This report outlines the current status of the procurement and inventory management for the laboratory testing facility operated by A. Bartalesi. It details the completion of 3D and 2D labels for various components across TM0, TM1, and TM4 systems. The report also highlights the receipt and assembly progress of key structures, including extremity flanges and V-shape supports, as well as the delivery status of critical items like waveguide flanges and copper gaskets for the vacuum systems. Comprehensive tracking of ordered and delivered components is emphasized.

juro
Télécharger la présentation

Laboratory Testing Facility Procurement and Inventory Management Overview

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LAB Test Modules componentsinventory and procurement schedule In LAB testing facility A. Bartalesi

  2. Procuring overview TM0s Labels: 3D done2D done Ordered Delivered A. Bartalesi

  3. Procuring overview TM1 Labels: 3D done2D done Ordered Delivered A. Bartalesi

  4. Procuring overview TM4 Labels: 3D done2D done Ordered Delivered A. Bartalesi

  5. Accelerating structure • All the accelerating structures parts for the fist TM0 have been received. Supporting system TM0s • The extremity flanges supports have been received and 50% has been assembled. • V shape supports delivery has been confirmed for beginning of February. Vacuum system TM0s • The extremity flanges have been delivered. • All the remaining waveguide flanges (VDL) have been delivered. • All the copper gaskets for the waveguide flanges and the vacuum networks have been delivered. Vacuum system TM1 and TM4 • All the components are in drawing phase (if not already made for TM0). A. Bartalesi

  6. Thank you! A. Bartalesi