ring cryogenics. • Most-costly deliverables for production phase are cryoplant, cryogenic distribution system, and deionized water systems. DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  19. SPX Mechanical Systems and IntegrationObligation Profile - U1.02.01.03 & U1.03.03 DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  20. SPX R&D and Production Milestones - U1.02.01.03 & U1.03.03 DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  21. SPX Mechanical Systems and IntegrationMilestones - U1.02.01.03 & U1.03.03 DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  22. SPX Mechanical Systems and IntegrationSummary Schedule - U1.02.01.03 & U1.03.03 • R&D phase and preliminary design for production phase run concurrently (now). • Final design begins after installation of SPX0 cryomodule. • Some small early procurements and installations are necessary to prepare for future installations (clean room, facility modifications). DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  23. SPX Mechanical Systems and IntegrationBOE Contingency – 1.02.01.03 & 1.03.03 DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  24. Work between CD-2 and CD-3 • Final design, fabrication, and installation of cryogenics for the SPX0 in-ring test. • Design review for SPX0 cryogenic and pressure systems. • Detailed installation plan for SPX0 cryomodules in the APS storage ring. • Completion of preliminary design for production-phase deliverables. • Continued mechanical integration support – top level CAD model and additional interface drawings as-needed. DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  25. Summary • The SPX mechanical systems WBS areas supply needed infrastructure, hardware, and installation support to the project. • The preliminary design is expected to be complete in mid-2013. Presently, most deliverables are well defined with regard to scope, cost, and schedule. • Total cost is $11,966k and is dominated by cryo plant procurement in 2016. • Installation • Installation plan complete by Jan 2014 (r&d) and May 2017 (prod.) • SPX0 cryomodules: Aug 2014 – Sept 2014 • SPX production mechanical components: Aug 2013 – Jan 2019 • SPX production cryogenics: Sept 2016 – March 2018 • SPX production cryomodules: April 2018 – March 2019 DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012