1 / 11

ES&H Status of Construction and Technical System Installations

ES&H Status of Construction and Technical System Installations. Mike Scharfenstein Project ES&H Coordinator. Construction Safety. November 17, 2008 – Substantial Completion 146 Days without lost time incident - Major Milestone 60 days w/o recordable – Major Milestone

kellan
Télécharger la présentation

ES&H Status of Construction and Technical System Installations

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ES&H Status of Construction and Technical System Installations Mike Scharfenstein Project ES&H Coordinator

  2. Construction Safety • November 17, 2008 – Substantial Completion • 146 Days without lost time incident - Major Milestone • 60 days w/o recordable – Major Milestone • Safety in GC managed work a disappointment Aggressive Management Steps • Weekly Senior Executive - Conference Calls & On-Site Meetings • Increased LCLS & TCCo field staff • Full-Time On-Site Nurse • Full time DOE field presence • Lessons Learned

  3. TCCo Incident Distribution

  4. Safety Stewardship Meeting – Weekly Analyze emerging issues Define action items (R&R, Nurse, Mgt Walks) LCLS Modified staffing UTR Safety Observation Training TCCo Job Hazards Analysis Re-invigoration (WP&C) LIFE Training Bottom Line Communicate to Hands-on Craft and Immediate Supervisors LCLS emphasis on safety. Construction Development

  5. Lagging Indicators Incident/Injury Indicator of Poor … Opportunity to Learn Work Planning Work Execution Work Oversight Field Work Assessments Assessed past performance Developed Corrective Actions ISM / WPC Leading Indicators Lessons Learned from incidents lead to improvements More oversight and involvement with work planning and execution Added Field Personnel Superintendents Lab UTRs Added Occupational Safety Nurse Leading & Lagging Indicators

  6. APPLY ISEMS ! 7 Guiding Principles & 5 Core Functions Good for All; staff and contractors Work Planning & Control Contractor Selection Needs to be thorough Meet the team / know the work Recent jobs / EMR Work Planning & Control Site Specific Safety Plan Detailed R2A2s Personnel competencies, Know the work – including hazards, Perform the work w/I controls, Feedback & Improvement Lessons Learneda little more detail

  7. SLAC has undertaken a lab-wide initiative to consistently assure that work is planned and controls identified before work is authorized to begin… 2006 downtime WP&C strategy 2007 LCLS begins dialog w/ NIF 2008 LCLS participating/driving process w/I Lab & w/ contractors Lesson Learned - Active Participation in Oversight Be a part of the major work packages Collaborate for success Firm and Fair Work Planning and Controla little more detail

  8. Work Goals Subcontracted Work Goals • CF & Technical Systems Installation • APPLY Integrated Safety Management • Direct subcontractor management • Detailed work planning The goal is to maintain exemplary safety record • GC managed • Current performance acceptable • Maintain engagement of GC and subs • <30 days of field work remaining • area to watch = demobilization The goal remains Zero future incidents

  9. Conclusion • Apply ISEM • Work Planning & Control • Maintain CF & Technical System direct managed work performance • Continue close work with TCCo • LCLS / Lab / SSO involvement • Past 6 months = acceptable performance The goal remains Zero!

  10. end of presentation

More Related