Mars Atmosphere and Volatile EvolutioN (MAVEN) Mission. Particles and Fields Package Pre-Ship Review October 30,31, 2012 25: SMA Jorg Fischer, MAM. PSR SMA - Summary.

kalkin
Télécharger la présentation

Particles and Fields Package Pre-Ship Review October 30,31, 2012 25: SMA Jorg Fischer, MAM

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Mars Atmosphere and Volatile EvolutioN (MAVEN) Mission Particles and Fields Package Pre-Ship Review October 30,31, 2012 25: SMA Jorg Fischer, MAM

  2. PSR SMA - Summary EIDP (including GSFC, IRAP, LASP) flight travel books have been reviewed, all open items are identified by SSL and GSFC and are tracked – cont. Hardware and Software are in good shape Configuration Control is in place and working No parts or materials issues No major issues during built-up – Exception: SWEA No major non-compliance exists – Exception: SWEA PFR’s: Jorg Fischer Testing and Verification: David Curtis Software code Status & GSE: Peter Harvey SSL Safety: Jorg Fischer, Safety: LM

  3. SMA SUMMARY Workmanship SMA supported PMB, PWA fabrication, assembly modifications, tuning efforts, repair/rework, box integration, and training (training at JPL, RMV, and informal in-house) Configuration Management FHW – Checked FLT Binder documentation and PFR status to confirm readiness, before start of testing FSW – ongoing support of informal and formal reviews, walk-throughs, and monthly reports Documentation Control – Performed FLT document reviews, and updates Work Order Management Travelers – Reviews performed by SSL QA and GSFC QA Procedures – Performed procedure reviews Inspections – Ongoing - Performed by SSL QA and GSFC QA.

  4. SMA SUMMARY Metrology & Calibration Performed the monthly checks (Tools and Certifications) – no issues. Scanned 100% of all certifications for EIDP delivery. Training Performed certifications review – no issues Cleanroom, PP, ESD, and Documentation training – no issues Held SSL Safety Training Meetings LM Training for SSL team members to meet LM in-house requirements might be necessary. Contact with C. Love - in progress. LL: Suspect counterfeit awareness training is planned for SMA and purchasing personnel - NA-HQ-2012-00 PFR-NCR SPR-SCR System PFR-NCR database revised and updated, documentation - in progress SPR-SCR list revised and updated, documentation - in progress

  5. SMA SUMMARY • Quality • Inspections of all FLT unit assemblies, PWA, boxes, and harnesses – ongoing. All issues are documented in PFR System. • Testing - Provided support for offsite testing, such as, EMC, Vibration testing setup and testing. Supported In-house testing, such as, TVAC set-up and testing of the instruments • Supported of LASP EUV efforts at SSL • Continuous inspections of Flight assembly, cleanroom, and test areas by SSL and GSFC QA • Supported PW board modifications/tuning and rework/repair • Supported integration and de-integration activities of the Instrument Stacks (PFDPU, SWEA, SWIA, SEP, LPW, STATIC)

  6. SMA SUMMARY • ESD Control • Implementation, equipment, maintenance, measurement, and training are addressed in the SSL ESD Control Plan (Rev. B) • Supported the annual independent ESD Control verification and performed the monthly survey – no issues • SSL MAVEN team ESD training was performed, as required • Material Processes and Parts Control • Updated EEE parts, Flight fastener, and Materials databases • As-built BOM documentation. ABPL for all instruments are complete • Alert response reports (GIDEP) – Provided disposition and updated the alert response database – no issues (ref. GIDEP slide) • Polymerics – Updated mix record database. Performed polymeric witness sample testing, filing, inspections, and documentation.

  7. SMA SUMMARY • Facilities/ Equipment • Continuous inspections of Flight assembly, vendor and in-house test areas by SSL and GSFC QA • Provided cleanroom support - cleaning of parts, continuous supplies, and maintenance, for all MAVEN cleanrooms • Industrial Safety: Provided support of chemical, hazardous waste inventory and UCB EH&S interaction • Delivery Readiness • End Item Data Acceptance Package – ongoing • Reviewed LM AIRR list – ongoing • Support of shipping effort

  8. PFR, ECN, Waiver, MUA Overview Anomalies/PFR/NCR 37 NCRs and 82 PFRs issued – STATUS next slides ECN/ECO 18 ECN/ECO issued, All closed WAIVERS, CCR 42 Waivers issued. Closure of all to be confirmed MUA 5 MUAs issued, Closure of all to be confirmed

  9. SMA - MRB • MRB System • PFR status report list sent to GSFC – weekly • PFR-NCR System will serve as a Lessons Learned System • Provided assistance to SSL engineers with PFR documentation and related item close-out

  10. SMA - MRB Anomalies/PFR/NCR – STATUS of six (6) open PFRs PFR 105,   EUV Temp Sensor Noise is open – LASP EUV - Waiting for thermal test PFR 108,    Operational and Actuator CE03 exceedances - PFDPU     - Waiting for Waiver to close PFR 109,   MAG Heater CE03 exceedance  - PFDPU     - Waiting for test data with the filters PFR 111,  MAG Sensor CS101 MAG susceptibility - PFDPU MAG Sensor FM1,2 -  Waiting for test data with the filters PFR 119,  STATIC TOF Field Emission Noise - SSL is working to close PFR 124, LASP LPW Cold Anomaly – LASP EUV - Ready to close - FRB

  11. PFR ECN Tracking PFRs, ECNs

  12. Configuration Control Instrument and Box Level Master sheet Assembly Subsystem Components Cognizant Engineers Serial Numbers and Designators: F1, F2, Spare. Rev Level AS-BUILT Schematics, AS-BUILT BOMs, AS-BUILT Assembly Instructions Master Binder for ECN, PFR, Waiver, MUA (all available electronically)

  13. SMA – SPR-SCR System

  14. Data Bases – Parts, Materials Approved no issues

  15. Data Bases – Alerts and GIDEP Approved no issues

  16. GIDEP Alerts & Problem Advisories As of 10/28/12, SSL SMA checked a quantity of 463 alerts As of 10/28/12, SSL SMA closed a quantity of 463 alerts Four (4) impact alerts were mitigated and closed Alert “051910 email from Oscar” Added a note to board drawings that “The use of brominated polyimide is unacceptable.” SMA produced PWA specification for MAVEN – SOW KE1-P-11-02, SOTA, solderable thin film MIL-PRF-55342 resistors were produced with defective end terminations. A) Date Codes not used. B) Additional inspections were implemented RS2-P-11-0, Microsemi, diode re-classified as ESD Class 0 – installed ESD class 0 workbench, device installed at JPL. NA-HQ-2012-001, Checked approx. 400 vendors, - no impact, used MFG authorized vendors only and received certs.

  17. FLT Travel Books FLT Travel Books

  18. SMA – Concerns & Observations Concerns – All concerns are well understood and are closely monitored by the SSL and GSFC QA teams. Pending – Expect two red flag PFRs (SWEA PFR 059 and PFR 122) – LM monitoring for both. Communications and working relationship of the experienced MAVEN PFP teams are excellent.