CLEAN FUELS UPGRADE at PETROTRIN’S POINTE- A-PIERRE REFINERY

CLEAN FUELS UPGRADE at PETROTRIN’S POINTE- A-PIERRE REFINERY. Mendoza, Argentina. October 31, 2006. Steve Hilaire. OUTLINE. Introduction Business Background Scope Economics Capital Expenditure Results & Benefits Project Risks Status Financing Template.

Télécharger la présentation

CLEAN FUELS UPGRADE at PETROTRIN’S POINTE- A-PIERRE REFINERY

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CLEAN FUELS UPGRADE at PETROTRIN’S POINTE- A-PIERRE REFINERY Mendoza, Argentina October 31, 2006 Steve Hilaire

  2. OUTLINE • Introduction • Business Background • Scope • Economics • Capital Expenditure • Results & Benefits • Project Risks • Status • Financing Template

  3. Introduction – About Trinidad & Tobago • Access to emerging & developed markets • Highly skilled and trained workforce • Stable economic/political environment • Global leader in • Export of Methanol • Export of Ammonia • Export of LNG to USA

  4. Introduction – PETROTRIN History • 1917: Commence Operations of P-a-P Refinery • 1940/41: Eastern Refinery Established • 1952: FCCU Installed • 1956: Acquisition by Texaco • 1958: No 1 CRU – Gasoline Upgrade & BTX • 1960/62: No 8 CDU, No 1 HTU, No 2 CRU • 1964/66: Lube Oil & Normal Paraffins • 1972: No 4 VDU & No 2 HTU –Fuel Oil Desulf • 1985: Acquisition by State • 1992/96: Refinery Upgrade – Phase 1 • Increased Conversion & Full Refining Capacity • Partial Revamp of FCCU • Rehab of No 2 HTU, No 2 CRU, • New Units: VBU, Hydrogen, Sulfur, MTBE • DCS Controls

  5. Introduction – PETROTRIN OVERVIEW • Fully State-owned • Commercially operated • Integrated • Exploration • Production • Refining • Marketing

  6. Introduction – Crude Oil Supply • Crude capacity – 168 MBPCD • Current conversion capacity 150 MBPD • Local crude 40 – 45 % (low cetane gas oil) • Imported crudes • Venezuela • Brazil • Columbia • Ecuador • West Africa (high cetane)

  7. Introduction – Product Supply • Markets • Local 100 % - 18% of Volume • Regional 75 % - 30% of Volume • Extra regional 5 % - 20% of Volume • International - 32% of Volume • Approx 10 % volume- unfinished/low value products • CRU naphtha • Low octane mogas • FCCU feed (VGO)

  8. Introduction: Operational Performance – R&M Performance Factors Petrotrin is highly sensitive to market price because it is a merchant refiner Market Price Sales Revenue High fuel oil cut & low value products reduces profits Lacks clean fuels capacity Mix + Volumes High unit operating costs compared to peers Direct Cost Financial Performance OPEX Indigenous crude only supplies 40% of needs Profitability Cash Flow ROACE Other High spend on maintaining competitiveness of old infrastructure Sustaining CAPEX Project delays / deferrals have led to missed opportunities Growth There are multiple areas where changes could improve future financial performance

  9. Introduction: Operational Performance – R&M Current and Planned R&M Improvement Initiatives Market Price Sales Revenue Clean fuels upgrade – in progress Mix + Volumes Bottom of Barrel Upgrade (conceptual stage) Direct Cost Refinery business improvement project (SGSI) Performance OPEX E&P oil winning projects (halt production decline) Profitability Cash Flow ROACE Other Infrastructure upgrade (planning stage) Sustaining CAPEX Growth Gasoline upgrade (implementation stage) A mixture of upgrades and operational changes to improve performance

  10. BUSINESS BACKGROUND – Driving Forces • Gasoline Optimisation Program • Equipment Integrity • No 1 CRU: 3 of 4 Rxs Changed – Expect 3 years Max • No 2 CRU: Remaining Life Estimated at 6 – 8 years • Sale of Unfinished Low Value Product • Reformer Feed • Low Octane Gasoline • VGO as FCCU Feed • Tighter Specifications • Elimination of Lead & MTBE– Octane & Volume Loss • Lower Benzene, Sulfur, Olefins and RVP • Increased Octane Demand • Shortfall of Premium Gasoline to some markets

  11. BUSINESS BACKGROUND – Driving Forces (Cont’d) • Tighter Diesel Specifications • Sulfur Reduction • Cetane Increase • Decrease in aromatics • Phase II - BOB Upgrade • High Fuel percent of Product Sales • Shrinking Fuel Oil Market

