This document outlines the agenda and proceedings of the Harmonisation Working Group (HWG) meeting held on February 22, 2012, at the NIAUR offices in Belfast. Key discussion points include the approval of minutes from the previous meeting, updates on the Enduring Solution Project, and changes related to the Market Design documents (MPD29). The unmetered market's growth, document updates, and several classification requests were also addressed, along with planning for future meetings. The next HWG meeting is scheduled for April 4, 2012, in Dublin.
E N D
Harmonisation Working Group HWG Meeting Wednesday, 22nd February, 2012 NIAUR Offices Belfast
Approval of Minutes Minutes from HWG meeting – 11th January 2012
Enduring Solution Project Update Ann Ferguson / Joan-Edel Smith
ROI HSP Update Conor Garrigan
Market Design Update Today’s Workload Overview
DR1085 V1 - Change to MPD29 - Grouped COS • Change Request • The unmetered market has grown significantly since Market Opening in 2005 • RMDS-driven process review project has assessed the processes in terms of bottlenecks, weaknesses and areas for improvement • This DR has been created to facilitate changes to MPD 29 • At today’s Meeting • Classification as ROI-specific
DR1115 V1 – Sundry Code Changes • Change Request • Use of Meter Configuration Code (Required) in NI Market • Work Type Code Value “W402” in NI Market • Addition of Supplier Codes (NI operations only at this time) • S40 (Budget Energy) • S41 (LCC Power Ltd) • Correction to Suppler Codes (for NI operations) • S08 (Vayu) • Code description changes • Meter Configuration Code “H050 - Interval Meter” • Reject Reason Code “CNM - Change of Tenancy/Legal Entity on 010(CoS)” • Withdrawal Reason Code “E1 – Miscellaneous”. • At today’s Meeting • Recommendation for approval as DR and MCR
DR1116 V1 -Updates to Enduring Solution NI Market Documentation • Change Request • Update of the Enduring Solution NI Market Documentation with corrections, clarifications and pending Discussion Request DR1115 at today’s meeting • At today’s Meeting • Classification as NI-Specific
MCR1079 V5 – HBL V2.3 • Change Request • HBL V2.3 Content Changes • No schema change required • HBL remains consistent with current Version of Harmonised schema • At today’s Meeting • Recommendation for approval
HWG Action Items Open Items as at end of last meeting
Next Steps • Next HWG meeting 4th April, 2012 (Dublin) • Dates for all meetings for 2012 are on the Calendar on the RMDS website
HWG Meeting • AOB
HWG Meeting Thank You