1 / 20

Readiness for 450 GeV/c

Readiness for 450 GeV/c. G.Arduini for the Machine Check-Out Team (Mike, Reyes, Rossano) Special thanks to: E. Ciapala, B. Goddard, J.J. Gras, W. Höfle, S. Redaelli, J. Wenninger. 450 GeV/c. 450 GeV/c: All “Day-1” circuits available Precycle and injection plateau Safe Beam intensity

judah
Télécharger la présentation

Readiness for 450 GeV/c

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Readiness for 450 GeV/c G.Arduini for the Machine Check-Out Team (Mike, Reyes, Rossano) Special thanks to: E. Ciapala, B. Goddard, J.J. Gras, W. Höfle, S. Redaelli, J. Wenninger LHCPerC

  2. 450 GeV/c • 450 GeV/c: • All “Day-1” circuits available • Precycle and injection plateau • Safe Beam intensity • RF for beam capture and radial steering • Instrumentation for optics characterization

  3. Magnet circuits & Power Converters • Available Sectors: • Sector 56 • Sector 67 • Sector 23 • Sector 78 • IT not fully HW Commissioned  tested only at injection (Pts. 2 & 8) • Warm magnets in: LSS 2/3/5/6/7/8

  4. Magnet circuits & Power Converters • Tested: • Alarms • SW interlocks (PC state)  procedures in place • Loaded settings for pre-cycle, injection and ramp • Control SW debugging • Preliminary tests for the squeeze, decay and snapback for sector 56 and verification of the specifications for ramp and acceleration rates vs. squeeze time, snap back,, etc.  feedback to HWC and revision of the parameters for the tests in the following sectors • Tracking verification for RB/RQD/RQF for two adjacent sectors • To be done: • Points 1 to 3 for the other sectors: typically 4-5 shifts once a sector is available

  5. Magnet circuits & Power Converters M. Strzelczyk, M. Lamont D. Nisbet

  6. Beam Instrumentation • Tested extensively during synchronization tests: • BPMs - OK • BTVs – OK • BST – OK (expts profited of it as well) • BLMs: • still issues for the logging of the full machine • test with radioactive source being completed this week (during nights) • Threshold controls still being investigated

  7. Beam Instrumentation • To be tested: • BCT/FBCT: • Application and fixed display available and tested • HW and front-end available • XPOC and capture acquisitions to be tested with beam during next injection test as well as EMC • Wire Scanners: • application and individual system tests completed • Test planned for next Monday 1/9 • BSRT (synch light monitor): • application available and individual system test completed • video transmission tested • Undulators to be HWC • BRSA (abort gap monitor)

  8. Beam Instrumentation • To be tested: • Tune measurement: • application available and tested in the injectors. Kicker controls to be tested (pending availability of MKQA) • BGI: • no gas injection system installed • To be verified whether the signal from residual gas ionization is sufficient (possibility to switch off ionization pumps if needed) • Video signal transmission not yet available due to missing SW for the remote control of the camera

  9. Collimators • Not available yet: • Alarms  FESA classes to be defined • Interlocks to be tested: • Position interlocks including TCDQ, TDI, TCLIA/B, TCDD • Temperature • Preparing for a test at the end of this week • IST completed • Control SW, logging and fixed displays available and tested • Movement and synchronization tested • TCDQ controls (movement and intlk. Functions) to be tested (ongoing) S. Redaelli

  10. Controls • All the main application SW is there and tested (at least in its main functionalities) • Settings generated and loaded in the HW as soon as sectors become available • Major issues: • Central Timing • BLM logging (concentrator stability)

  11. Injection system • Injection system thoroughly tested during past two injection tests: • Injection sequences • MKI controls • Slow and fast timings • Injection tuning tools • Verification of injection protection functionality to be completed: • during or in the preparation for the next injection test (few hours required) with beam permit available.