  12. BUSINESS BACKGROUND – Options • Discontinue Refining Operations • Huge economic impact on country and South in particular. • New refinery • Grassroots facility US$3-4 Bn • Upgrade Current refinery • Performance and Technology

  13. Scope Identified • Gasoline Optimisation Program • FCCU: Upgrade • Capacity from 26,000 BPSD to 35,000 BPSD • Product Octane from 81 MON to 83 MON • Pre-Fractionation • Remove Benzene from CRU feed • Provide feed for Isomerisation • Isomerisation • New 7,400 BPSD using C5/C6 Naphtha Feed • Improve Octane from 70 MON to 80 MON

  14. PROGRAM SCOPE (Cont’d) • CCRPlatformer • Replace Fixed Bed Platformers • Improve product Octane from 86 MON to 90 MON • Alkylation • New using C3/C4 ex FCCU • New Acid Regen Plant • Optimize LPG Production • Offsites & Utilities • New Boiler & Water Treating • Tanks, Transfer Systems • Power Supply • Control equipment • Flare System

  15. PROGRAM SCOPE (Cont’d) • New ULSD Hydrogenator • 35,000 BPSD unit • 8 – 9 point cetane lift • < 25% aromatics • 8 ppm S

  16. Economics & Approval • LP model Runs • Delta economics • Base case vs enhanced • Price/markets scenario forecast • Optimum configuration determined • Capex Estimates • Published/licensor data • Inflated for time/location/experience • Economics developed • Increased margin • DCFROR • NPV • Payback

  17. Economics & Approval • Income statement/Cash Flows generated • Sensitivity/ Risk Analyses developed • Approval Process • Executive management • Board • Shareholder - Cabinet

  18. CAPITAL EXPENDITURE • New Units ISBL 630 MM • OSBL, Project Mgmt Other 170 MM TOTAL (2006) 800 MM ORIGINAL ESTIMATE 650 MM (2005)

  19. PROGRAM BENEFITS • Gasoline Optimisation Program • Increase Gasoline Quantity • Total from 24% to 30% • Eliminate Unfinished Products (Naphtha & VGO) • Improve Gasoline Quality • Increase MON from 83 to 86 • Reduce Benzene from 1.6% to 0.7% • Reduce sulphur fron 41 ppm to 8 ppm • Customer Satisfaction • Lower Olefins in LPG • Ability to eliminate MTBE

  20. PROGRAM BENEFITS (Cont’d) • ULSD HTU • Improve Gas Oil Quality • Increase Pool Cetane • Reduce Aromatics/ Pool Sulfur • Improved Operations of the P-a-P Refinery • Energy Efficiency & Environmental Compliance • Increase full refining capacity to 168 MBPCD • Ability to process sour, low cetane crudes • Petrocaribe (New) • Products displaced from regional market • Improved Quality can be marketed elsewhere

  21. COUNTRY BENEFITS • Local Content:20% or US$ 160 million • Maximize local sub contractors • Offsite Works by Petrotrin • Construction Labor: 14million hours • Peak Site Labor: 2,800 • Corp Tax / UL: US$ 375 million • Sustained Operations of P-a-P Refinery • Security of Fuel Supply / Prices • Economic Activity

  22. PROJECT RISKS • Market / Product Pricing • Delay in Tighter Specs / Conservative Prices Used • Capital Cost Overrun • Scope of Work • EPC Contracts – Hybrid vs Lump Sum • Schedule Delays • Statutory Approval • Experienced EPC Contractors • Industrial relations problems • Skilled sub-contractor labour

  23. PROJECT RISKS • Technology: • Well Proven / State-of –the Art • Environmental: • No new type of effluent • Refinery systems (current and proposed) adequate • Funding: • Current Market Conditions Ideal for Loan

  24. Status • Pre Frac/Isomerization • EPC awarded • Piling commenced • Commercial production Dec 2007 • FCCU upgrade • Discussions on EPC award – Hybrid contract • Project completion date April 2008 • CCR Platformer • EPC Negotiations complete • ETC December 2008 • Alky / Acid • Hybrid contract • Lump sum for services • Re imbursable for Equipment/materials

  25. Status – Points to Note • Get Project Manager on board early. • Licensor estimates normally low. • Don’t forget infrastructure and services • Industry quite busy – Innovative bid requests required. • Fast track procurement on long lead items • Monitoring and control essential

  26. GAS OPT PROGRAM- FINANCING PLANMAJOR FINANCING OPTIONS Note: Fixed Rate funding with minimum 10 Year tenor and minimum 2 Year moratorium is preferred.

  27. FINANCING SCHEDULE

  28. Muchas Gracias