This document outlines the updated organisation structure for the LHC Experimental Areas as of March 3, 2006, to improve work-site management and safety coordination in light of recent personnel appointments. Four new technicians have been added for work-site supervision, alongside two new safety coordinators, ensuring adherence to working procedures. The updates encompass changes in the ATLAS and CMS experimental areas, focusing on installation and commissioning phases while maintaining safety measures. This document is crucial for streamlining coordination and operations within the experimental domains.
E N D
Update on Experimental Area Organisation Structure Emmanuel Tsesmelis LEAF 3 March 2006 E. Tsesmelis - TS/LEA
Introduction • In view of • the appointment of four new Technicians (Work-site Management), the • the addition of two new Safety Coordinators, and • the start of a new phase of activities at the experimental areas, the organisation structure supplied by the TS Department to ensure the coordination of the LHC experimental areas has been updated. E. Tsesmelis - TS/LEA
Technicians (Work-site Management) • As work-site supervision technicians for the LHC experimental areas, the four newly-appointed Technicians (Work-site Management) have the following functions: • In the framework of the Experimental Area Teams already in place, actively ensure that working procedures are respected in the experimental areas under the responsibility of TS-LEA, keeping technicians and engineers of the TS-LEA-EAM section well-informed of the application of procedures. E. Tsesmelis - TS/LEA
Updated Organisation Structure *Assistance for USA15 and US15 ** Assistance to ATLAS until milestone of Ready for Lowering CMS Detector E. Tsesmelis - TS/LEA
Update to Point 1 (ATLAS) Experimental Area Organisation • Update has been made to the organisation structure supplied by the TS Department to ensure the coordination of the ATLAS Experimental Area at Point 1 to cover the installation and commissioning of the ATLAS experiment in the underground areas. • The UX15 organisation structure for the installation and commissioning phase of the ATLAS experiment remains unchanged. • The ATLAS Counting Room Management (CRM) organisation structure has been created under the responsibility of the ATLAS Collaboration to provide analysis and follow-up of WPs for USA15 and US15, where commissioning of the experiment electronics is carried-out. E. Tsesmelis - TS/LEA
Global Coordination • - Work Package definition • (budget, scope & schedule) • - All activities outside the Experimental Area • - Detector Installation & commissioning • - Overall schedule Global coordination of the Istallation and comissioning of the Experiment TC Team TC PH HD In situ coordination -TS services & infrastructure - Detector installation & commissioning EAM LEA GL TS HD EAT Update to Point 1 (ATLAS) Experimental Area Organisation PH TS E. Tsesmelis - TS/LEA
ATLAS Technical Coordinator PH Work Package 1 Work Package 2 Work Package n-1 Work Package n Experimental Area Manager TS Transport Coordination Weekly Planning Safety Coordination Transport Contract Update to Point 1 (ATLAS) Experimental Area Organisation E. Tsesmelis - TS/LEA
Update to Point 5 (CMS) Experimental Area Organisation • In view of the start of CMS lowering in to the UXC55 cavern in Summer 2006, the corresponding organisation structure for Point 5 (CMS) is presently under review. E. Tsesmelis - TS/LEA
SXL2 Surface Building at Point 2 • In order to guarantee the safety coordination of the ALICE activities in SXL2, the safety co-ordination of this building has been re-integrated under the responsibility of the TS Department. • The update has resulted in the following: • E. Paulat has been re-appointed Safety Coordinator for SXL2. • P. Ijzermans remains TSO and will continue to lead the organisation of Work Packages and the corresponding Work Package Analysis meetings for SXL2. • Effective as of 1 February 2006 E. Tsesmelis - TS/LEA
Documentation • Updated versions of the relevant documents • EDMS Doc. No. 483480 (Experimental Areas Organisation) • EDMS No. 490701 (List of Buildings and Civil Engineering Infrastructures Included in the Different Experimental Areas) • EDMS Doc. No. 690581 (Update of Organisation Structure for ATLAS Experimental Area) has been released. E. Tsesmelis - TS/LEA