  12. LBDS • All HW and controls available • PM/XPOC prototype versions available • LBDS connected to access system and functionality verified • Energy tracking partly tested (3 out of 4 bends sectors + Q4 + Magnetic Septum connected) with nominal ramps to 5 TeV/c. Run with energy provided by one sector during the last 2 injection tests. • Detailed test plan available (c/o Brennan) to complete most of the tests by the middle/end of next week in view of an injection/dump test for beam 2. In particular: • Connection to BIC and BIC-LBDS test • TCDQ synchronized movement and interlocks • Links to injection system

  13. Interlocks • 50 % already enabled & a good fraction of them tested: • BTVs (all channels) • PIC (only the sectors affected by the test in a “soft” configuration, i.e. most of the entries maskable)  automatic test program allows rapid verification of the interlocks (~ 2 hours/sector) • WIC (all channels) – 1 WIC crate to be tested (need machine closed) • Collimators (to be tested thoroughly) • BLM (maskable input): to be tested at least for a few BLMs • Vacuum (LSS 2/3/6/7/8) enabled • ALICE and LHCb channels • FMCM connected but not tested (1 FMCM card likely not available before the start-up)  implications to be evaluated

  14. Interlocks • continued: • Most of them can be tested in parallel to HWC in the next 10 days (remaining experiments and FMCM at the beginning of next week) • Final verification of a few channels when beam dump connected and beam permits available • SW Interlocks: • Thorough checking ongoing as soon as sectors become available. • BTVs done

  15. Post-Mortem & Safe Beam Parameters • Post-mortem enabled during the last Synch. Test: • 20 events observed: all sent data been recorded correctly. Link between BIS and Timing system OK.  Left connected. • BLM PM data. Not reliable sending of data yet • Further client discussions to send PM data (not yet integrated in all BI systems, RF, etc…) • Received data can be browsed with the latest version of the PMDataViewer. • Beam PM framework ongoing, first vertical slice is planned to be ready for 10th of September. • Safe Beam Parameters: • Energy from LBDS-Beam Energy Meter available • Intensity with simulated values • Should be in place end of the week/beginning of next for tests

  16. RF • Synchronization: • SPS re-phasing operational • Pre-pulses, revolution frequency to BI, BT, Expts., control of the injection settings distributed for beam 1 and 2 • Injection bucket number selection tested • ACS Power: • All 16 cavities conditioned to 2 MV. • Remote control of power systems available in CCC • Reliability tests ongoing in parallel • ACS Low level: • RF feedbacks set-up in 10/16 cavities. Cavity phasing to be done. • Cavity voltage setting and function execution tested (LSA)

  17. RF • Low level controls (frequency program, phase loop, synchro loop, radial loop): • HW & front-end SW in test  Install in SR4 next week • Frequency setting and frequency program control from CCC by the end of next week (tbc) • Transverse feedback: • Power part HW commissioned • Available for excitation of the beam for tune measurement • Low level HW available by mid/end of September • Remote controls power part (Labview expert application for now) • Abort gap cleaning function to be developed • OASIS signals: • APW longitudinal pick-up acquisition installed and being tested • Damper signals in SR4 but not yet available in CCC ICC

  18. Vacuum • Beam Interlocks from vacuum valves in the available vacuum sectors (in strict collaboration with AT/VAC): • LSS 1-2-3-4-6-7-8, end of TI2/8 • Vacuum gauges, vacuum valve logging • Alarms • Need to test Accelerator Safety Block, presently disconnected after problem identified in the connection  Need closed machine • Need to test LSS5  Need CMS closed • Need to verify fine delays between interlock and vacuum valve closure for a few valves once the beam dump is connected to BIC (a few hours with closed machine)

  19. Issues • Frequent accesses for activities still ongoing • Lack of discipline resulting in frequent loss of searches and needs for patrols • Access system reliability: improved but still not satisfactory • Frequent loss of communication with QPS controllers requiring access (almost daily)  QPS team working on a solution for that • Timing & controls aspects • RF signals and controls availability from CCC on day 1 • Need machine closed, beam permits available and LBDS connected for final verification of the full chain of machine protection at least for a small subset of elements after systematic verification

  20. Summary and Conclusions • Try to progress with cold check-out in parallel with HWC as much as possible • Aim at preparing the machine for circulating low intensity beams for 10/9 with • Circuits made available from the HWC • minimum but well-tested machine protection in place for 450 GeV/c with low intensity • Instrumentation for qualifying the machine • RF equipment to allow capture and radial steering of the beam • 5 PM meetings in the CCC glass-box to review the status of the preparation, issues and next steps. We will • Follow-up of tests progress and procedures at: • https://espace.cern.ch/LHCMachineCheckout/default.aspx

More Related